ABB Australia Pty Ltd v CH2M Hill Australia Pty Limited & Ors [2017] NTSC 1
PARTIES:ABB Australia Pty Ltd
(ABN 68 003 337 611)
v
CH2M Hill Australia Pty Limited
(ABN 42 050 070 892)
and
UGL Engineering Pty Limited
(ABN 96 096 365 972)
and
KIRKPATRICK, Neil
TITLE OF COURT: SUPREME COURT OF THE NORTHERN TERRITORY
JURISDICTION: SUPREME COURT OF THE NORTHERN TERRITORY EXERCISING TERRITORY JURISDICTION
FILE NO:81 of 2016 (21635965)
DELIVERED: 13 JANUARY 2017
HEARING DATES: 22 SEPTEMBER 2016
JUDGMENT OF: KELLY J
CATCHWORDS:
Construction Contracts (Security of Payments) Act 2004 (NT) (“the Act”) s 48(1) – application under s 48(1) to set aside adjudicator’s determination under s 33(1)(a) to dismiss an application for adjudication without making a determination on the merits - by consent referred to the Supreme Court pursuant to s 18 of the Local Court (Civil Procedure) Act 2015 (NT)
Applicant sub-contractor served payment claim on respondent in respect of money said to be owing under a construction contract – applicant in breach of security requirement in the contract – respondent replied by letter requiring applicant to resubmit its payment claim for certification by respondent after provision of replacement security – applicant provided replacement security and resubmitted payment claim in identical terms – respondent replied certifying a lesser amount payable under the contract but claimed to set off that amount against liquidated damages – applicant applied for adjudication under s 28 of the Act – adjudicator appointed
Applicant and respondent both agreed that first payment claim not a valid payment claim under the contract - adjudicator held that though the first payment claim was not a valid payment claim under the contract it was a valid payment claim under the Act – therefore a payment dispute arose when respondent replied by letter requiring applicant to resubmit payment claim after provision of alternative security – adjudicator held application not made within 90 days after payment dispute arose – adjudicator dismissed claim under s 33(1)(a) without making a determination on the merits
Held first payment claim not a valid payment claim under the Act – validity of payment claim to be determined by reference to the contract - therefore letter requiring applicant to resubmit payment claim after provision of alternative security did not give rise to a payment dispute within the meaning of s 8 of the Act – therefore application not made more than 90 days after payment dispute arose - appeal allowed
Duties of adjudicator - adjudicator obliged to determine whether there is a “payment dispute” and, if so whether it arose not more than 90 days before the making of the application – this requires the adjudicator to look at the terms of the contract and consider whether what purports to be a payment claim is capable of giving rise to a liability on the part of the principal to pay – if not there is no “payment dispute” and the adjudicator is required by s 33(1)(a) to dismiss the application without a determination…
Keep reading for free
Create a free CaseChat account to read ABB Australia Pty Ltd v CH2M Hill Australia Pty Limited and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2017] NTSC 1
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether the first payment claim was a valid payment claim under the Construction Contracts (Security of Payments) Act 2004 (NT) and whether the requirement for the resubmission of the payment claim after providing alternative security gave rise to a payment dispute. The court considered the duties of the adjudicator and whether the adjudicator was required to determine whether there was a “payment dispute” and, if so, whether it arose not more than 90 days before the making of the application. The court held that the validity of the payment claim was to be determined by reference to the contract, and as the first payment claim was not a valid payment claim under the contract, the letter requiring the resubmission of the payment claim after providing alternative security did not give rise to a payment dispute within the meaning of the Act. The court held that the application was not made more than 90 days after the payment dispute arose, and the appeal was allowed.
The court found that the adjudicator was obliged to determine whether there was a “payment dispute” and, if so, whether it arose not more than 90 days before the making of the application. The court held that the adjudicator was required to look at the terms of the contract and consider whether what purports to be a payment claim is capable of giving rise to a liability on the part of the principal to pay. If not, there is no “payment dispute” and the adjudicator is required by section 33(1)(a) to dismiss the application without a determination on the merits. The court held that the adjudicator had erred in law by failing to consider whether the first payment claim was a valid payment claim under the contract and whether the requirement for the resubmission of the payment claim after providing alternative security gave rise to a payment dispute.
The final orders were that the appeal was allowed, the adjudicator’s determination under section 33(1)(a) to dismiss Application 1 without making a determination on the merits was set aside, and Application 1 was referred back to the third respondent to be determined under section 33(1)(b). The applicant was to bear the costs of the appeal.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi