ABB Australia Pty Ltd v CH2M Hill Australia Pty Limited (No 2)

Link copied
Case Copied 36 min read

ABB Australia Pty Ltd v CH2M Hill Australia Pty Limited & Ors (No 2) [2017] NTSC 11

PARTIES:ABB Australia Pty Ltd

(ABN 68 003 337 611)

v

CH2M Hill Australia Pty Limited

(ABN 42 050 070 892)

and

UGL Engineering Pty Limited

(ABN 96 096 365 972)

and

KIRKPATRICK, Neil

TITLE OF COURT:  SUPREME COURT OF THE NORTHERN TERRITORY

JURISDICTION:  SUPREME COURT OF THE NORTHERN TERRITORY EXERCISING TERRITORY JURISDICTION

FILE NO:81 of 2016 (21635965)

DELIVERED:  14 FEBRUARY 2017

HEARING DATE:  6 FEBRUARY 2017

JUDGMENT OF:  KELLY J

CATCHWORDS:

BUILDING AND CONSTRUCTION – Building contracts – Payment claims

Building and construction – Building contracts – Adjudication process

STATUTES – Interpretation – (NT) Construction Contracts (Security of Payments) Act 2004 s 8 – Payment dispute – Determined by reference to terms of the contract between the parties

STATUTES – Interpretation – (NT) Construction Contracts (Security of Payments) Act 2004 s 48 – Review of adjudicator’s decision – Nature of review – Meaning of hearing de novo under s 60

Building and Construction Industry Security of Payment Act 1999 (NSW), s 13

Construction Contracts (Security of Payments) Act 2004 (NT), s 3(2)(b), s 8, s 10, s 28, s 28(1), s 28(1)(a), s 28(1)(d), s 28(2)(a), s 28(2)(b), s 28(2)(c), s 29, s 29(1), s 29(2)(a), s 29(2)(b), s 29(2)(c), s 33(1)(a), s 33(1)(a)(i), s 33(1)(a)(ii), s 33(1)(a)(iii), s 33(1)(a)(iv), s 33(1)(b), s 33(3), s 34, s 34(1), s 34(1)(a), s 34(2), s 34(2)(b), s 34(2)(c), s 34(3), s 34(5), s 46(7), s 46(8), s 48, s 48(1), s 48(2), s 60, s 62(1)(a), s 62(1)(c), s 62(3); Reg 6 and Reg 7

Local Court (Civil Procedure) Act 2015 (NT), s 18

AON Risk Services Australia Limited v Australian National University (2009) 239 CLR 175; Harris v Caladine (1991) 172 CLR 84; Ketteman & Ors v Hansel Properties Ltd & Ors [1987] 1 AC 189; Totev v Sfar and Another (2008) 167 FCR 193; Zdrilic v Hickie [2016] FCAFC 101, referred to

REPRESENTATION:

Counsel:

Applicant:A Wyvill SC

First and Second Respondents:     R Fenwick Elliott

Solicitors:

Applicant:DeSilva Hebron

First and Second Respondents:     Squire Patton Boggs (AU)

Judgment category classification:    C

Judgment ID Number:  KEL1703

Number of pages:  30

IN THE SUPREME COURT
OF THE NORTHERN TERRITORY
OF AUSTRALIA
AT DARWIN

ABB Australia Pty Ltd v CH2M Hill Australia Pty Limited & Ors (No 2) [2017] NTSC 11

No. 81 of 2016 (21635965)

BETWEEN:

ABB AUSTRALIA PTY LTD

(ABN 68 003 337 611)

Applicant

AND:

CH2M HILL AUSTRALIA PTY LIMITED

(ABN 42 050 070 892)

First Respondent

AND:

UGL ENGINEERING PTY LIMITED
  (ABN 96 096 365 972)
  Second Respondent

AND:

NEIL KIRKPATRICK
  Third Respondent

CORAM:     KELLY J

REASONS FOR ORDERS

(Delivered 14 February 2017)

Background

  1. On 17 July 2014, the first and second respondents, as joint venturers, and the applicant entered into a construction contract (“the Contract”) under which the applicant was to supply to the joint venture major equipment for the combined cycle power plant at the Ichthys Onshore…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read ABB Australia Pty Ltd v CH2M Hill Australia Pty Limited (No... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2017] NTSC 11
Decision Date

CaseChat Overview and Summary

The matter before the court involved a dispute between ABB Australia Pty Ltd and CH2M Hill Australia Pty Limited concerning a building contract. ABB, the contractor, served a payment claim under the contract for a substantial amount, which was subsequently partially accepted by the joint venture (JV), the principal. The dispute centred on whether the payment claim was valid under the contract and the Act, and whether the adjudication process was correctly applied. The court had to decide whether the adjudicator's decision to dismiss the application for adjudication was correct, particularly in relation to the timeliness of the application and the validity of the payment claims.

