ABB Australia Pty Ltd v CH2M Hill Australia Pty Limited

Link copied
Case Copied 25 min read

ABB Australia Pty Ltd v CH2M Hill Australia Pty Limited & Ors [2017] NTSC 1

PARTIES:ABB Australia Pty Ltd

(ABN 68 003 337 611)

v

CH2M Hill Australia Pty Limited

(ABN 42 050 070 892)

and

UGL Engineering Pty Limited

(ABN 96 096 365 972)

and

KIRKPATRICK, Neil

TITLE OF COURT:  SUPREME COURT OF THE NORTHERN TERRITORY

JURISDICTION:  SUPREME COURT OF THE NORTHERN TERRITORY EXERCISING TERRITORY JURISDICTION

FILE NO:81 of 2016 (21635965)

DELIVERED:  13 JANUARY 2017

HEARING DATES:  22 SEPTEMBER 2016

JUDGMENT OF:  KELLY J

CATCHWORDS:

Construction Contracts (Security of Payments) Act 2004 (NT) (“the Act”) s 48(1) – application under s 48(1) to set aside adjudicator’s determination under s 33(1)(a) to dismiss an application for adjudication without making a determination on the merits - by consent referred to the Supreme Court pursuant to s 18 of the Local Court (Civil Procedure) Act 2015 (NT)

Applicant sub-contractor served payment claim on respondent in respect of money said to be owing under a construction contract – applicant in breach of security requirement in the contract – respondent replied by letter requiring applicant to resubmit its payment claim for certification by respondent after provision of replacement security – applicant provided replacement security and resubmitted payment claim in identical terms – respondent replied certifying a lesser amount payable under the contract but claimed to set off that amount against liquidated damages – applicant applied for adjudication under s 28 of the Act – adjudicator appointed

Applicant and respondent both agreed that first payment claim not a valid payment claim under the contract - adjudicator held that though the first payment claim was not a valid payment claim under the contract it was a valid payment claim under the Act – therefore a payment dispute arose when respondent replied by letter requiring applicant to resubmit payment claim after provision of alternative security – adjudicator held application not made within 90 days after payment dispute arose – adjudicator dismissed claim under s 33(1)(a) without making a determination on the merits

Held first payment claim not a valid payment claim under the Act – validity of payment claim to be determined by reference to the contract - therefore letter requiring applicant to resubmit payment claim after provision of alternative security did not give rise to a payment dispute within the meaning of s 8 of the Act – therefore application not made more than 90 days after payment dispute arose - appeal allowed

Duties of adjudicator - adjudicator obliged to determine whether there is a “payment dispute” and, if so whether it arose not more than 90 days before the making of the application – this requires the adjudicator to look at the terms of the contract and consider whether what purports to be a payment claim is capable of giving rise to a liability on the part of the principal to pay – if not there is no “payment dispute” and the adjudicator is required by s 33(1)(a) to dismiss the application without a determination…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read ABB Australia Pty Ltd v CH2M Hill Australia Pty Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2017] NTSC 1
Decision Date

CaseChat Overview and Summary

In this case, ABB Australia Pty Ltd, a sub-contractor, served a payment claim on CH2M Hill Australia Pty Limited, a main contractor, in respect of money allegedly owed under a construction contract. ABB was in breach of a security requirement in the contract, prompting CH2M Hill to respond by requiring ABB to resubmit its payment claim after providing replacement security. ABB provided the replacement security and resubmitted the payment claim in identical terms. CH2M Hill certified a lesser amount payable under the contract but claimed to set off that amount against liquidated damages. ABB applied for adjudication under the Construction Contracts (Security of Payments) Act 2004 (NT) but the adjudicator dismissed the claim without making a determination on the merits. ABB sought to set aside the adjudicator's determination under section 48(1) of the Act, arguing that the first payment claim was valid, and the dispute arose when CH2M Hill required the resubmission of the payment claim after providing alternative security.

