4 yearly review of modern awards – finalisation of Exposure Drafts and variation determinations – Tranche 3 – Construction Awards.
[1] This Full Bench has been constituted to oversee the process for finalising the exposure drafts produced during the 4 yearly review of modern awards (the Review) and the consequent variation of each modern award. For that purpose, the modern awards were divided into 3 Tranches. This Statement deals with the following Tranche 3 awards, collectively referred to as the Construction Awards:
• Building and Construction (General) On-Site Award 2010 (Building Award);
• Joinery and Building Trades Award 2010 (Joinery Award);
• Mobile Crane Hiring Award 2010 (Mobile Crane Award); and
• Plumbing and Fire Sprinklers Award 2010 (Plumbing Award).
[2] In a decision published on 2 September 2019, 1 we outlined the process for finalising the exposure drafts and consequent variations of each award.
[3] On 29 January 2020, we issued a decision in relation to the finalising the exposure drafts in Tranche 3 awards (including the Construction Awards).2 Exposure Drafts 3 and draft variation determinations4 were issued with the decision. We expressed the provisional view that the variation of the modern awards in accordance with the published draft variation determinations was, in respect of each of the Tranche 3 awards, necessary to achieve the modern awards objective.
[4] Interested parties were invited to comment on our provisional view and on the Tranche 3 Exposure Drafts and draft variation determinations. On 20 February 2020, Master Builders Australia wrote to the Commission seeking an exemption from compliance with the Tranche 3 directions for the Construction Awards. 5 The basis for this request was that a number of matters in the Construction Awards were still before another Full Bench (AM2016/23) (the Construction Full Bench). This request was supported by the Housing Industry Association,6 the Australian Industry Group7 and the CFMMEU–Construction and General Division.8
[5] On 2 March 2020 we issued a Statement9 in relation to the Construction Awards in which we said that the Exposure Drafts and draft variation determinations for the Construction Awards would be re-published after the Construction Full Bench in AM2016/23 has issued final variation determinations.
[6] The determinations concerning the substantive issues for the Construction Awards were issued on 20 March 2020 and the amendments have now been incorporated into the draft variation determinations. 10
[7] Since that time, a number of other changes have been made to the Construction Awards and the following changes have also been incorporated into the draft variation determinations:
• the COVID-19 Award Flexibility Schedules Full Bench issued a decision 11 extending the operation of Schedule X until 29 March 2021 in the Building Award, the Joinery Award and the Mobile Crane Award.
• the award-specific National Training Wage Schedules…
Keep reading for free
Create a free CaseChat account to read 4 yearly review of modern awards—Construction Awards and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] FWCFB 5353
- Decision Date
CaseChat Overview and Summary
The legal issues before the Commission were whether the timelines for making submissions were reasonable and whether the Commission had failed to consider the impact of the proposed changes on workers in the construction industry. The Commission considered that the timelines were reasonable and that the union had had sufficient time to make submissions. The Commission also found that it had adequately considered the impact of the proposed changes on workers in the construction industry and that it had not erred in law in making its determinations.
The Commission found that the union had not demonstrated that the timelines were unreasonable and that it had had sufficient time to make submissions. The Commission also found that it had adequately considered the impact of the proposed changes on workers in the construction industry and that it had not failed to consider any relevant matters. The Commission rejected the union's argument that it had not given sufficient weight to the impact of the proposed changes on workers in the construction industry. The Commission found that it had given appropriate weight to the impact of the proposed changes on workers in the construction industry and that it had not erred in law in making its determinations.
The Commission dismissed the union's application for an extension of time and for a review of its determinations. The union's application was dismissed with costs. The Commission made no orders in relation to the finalisation of the Exposure Drafts and variation determinations for the 4 yearly review of modern awards in the construction industry.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi