Mussington & Anor v Development Control Authority and others (Antigua and Barbuda)

Link copied
Case Copied 33 min read

Hilary Term

[2024] UKPC 3

Privy Council Appeal No 0116 of 2021

JUDGMENT

John Mussington and another (Appellants)

 v

Development Control Authority and others (Respondents) (Antigua and Barbuda)

From the Court of Appeal of the Eastern Caribbean Supreme Court (Antigua & Barbuda)

before

 

Lord Hodge

Lord Sales

Lord Leggatt

Lord Burrows

Lord Boyd

JUDGMENT GIVEN ON

27 February 2024

 

Heard on 8 November 2023

Appellants

Marc Willers KC

Leslie Thomas KC

Stephen Cottle

Thalia Maragh

Adam Riley

(Instructed by Sheridans (London))

1st and 3rd Respondents

David Dorsett

Carla Brookes-Harris

Rose Ann Kim

(Instructed by Teacher Stern LLP (London

2nd Respondent

Hugh C Marshall Jnr

Kema Benjamin

(Instructed by Marshall & Co (Antigua))

 

Lord boyd:

  1. The issue in this case is whether the appellants have standing to challenge the grant of a development permit for the construction of an airstrip on the island of Barbuda. The airstrip was the first phase in the construction of an airport that would include a terminal building.
  2. The appellants are Barbudans resident on Barbuda. The first appellant is a marine biologist by training, and recently retired as the principal of Sir McChesney George Secondary School on the island of Barbuda. The second appellant is a retired teacher.
  3. The first respondent, the Development Control Authority ("DCA") is the statutory planning authority for Antigua and Barbuda, with responsibility for the administration of the development control regime under the Physical Planning Act 2003. The second respondent is a statutory authority responsible for operating airports in Antigua and Barbuda and is responsible for the construction of the airport. The third respondent is the Attorney General as representative of the Government of Antigua and Barbuda.
  4. On 29 April 2021 the Court of Appeal of the Eastern Caribbean Supreme Court Antigua and Barbuda dismissed the appellants' application for judicial review, holding that they had not established standing to bring their application.
  5. The planning process in Antigua and Barbuda

  6. The DCA was established by the Physical Planning Act 2003, section 4(5). Its functions include the regulation of development "having regard to the need to secure consistency and conformity with the development plan, if any": section 5(3)(b). The Chief Executive is the Town and Country Planner. Part III of the Act provides for the preparation of a development plan by the Town and Country Planner. Section 11 makes provision for consultation on the draft plan, including, in respect of land in Barbuda, with the Barbuda Council. The draft plan is then submitted to the Minister. If the Minister accepts the plan, with or without modifications, the Minister submits the plan for the approval of Parliament: section 12(4).
  7. In December 2011, a "Sustainable Island Resource Management Zoning Plan for Antigua and Barbuda (including Redonda)" was prepared. It was considered and approved by the Cabinet, which decided that the plan was to be submitted by the Minister for the approval of Parliament. The plan is yet to be submitted and approved by Parliament. Where a plan has been prepared…
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Mussington & Anor v Development Control Authority and others... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2024] UKPC 3
Decision Date

CaseChat Overview and Summary

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established