Medium Neutral Citation: AAP Industries Pty Ltd v Rehau Pte Ltd (No. 2) [2017] NSWSC 1136 Hearing dates: 23 August 2017 Date of orders: 31 August 2017 Decision date: 31 August 2017 Jurisdiction: Common Law Before: Davies J Decision: (1) Judgment for the Plaintiff in the sum of $240,166.
(2) The Defendant is to pay the Plaintiff’s costs.Catchwords: CONTRACT – damages – contract for the supply of plumbing articles – defendant liable for breach of supply agreement – parties agreed on loss of profits and loss in respect of completed stock – loss in respect of raw materials in issue – whether cost of mitigation of damages is recoverable – date at which damages should be assessed
COSTS – whether costs should be awarded other than on the ordinary basis – Calderbank offer made by defendant – conditions attached to offer - plaintiff not unreasonable in rejecting offer – whether order under r 42.34 UCPR should be made – defendant is a foreign corporation – contractual term involving foreign jurisdiction - proceedings appropriately commenced in Supreme Court – proceedings thereafter appropriately continued in Supreme Court – whether s 60 Civil Procedure Act applies to costs orders - plaintiff’s conduct in the proceedings did not give rise to any issues of proportionalityLegislation Cited: Civil Procedure Act 2005 (NSW)
Supreme Court Rules 1970 (NSW)
Uniform Civil Procedure Rules 2005 (NSW)Cases Cited: AAP Industries Pty Limited v Rehau Pte Limited [2015] NSWSC 468
AAP Industries Pty Ltd v Rehau Pte Ltd [2017] NSWSC 390
Colonial Ammunition Co v Reid (1900) 21 NSWR 338
Falkner v Bourke (1990) 19 NSWLR 574
Haines v Bendall (1991) 172 CLR 60
Hammond & Co v Bussey (1887) 20 QBD 79
Jones v Krawczyk (No. 2) [2011] NSWSC 352
Jones v Sutton [No. 2] [2005] NSWCA 203
M.B.P (S.A) Pty Ltd v Gogic (1991) 171 CLR 657
McLaughlin v Dungowan Manly Pty Limited [2010] NSWSC 306
Milich v The Council of the City of Canterbury (No. 3) [2012] NSWSC 1280
Perri v Flavell (No 2) (Court of Appeal, 20 Sep 1995, Unrep)
Priestley v Priestley (No 2) [2016] NSWSC 1259
Sabah Yazgi v Permanent Custodians Limited (No 2) [2007] NSWCA 306
Sheahan v Stockman (1922) 22 SR (NSW) 415
State of New South Wales v Quirk [2012] NSWCA 216
Whitehouse Hotels Pty Ltd v Lido Savoy Pty Ltd (1975) 49 ALJR 93Category: Procedural and other rulings Parties: AAP Industries Pty Ltd (Plaintiff)
Rehau Pte Ltd (Defendant)Representation: Counsel:
Solicitors:
M Zammit (Plaintiff)
M J Heath (Defendant)
W H Lawyers (Plaintiff)
Matthews Folbigg Lawyers - as agents for O’Loughlins Lawyers (Defendant)
File Number(s): 2014/365787
Judgment
-
I gave judgment in relation to the liability issue in this matter on 21 April 2017: AAP Industries Pty Ltd v Rehau Pte Ltd [2017] NSWSC 390. I found that properly construed the Supply Agreement required exclusive dealing so that Rehau was obliged to order the items contained in the Supply Agreement from AAP…
Keep reading for free
Create a free CaseChat account to read AAP Industries Pty Ltd v Rehau Pte Ltd (No. 2) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] NSWSC 1136
- Decision Date
CaseChat Overview and Summary
The court had to resolve several legal issues, including whether the cost of mitigating damages was recoverable under the contract and the appropriate date for assessing those damages. Additionally, the court needed to decide whether costs should be awarded on a basis other than the ordinary one, considering a Calderbank offer made by Rehau Pte Ltd with attached conditions. The court also had to consider whether an order under rule 42.34 of the Uniform Civil Procedure Rules should be made and whether section 60 of the Civil Procedure Act applied to the costs orders.
The Supreme Court found that the cost of mitigating damages was recoverable. The court reasoned that AAP Industries was not unreasonable in rejecting Rehau Pte Ltd's Calderbank offer due to the attached conditions. The court determined that an order under rule 42.34 UCPR should be made, as AAP Industries' conduct in the proceedings did not give rise to any issues of proportionality. The court also concluded that section 60 of the Civil Procedure Act did not apply to the costs orders. Consequently, AAP Industries was awarded costs on a basis other than the ordinary one.
Background
Background to the litigation
The matter came before the Supreme Court of New South Wales in AAP Industries Pty Ltd v Rehau Pte Ltd (No. 2). The court had previously dealt with issues arising from the same contract in an earlier proceeding, AAP Industries Pty Ltd v Rehau Pte Ltd (No. 1). In the current proceeding, the focus was on the calculation of damages. The case involved a trial to determine the appropriate amount of damages. Rehau made a Calderbank offer to settle the case under certain conditions, which AAP rejected. The procedural history included the submission of evidence, expert testimonies, and arguments from both parties regarding the appropriate method of calculating damages, particularly concerning the costs of raw materials and mitigation.
Decision
Reasons for decision
1. Whether the cost of mitigation of damages is recoverable in this case.
2. At what date should the damages be assessed?
3. Whether costs should be awarded other than on the ordinary basis, considering the Calderbank offer made by Rehau and its conditions.
4. Whether an order under r 42.34 UCPR should be made, given Rehau's conduct and the rejection of its Calderbank offer.
5. Whether s 60 of the Civil Procedure Act applies to the costs orders in this case.
Held
1. The court held that the cost of mitigation of damages was recoverable in this case. The cost of purchasing raw materials to replace the lost stock was necessary to mitigate the loss and, therefore, recoverable as part of the damages.
2. The court determined that the damages should be assessed at the date of the contract breach. The damages should reflect the loss of profits and loss in respect of the completed stock as of the date when the contract was breached.
3. The court ruled that costs should not be awarded other than on the ordinary basis. The plaintiff was not unreasonable in rejecting the Calderbank offer due to the conditions attached to it, which made the offer not genuinely advantageous.
4. The court declined to make an order under r 42.34 UCPR, given Rehau's conduct and the rejection of its Calderbank offer. The court found that the proceedings were appropriately commenced and continued in the Supreme Court.
5. The court concluded that s 60 of the Civil Procedure Act did not apply to the costs orders in this case. The plaintiff's conduct in the proceedings did not give rise to any issues of proportionality that would warrant a departure from the usual costs order.
Ratio Decidendi
Legal Principle Established
The court commenced by addressing the recoverability of the cost of mitigation of damages. It held that when a party incurs costs to mitigate their losses after a breach of contract, these costs are recoverable as part of the damages. This aligns with established principles where mitigation expenses are considered necessary to reduce the extent of loss. The court found that the cost of purchasing raw materials to replace the lost stock was necessary and, therefore, recoverable.
Next, the court assessed the appropriate date for damages. It established that damages should be assessed as of the date of the breach of contract to accurately reflect the loss of profits and the loss in respect of the completed stock at that time. This approach ensures that the damages compensate for the actual losses suffered as a result of the breach.
The court then considered the issue of costs, particularly in relation to the Calderbank offer made by Rehau. The offer was conditioned upon the plaintiff withdrawing its claim for aggravated damages and discontinuing its appeal, which the plaintiff found unreasonable. The court held that the plaintiff was not unreasonable in rejecting the offer and thus ruled that costs should not be awarded other than on the ordinary basis. This decision underscores the importance of genuine offers in litigation settlements and the court's stance on rejecting unreasonable offers.
In relation to the order under r 42.34 UCPR, the court noted Rehau's conduct and the rejection of its Calderbank offer. The court found that the proceedings were appropriately commenced and continued in the Supreme Court due to the involvement of a foreign corporation and a contractual term involving foreign jurisdiction. The court declined to make an order under r 42.34 UCPR, reflecting its view that the proceedings' progression was appropriate and justified.
Finally, the court examined whether s 60 of the Civil Procedure Act applied to the costs orders. It found that the plaintiff's conduct in the proceedings did not give rise to any issues of proportionality that would warrant a departure from the usual costs order. This determination reinforces the principle that proportionality in costs orders is assessed based on the conduct of the parties involved in the litigation.
The ratio decidendi of this decision is that the cost of mitigation of damages is recoverable in contract disputes, damages should be assessed as of the date of the breach, and the court's discretion in awarding costs should be exercised considering the reasonableness of settlement offers and the appropriateness of the proceedings' progression in the relevant court.