The court was required to determine whether the first payment claim was a valid payment claim under the Construction Contracts (Security of Payments) Act 2004 (NT) and whether the requirement for the resubmission of the payment claim after providing alternative security gave rise to a payment dispute. The court considered the duties of the adjudicator and whether the adjudicator was required to determine whether there was a “payment dispute” and, if so, whether it arose not more than 90 days before the making of the application. The court held that the validity of the payment claim was to be determined by reference to the contract, and as the first payment claim was not a valid payment claim under the contract, the letter requiring the resubmission of the payment claim after providing alternative security did not give rise to a payment dispute within the meaning of the Act. The court held that the application was not made more than 90 days after the payment dispute arose, and the appeal was allowed.

The court found that the adjudicator was obliged to determine whether there was a “payment dispute” and, if so, whether it arose not more than 90 days before the making of the application. The court held that the adjudicator was required to look at the terms of the contract and consider whether what purports to be a payment claim is capable of giving rise to a liability on the part of the principal to pay. If not, there is no “payment dispute” and the adjudicator is required by section 33(1)(a) to dismiss the application without a determination on the merits. The court held that the adjudicator had erred in law by failing to consider whether the first payment claim was a valid payment claim under the contract and whether the requirement for the resubmission of the payment claim after providing alternative security gave rise to a payment dispute.

The final orders were that the appeal was allowed, the adjudicator’s determination under section 33(1)(a) to dismiss Application 1 without making a determination on the merits was set aside, and Application 1 was referred back to the third respondent to be determined under section 33(1)(b). The applicant was to bear the costs of the appeal.

Background

Background to the litigation

The applicant has applied under s 48(1) of the Act to set aside the adjudicator’s determination under s 33(1)(a) to dismiss Application 1 without making a determination on the merits and is seeking an order under s 48(2) of the Act referring Application 1 back to the third respondent to be determined under s 33(1)(b). By consent the matter was referred to the Supreme Court pursuant to s 18 of the Local Court (Civil Procedure) Act 2015 (NT) and listed before me. The Facts On 19 February 2016 the applicant sent the respondent a payment claim, PC-009 Rev 1, dated 19 February 2016 claiming payment of $2,418,603.99. By letter dated 2 March 2016, the respondent advised the applicant that the applicant was in breach of the security requirement in cl 14 of the Contract and as a result had not met a condition precedent to the right to deliver a payment claim under cl 12 of the Contract. The letter advised that “(f)ollowing replacement of the Security, (the applicant) is required to resubmit its payment claim for certification by (the respondent) in accordance with Contract clause 12”. The applicant provided the security required under cl 14 of the Contract and on 7 March 2016 sent a payment claim, PC-009 Rev 2, dated 7 March 2016, to the respondent. Apart from the change of date, PC-009 Rev 2 was in the same terms as PC-009 Rev 1. On 15 March 2016, the respondent responded certifying that of the amount of $2,418,603.99 claimed, $908,047.14 was payable under the Contract, but claiming to set off the whole of that amount against liquidated damages said to be owing by the applicant to the respondent. On that basis, the respondent advised that it would not be making any payment on PC-009 Rev 2. On 10 June 2016, the applicant made Application 1 and the third respondent was appointed as adjudicator. On 23 June 2016, the respondent delivered its response (“the Response”) in which it submitted that the adjudicator should dismiss the application under s 33(1)(a) relying on a number of not presently relevant grounds. The grounds relied upon by the respondent did not include a contention that the Application had not been brought within time on the basis that a payment dispute had arisen on the rejection of PC-009 Rev 1 by the letter of 2 March 2016. On 4 July 2016, the adjudicator sought further submissions in relation to two issues. The first issue was a contention by the respondent that PC-009 Rev 2 was not a valid payment claim under the Contract and is not presently relevant. The second issue raised by the adjudicator was this. I request the parties provide me with submissions on the following:(a)whether the purported payment claim reference PC-009 Rev 1, as referred to by the Applicant, was a valid payment claim for the purposes of the Construction Contracts (Security of Payment) (sic) Act; and(b)whether the Respondents (sic) letter [of 2 March 2016] provides for an agreement between the parties for the re-submission of a payment claim under the contract that has subsequently given rise to an entitlement to make an application for adjudication under the Construction Contracts (Security of Payment) (sic) Act.

Decision

Reasons for decision

Ratio Decidendi

Legal principle established