| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMERCIAL AND EQUITY DIVISION
BUILDING CASES LIST
No. 9671 of 2005
| 620 COLLINS STREET PTY LTD and ORS | Plaintiff |
| v | |
| ABIGROUP CONTRACTORS PTY LTD and ANOR (No. 1) | Defendant |
---
JUDGE: | OSBORN J | |
WHERE HELD: | MELBOURNE | |
DATE OF HEARING: | 31 AUGUST, 1 SEPTEMBER 2006 | |
DATE OF JUDGMENT: | 14 DECEMBER 2006 | |
CASE MAY BE CITED AS: | 620 COLLINS STREET PTY LTD v ABIGROUP CONTRACTORS PTY LTD (No. 1) | |
MEDIUM NEUTRAL CITATION: | [2006] VSC 490 | |
---
Commercial arbitration – allegation of technical misconduct – building dispute – delay by arbitrator – alleged failure to deal with submissions worthy of serious consideration – baseline program for assessment of delay – evidence of delay – alleged making of findings not pleaded or contended for – separable portions – extension of time – section 42 Commercial Arbitration Act 1984 (Vic).
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Mr B. Martin QC with Mr F.J. Tiernan | DLA Phillips Fox |
| For the Defendant | Mr P.W. Almond QC with Mr M.G. Roberts and Ms P. Neskovcin | Deacons |
HIS HONOUR:
Introduction
This is an application to set aside the award of an arbitrator on grounds of misconduct pursuant to s.42 of the Commercial Arbitration Act 1984 ("the Act").
In August 2001 620 Collins Street Pty Ltd ("620") and Abigroup Contractors Pty Ltd ("Abigroup") entered into a building contract ("the contract") pursuant to which Abigroup agreed to design and construct Liberty Tower. The tower comprised a 27 level residential building with retail street frontage and associated car parking on the corner of Spencer and Collins Street, Melbourne. The initial contract price was $46,144,080 plus GST and subject to adjustments.
The contract followed design development work undertaken by Abigroup over the previous year for the purpose of obtaining a building permit.
The contract was an amended form of Australian Standard general conditions of contract for design and construct AS4300, itself similar to the well known AS2124 general conditions of contract.
The contract provided for two separable portions of works. Separable portion 1 (SP1) comprised the ground floor retail, part of level 1, the car park to level 18 inclusive and relevant plant room areas. Separable portion 2 (SP2) comprised the balance of level 1, levels 19-27 and the balance of the building.
The original dates of practical completion were 1 April 2002 for SP1 and 9 August 2002 for SP2. The contract also stipulated a rate of liquidated damages, bonus payments for early practical completion, and the rate of delay costs applicable to certain classes of delay events. Both liquidated damages and bonus payments were capped at $1.8 million.
The construction of the works gave rise to a series of disputes between 620 and Abigroup arising in circumstances which the Arbitrator summarised as follows:
"10.Whilst the Building Contract was entered into on about 24 August 2001, Abigroup actually established on site on about 15 September 2000. Apparently it was originally intended that Abigroup would undertake the demolition work, however, this work…
Keep reading for free
Create a free CaseChat account to read 620 Collins Street Pty Ltd v Abigroup Contractors Pty Ltd (N... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2006] VSC 490
- Decision Date
CaseChat Overview and Summary
The court had to decide whether the alleged misconduct by the arbitrator was sufficient to justify setting aside the arbitration award. Issues included whether the arbitrator delayed unreasonably, failed to address submissions, made findings outside the scope of the pleadings, and whether these actions amounted to serious misconduct. The court also considered the implications of the alleged misconduct on the fairness and integrity of the arbitration process.
The court held that the alleged misconduct by the arbitrator did not reach the threshold of serious misconduct. The delays were not unreasonable, the arbitrator had addressed all significant submissions, and the findings made, while perhaps not ideal, did not prejudice the outcome. The court found that the arbitration process, despite its imperfections, was fundamentally fair and did not warrant setting aside the award. The court concluded that the alleged misconduct did not undermine the validity of the arbitration process to the extent required by statute.
As a result, the Supreme Court dismissed the application by 620 Collins Street to set aside the arbitration award. The award stood, and the parties were bound by its terms.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi