Transfield Shipping Inc v Mercator Shipping Inc (The Achilleas)

Link copied
Case Copied 67 min read
HOUSE OF LORDS SESSION 2007–08
[2008] UKHL 48

on appeal from: [2007] EWCA Civ 901

OPINIONS

OF THE LORDS OF APPEAL

FOR JUDGMENT IN THE CAUSE

Transfield Shipping Inc (Appellants) v Mercator Shipping Inc (Respondents)

Appellate Committee

Lord Hoffmann


Lord Hope of Craighead
Lord Rodger of Earlsferry
Lord Walker of Gestingthorpe
Baroness Hale of Richmond

Counsel

Appellant:  Respondent:
Dominic Kendrick QC Simon Croall QC
Benjamin Parker Ruth Hosking
(Instructed by Swinnerton Moore LLP) (Instructed by Bentleys Stokes & Lowless)

Hearing date: 1 MAY 2008

ON
WEDNESDAY 9 JULY 2008

HOUSE OF LORDS

OPINIONS OF THE LORDS OF APPEAL FOR JUDGMENT

IN THE CAUSE

Transfield Shipping Inc (Appellants) v Mercator Shipping Inc

(Respondents)

[2008] UKHL 48

LORD HOFFMANN

My Lords,

1. The Achilleas is a single-decker bulk carrier of some 69,000 dwt built in 1994. By a time charter dated 22 January 2003 the owners let her to the charterers for about five to seven months at a daily hire rate of US$13,500. By an addendum dated 12 September 2003 the parties fixed the vessel for a further five to seven months at a daily rate of US$16,750. The latest date for redelivery was 2 May 2004.

2. By April 2004, market rates had more than doubled compared with the previous September. On 20 April 2004 the charterers gave notice of redelivery between 30 April and 2 May 2004. On the following day, the owners fixed the vessel for a new four to six month hire to another charterer, following on from the current charter, at a daily rate of US$39,500. The latest date for delivery to the new charterers, after which they were entitled to cancel, was 8 May 2004.

3. With less than a fortnight of the charter to run, the charterers fixed the vessel under a subcharter to carry coals from Quingdao in China across the Yellow Sea to discharge at two Japanese ports, Tobata and Oita. If this voyage could not reasonably have been expected to allow redelivery by 2 May 2004, the owners could probably have refused to perform it: see Torvald Klaveness A/S v Arni Maritime Corpn (The Gregos) [1995] 1 Lloyd’s Rep 1. But they made no objection. The vessel completed loading at Quingdao on 24 April. It discharged at Tobata, went on to Oita, but was unfortunately delayed there and not redelivered to the owners until 11 May.

4. By 5 May it had become clear to everyone that the vessel would not be available to the new charterers before the cancelling date of 8 May. By that time, rates had fallen again. In return for an extension of the cancellation date to 11 May, the owners agreed to reduce the rate of hire for the new fixture to $31,500 a day.

5. The owners claimed damages for the loss of the difference between the original rate and the reduced rate over the period of the fixture. At US$8,000 a day, that came to US$1,364,584.37. The charterers said that the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Transfield Shipping Inc v Mercator Shipping Inc (The Achille... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2008] UKHL 48
Decision Date

CaseChat Overview and Summary

In Transfield Shipping Inc v Mercator Shipping Inc, the House of Lords addressed the issue of damages recoverable for delay in redelivery of a chartered vessel. The shipowners, Mercator, had chartered their vessel to Transfield for a fixed period, and then sub-chartered the vessel for a subsequent period at a higher rate. When Transfield delayed the redelivery, Mercator lost the sub-charter at the higher rate, and claimed damages for the difference between the charter rates. Transfield argued that the measure of damages should be the loss of profit from the sub-charter, as the loss was foreseeable. The House of Lords held that the measure of damages should be the difference between the charter rate and the market rate for the period of delay. The Lords found that the loss from the sub-charter was not of a type which the charterers could have been expected to have assumed responsibility for, as it depended on unpredictable factors such as market volatility and the terms of the sub-charter. The House emphasised that damages should be limited to losses which were within the contemplation of the parties at the time the contract was made, and which could be said to flow naturally from the breach of contract. The decision reinforces the principle that a party is not liable for unforeseeable or exceptional losses arising from a breach of contract, unless the contract specifically provides otherwise.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established