The primary legal issues in the case were whether the payment claims were valid under the terms of the contract and the Construction Contracts (Security of Payments) Act 2004 (NT). Specifically, the court needed to determine if the payment claims complied with the contractual requirements for timing and format, and if they were valid claims under the Act regardless of their compliance with the contract. Another significant issue was the adjudicator's interpretation of the timeliness of the adjudication application, which hinged on whether the payment dispute arose when the payment claim was initially rejected or when the substitute payment claim was served. The court also had to consider the scope of review of the adjudicator’s decision, particularly whether the review was de novo or limited to errors of law.

The court examined the adjudicator's decision and found that the adjudicator had correctly identified that the payment dispute arose when the initial payment claim was rejected. This meant that the adjudication application was not made within the required 90-day period, leading to the dismissal of the application. The court upheld the adjudicator's findings that both the initial and substitute payment claims, while not strictly compliant with the contractual terms, were valid under the Act. The court held that the adjudicator had the authority to treat non-compliant payment claims as valid for the purposes of the Act, and that the dismissal of the adjudication application was justified based on the timeliness issue. The court also noted that the review of the adjudicator's decision was limited and did not extend to re-evaluating the evidence or findings made by the adjudicator.

The court's final orders affirmed the adjudicator's decision to dismiss the adjudication application on the ground that it was not made within the required time frame. The court found no error in the adjudicator's interpretation of the Act and the contract, and thus upheld the dismissal of the application.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

ABB provided substitute security and on 7 March 2016, served on JV PC-009 Rev 2 claiming payment of $2,418,603.99 (plus GST). On 15 March 2016 JV issued a payment certificate under the Contract for $908,047.14 of that amount which it then set off against its claim for liquidated damages.[1]The adjudication application and decision On 10 June 2016 ABB made application under s 28 of the Construction Contracts (Security of Payments) Act 2004 (NT) (“the Act”) to have the payment dispute adjudicated (“Application 1”)[2] and the third respondent, Mr Neil Kirkpatrick, was appointed as the adjudicator. (The third respondent is referred to as “the Adjudicator”.) On 23 June 2016, JV delivered its response (“the Response”) in which it submitted that the Adjudicator should dismiss Application 1 under s 33(1)(a) of the Act relying on six different grounds. The grounds relied upon by JV did not include a contention that Application 1 had not been brought within time on the basis that a payment dispute had arisen on the rejection of PC-009 Rev 1 by the letter of 2 March 2016. On 4 July 2016, the Adjudicator sought further submissions in relation to two issues. The first issue related to a contention by the respondent that PC-009 Rev 2 was not a valid payment claim under the Contract. The second issue raised by the Adjudicator was whether PC-009 Rev 1 was a valid payment claim under the Contract and whether the letter of 2 March 2016 amounted to an agreement for the re-submission of a payment claim under the Contract that had already given rise to an entitlement to make an application for adjudication. On 5 July 2016 solicitors for both JV and ABB provided their submissions on the questions raised by the Adjudicator. On 11 July 2016, the Adjudicator dismissed Application 1 under s 33(1)(a) of the Act on the ground that the payment dispute had in fact arisen on 2 March 2016 and Application 1 had not been made within 90 days as required by s 28(1) (“the Adjudicator’s Decision”). The basis of the Adjudicator’s Decision was a finding by the Adjudicator that even though PC-009 Rev 1 was not a valid payment claim under the Contract, it was nevertheless a valid payment claim under the Act and that the letter of 2 March amounted to a rejection of that payment claim giving rise to a payment dispute within the meaning of the Act. The Adjudicator had earlier made the same finding in relation to PC-009 Rev 2. One of the jurisdictional grounds relied on by JV to assert that Application 1 should be dismissed under s 33(1)(a) was that PC-009 Rev 2 was not a valid payment claim as it was not submitted on the first business day of the month or within 30 days after completing a payment milestone as required by cl 12.1(a). The Adjudicator found that although it did not comply with the requirements of the Contract, PC-009 Rev 2 should nevertheless be treated as a valid payment claim for the purposes of the Act. He then determined that PC-009 Rev 1 suffered from the same defect but should be treated the same way – as a valid payment claim for the purposes of the Act. This proceeding

Ratio Decidendi

Legal Principle Established