Renewable Energy (Electricity) Amendment Act 2009
No. 78, 2009
An Act to amend the Renewable Energy (Electricity) Act 2000, and for related purposes
Contents
1 Short title
2 Commencement
3 Schedule(s)
Schedule 1—Amendment of the Renewable Energy (Electricity) Act 2000
Schedule 2—Partial exemptions from liability to charge
Renewable Energy (Electricity) Act 2000
Schedule 3—Amendments relating to the transition of State renewable energy target schemes
Part 1—Amendments relating to constitutional corporations
Renewable Energy (Electricity) Act 2000
Part 2—Transitional provisions
Renewable Energy (Electricity) Amendment Act 2009
No. 78, 2009
An Act to amend the Renewable Energy (Electricity) Act 2000, and for related purposes
[Assented to 7 September 2009]
The Parliament of Australia enacts:
1 Short title
This Act may be cited as the Renewable Energy (Electricity) Amendment Act 2009.
2 Commencement
(1) Each provision of this Act specified in column 1 of the table commences, or is taken to have commenced, in accordance with column 2 of the table. Any other statement in column 2 has effect according to its terms.
Commencement information |
Column 1 | Column 2 | Column 3 |
Provision(s) | Commencement | Date/Details |
1. Sections 1 to 3 and anything in this Act not elsewhere covered by this table | The day on which this Act receives the Royal Assent. | 7 September 2009 |
2. Schedule 1 | The day on which this Act receives the Royal Assent. | 7 September 2009 |
3. Schedule 2 | At the same time as the provision(s) covered by table item 2. | 7 September 2009 |
4. Schedule 3, Part 1 | A single day to be fixed by Proclamation. However, if the provision(s) do not commence before 1 July 2011, they commence on that day. | 1 July 2011 |
5. Schedule 3, item 3 | The day after this Act receives the Royal Assent. | 8 September 2009 |
6. Schedule 3, item 4 | 1 February 2010. | 1 February 2010 |
7. Schedule 3, item 5 | The day after this Act receives the Royal Assent. | 8 September 2009 |
8. Schedule 3, items 6 and 7 | A single day to be fixed by Proclamation. However, if any of the provision(s) do not commence within the period of 9 months beginning on the day on which this Act receives the Royal Assent, they commence on the first day after the end of that period. | 18 April 2010 (see F2010L00946) |
9. Schedule 3, items 8 and 9 | 1 February 2010. | 1 February 2010 |
Note: This table relates only to the provisions of this Act as originally passed by both Houses of the Parliament and assented to. It will not be expanded to deal with provisions inserted in this Act after assent.
(2) Column 3 of the table contains additional information that is not part of this Act. Information in this column may be added to or edited in any published version of this Act.
3 Schedule(s)
Each Act that is specified in a Schedule to this Act is amended or repealed as set out in the applicable items in the Schedule concerned, and any other…
Overview
The Renewable Energy (Electricity) Amendment Act 2009 (Cth) was enacted by the Parliament of Australia to amend the Renewable Energy (Electricity) Act 2000 (Cth) and address the growing need for increased renewable energy production and integration within the electricity sector, as well as the introduction of waste coal mine gas as a new eligible energy source. This amendment aimed to enhance the renewable energy target, expand the range of eligible energy sources, and provide a mechanism for varying the 2008 waste coal mine gas limits for accredited power stations. Additionally, the Act introduced partial exemptions from the liability to charge for liable entities engaged in emissions-intensive trade-exposed activities. The policy objective of the Renewable Energy (Electricity) Amendment Act 2009 was to further Australia's commitment to reducing greenhouse gas emissions, promoting the use of renewable energy sources, and supporting the transition to a more sustainable and low-carbon electricity sector.
Scope and Application
The Renewable Energy (Electricity) Amendment Act 2009 amends the Renewable Energy (Electricity) Act 2000 and applies to constitutional corporations, which are defined as corporations to which paragraph 51(xx) of the Constitution applies. This Act operates on a national level within Australia, and constitutional corporations are immune from any state laws that substantially correspond to this Act. The provisions of the Act commence on various dates, with some sections coming into effect upon Royal Assent on 7 September 2009, while others have specific commencement dates or are subject to a proclamation. The Act extends its application through subordinate instruments, such as regulations, which may provide for varying 2008 Waste Coal Mine Gas (WCMG) limits, among other provisions. The Act introduces the concept of "eligible WCMG," which is waste coal mine gas used in electricity generation from 1 July 2011 to 31 December 2020 under specific conditions. Additionally, the Act includes provisions for partial exemptions from liability to charge for emissions-intensive trade-exposed activities, which can reduce the renewable energy shortfall charge otherwise payable. Transitional regulations may be made to facilitate the transition from state renewable energy target schemes to the Commonwealth's scheme.
Key Provisions
- The Renewable Energy (Electricity) Amendment Act 2009 (C2009A00078) amends the Renewable Energy (Electricity) Act 2000 (the principal Act) in several significant ways. Firstly, it modifies the scope and objectives of the principal Act. Section 3(b) now specifically aims to reduce greenhouse gas emissions within the electricity sector, rather than more broadly. The target date for achieving the renewable energy objective is extended from 2020 to 2030 (section 4). Additionally, the Act introduces the concept of "eligible WCMG" (Waste Coal Mine Gas) as a form of eligible energy, with specific eligibility criteria and limits (sections 17A, 30G).
- The Act imposes several obligations on parties governed by it. Accredited power stations must adhere to the newly introduced 2008 WCMG limit and can have this limit varied by the Regulator under certain conditions (section 30G). The Regulator is mandated to decide on applications listing eligible WCMG as an eligible energy source by 31 December 2010, with automatic refusal if not decided by then (subsection 15A(3)). Additionally, the Minister is required to commission an independent review of the operation of the Act and related regulations by 31 December 2013, with the review report to be tabled in Parliament (section 162).
- The Act also introduces several offences and penalties for breaches. The most notable is the failure to comply with record-keeping obligations under section 160, which is an offence carrying a penalty of 30 penalty units (subsection 160(7)). Furthermore, the Act includes provisions for the conversion of State certificates to renewable energy certificates, with specific timelines and conditions for such conversions (Schedule 3, Part 2, item 6). Non-compliance with these provisions, such as creating a renewable energy certificate when a State certificate has already been created, is prohibited and can result in legal repercussions (item 8).
- Additionally, the Act includes transitional provisions to manage the shift from state-based renewable energy schemes to the Commonwealth scheme, ensuring continuity for existing accredited power stations and their operators (Schedule 3, Part 2, items 4 and 5). The Commonwealth Regulator is granted immunity from state laws that substantially correspond to the provisions of this Act, particularly in relation to constitutional corporations (Schedule 3, Part 1, item 7C).
- Area of Law
- Environmental Law
- Instrument
- Amending Act
- Concepts
- Commencement Provisions
- Repeal & Amendment
- Transitional Provisions
- Regulatory Standards
- Licensing & Registration
- Enforcement Powers