ABB Australia Pty Ltd v CH2M Hill Australia Pty Limited & Ors (No 2) [2017] NTSC 11
PARTIES:ABB Australia Pty Ltd
(ABN 68 003 337 611)
v
CH2M Hill Australia Pty Limited
(ABN 42 050 070 892)
and
UGL Engineering Pty Limited
(ABN 96 096 365 972)
and
KIRKPATRICK, Neil
TITLE OF COURT: SUPREME COURT OF THE NORTHERN TERRITORY
JURISDICTION: SUPREME COURT OF THE NORTHERN TERRITORY EXERCISING TERRITORY JURISDICTION
FILE NO:81 of 2016 (21635965)
DELIVERED: 14 FEBRUARY 2017
HEARING DATE: 6 FEBRUARY 2017
JUDGMENT OF: KELLY J
CATCHWORDS:
BUILDING AND CONSTRUCTION – Building contracts – Payment claims
Building and construction – Building contracts – Adjudication process
STATUTES – Interpretation – (NT) Construction Contracts (Security of Payments) Act 2004 s 8 – Payment dispute – Determined by reference to terms of the contract between the parties
STATUTES – Interpretation – (NT) Construction Contracts (Security of Payments) Act 2004 s 48 – Review of adjudicator’s decision – Nature of review – Meaning of hearing de novo under s 60
Building and Construction Industry Security of Payment Act 1999 (NSW), s 13
Construction Contracts (Security of Payments) Act 2004 (NT), s 3(2)(b), s 8, s 10, s 28, s 28(1), s 28(1)(a), s 28(1)(d), s 28(2)(a), s 28(2)(b), s 28(2)(c), s 29, s 29(1), s 29(2)(a), s 29(2)(b), s 29(2)(c), s 33(1)(a), s 33(1)(a)(i), s 33(1)(a)(ii), s 33(1)(a)(iii), s 33(1)(a)(iv), s 33(1)(b), s 33(3), s 34, s 34(1), s 34(1)(a), s 34(2), s 34(2)(b), s 34(2)(c), s 34(3), s 34(5), s 46(7), s 46(8), s 48, s 48(1), s 48(2), s 60, s 62(1)(a), s 62(1)(c), s 62(3); Reg 6 and Reg 7
Local Court (Civil Procedure) Act 2015 (NT), s 18
AON Risk Services Australia Limited v Australian National University (2009) 239 CLR 175; Harris v Caladine (1991) 172 CLR 84; Ketteman & Ors v Hansel Properties Ltd & Ors [1987] 1 AC 189; Totev v Sfar and Another (2008) 167 FCR 193; Zdrilic v Hickie [2016] FCAFC 101, referred to
REPRESENTATION:
Counsel:
Applicant:A Wyvill SC
First and Second Respondents: R Fenwick Elliott
Solicitors:
Applicant:DeSilva Hebron
First and Second Respondents: Squire Patton Boggs (AU)
Judgment category classification: C
Judgment ID Number: KEL1703
Number of pages: 30
IN THE SUPREME COURT
OF THE NORTHERN TERRITORY
OF AUSTRALIA
AT DARWINABB Australia Pty Ltd v CH2M Hill Australia Pty Limited & Ors (No 2) [2017] NTSC 11
No. 81 of 2016 (21635965)
BETWEEN:
ABB AUSTRALIA PTY LTD
(ABN 68 003 337 611)
Applicant
AND:
CH2M HILL AUSTRALIA PTY LIMITED
(ABN 42 050 070 892)
First Respondent
AND:
UGL ENGINEERING PTY LIMITED
(ABN 96 096 365 972)
Second Respondent
AND:
NEIL KIRKPATRICK
Third Respondent
CORAM: KELLY J
REASONS FOR ORDERS
(Delivered 14 February 2017)
Background
On 17 July 2014, the first and second respondents, as joint venturers, and the applicant entered into a construction contract (“the Contract”) under which the applicant was to supply to the joint venture major equipment for the combined cycle power plant at the Ichthys Onshore…
Keep reading for free
Create a free CaseChat account to read ABB Australia Pty Ltd v CH2M Hill Australia Pty Limited (No... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] NTSC 11
- Decision Date
CaseChat Overview and Summary
The primary legal issues in the case were whether the payment claims were valid under the terms of the contract and the Construction Contracts (Security of Payments) Act 2004 (NT). Specifically, the court needed to determine if the payment claims complied with the contractual requirements for timing and format, and if they were valid claims under the Act regardless of their compliance with the contract. Another significant issue was the adjudicator's interpretation of the timeliness of the adjudication application, which hinged on whether the payment dispute arose when the payment claim was initially rejected or when the substitute payment claim was served. The court also had to consider the scope of review of the adjudicator’s decision, particularly whether the review was de novo or limited to errors of law.
The court examined the adjudicator's decision and found that the adjudicator had correctly identified that the payment dispute arose when the initial payment claim was rejected. This meant that the adjudication application was not made within the required 90-day period, leading to the dismissal of the application. The court upheld the adjudicator's findings that both the initial and substitute payment claims, while not strictly compliant with the contractual terms, were valid under the Act. The court held that the adjudicator had the authority to treat non-compliant payment claims as valid for the purposes of the Act, and that the dismissal of the adjudication application was justified based on the timeliness issue. The court also noted that the review of the adjudicator's decision was limited and did not extend to re-evaluating the evidence or findings made by the adjudicator.
The court's final orders affirmed the adjudicator's decision to dismiss the adjudication application on the ground that it was not made within the required time frame. The court found no error in the adjudicator's interpretation of the Act and the contract, and thus upheld the dismissal of the application.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi