Morge (FC) (Appellant) v Hampshire County Council (Respondent)

Link copied
Case Copied 55 min read

Hilary Term

[2011] UKSC 2

On appeal from: 2010 EWCA Civ 608

JUDGMENT

Morge (FC) (Appellant) v Hampshire County Council (Respondent)

before

Lord Walker


Lady Hale
Lord Brown
Lord Mance
Lord Kerr

JUDGMENT GIVEN ON

19 January 2011

Heard on 8 November 2010

Appellant Respondent
Charles George QC Neil Cameron QC
Gregory Jones Sasha White
Sarah Sackman
(Instructed by Swain & Co (Instructed by Hampshire
Solicitors) County Council Legal

Services)

LORD BROWN

1. This appeal concerns a planning permission granted on 29 July 2009 for a proposed three mile (4.7km) stretch of roadway to provide a rapid bus service between Fareham and Gosport in South East Hampshire. The permission was challenged on environmental grounds including not least its likely impact on several species of European protected bats inhabiting the general area around the proposed busway. The challenge having failed before Judge Bidder QC (sitting as a Deputy High Court judge) on 17 November 2009 – [2009] EWHC 2940 (Admin) – and before the Court of Appeal (Ward, Hughes and Patten LJJ) on 10 June 2010 – [2010] EWCA Civ 608, [2010] PTSR 1882 – this Court on 27 July 2010 gave the appellant limited permission to appeal so as to raise two issues of some general importance.

2. Issue one concerns the proper interpretation of article 12 (1)(b) of the Habitat’s Directive 92/43/EEC which provides that:

“Member States shall take the requisite measures to establish a system of strict protection for the animal species listed [the protected species] in their natural range, prohibiting . . . (b) deliberate disturbance of these species, particularly during the period of breeding, rearing, hibernation and migration; . . .”

3. Issue two concerns the proper application of regulation 3(4) of the Conservation (Natural Habitats, etc) Regulations 1994 SI 1994/2716 (as amended first by the Amendment Regulations 2007 and then the Amendment Regulations 2009), by which domestic effect is given to the Directive:

“3(4) . . . every competent authority in the exercise of any of their functions, shall have regard to the requirements of the Habitats Directive so far as they [the requirements] may be affected by the exercise of those functions.”

With that briefest of introductions let me turn to the essential factual context in which these issues now arise, noting as I do so that altogether fuller descriptions of the facts can be found in the judgments below.

4. The proposed new rapid busway – the first and larger phase of which is already substantially under way, applications for interlocutory relief to stay its continuance having been refused by the Court of Appeal and refused by this Court on granting leave to appeal – runs along the path of an old railway line, last used in 1991. The scheme provides for buses to be able to join existing roads at various points along the route. It will create a new and efficient form of public transport to the benefit of many residents, workers and visitors to the region. Central Government has committed…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Morge (FC) (Appellant) v Hampshire County Council (Responden... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2011] UKSC 2
Decision Date

CaseChat Overview and Summary

In the case of Morge (FC) (Appellant) v Hampshire County Council (Respondent), the Supreme Court was asked to determine two main issues. The first issue concerned the proper interpretation of article 12(1)(b) of the Habitats Directive 92/43/EEC, which prohibits the deliberate disturbance of protected species, particularly during breeding, rearing, hibernation, and migration. The second issue was the proper application of regulation 3(4) of the Conservation (Natural Habitats, etc.) Regulations 1994, which requires competent authorities to have regard to the requirements of the Habitats Directive when exercising their functions. The case revolved around a proposed busway project in South East Hampshire, which raised concerns about its potential impact on several species of protected bats.

On the first issue, the Court held that article 12(1)(b) of the Habitats Directive should be interpreted in the light of the Directive as a whole, with a focus on protecting species rather than their habitats. The Court disagreed with the Court of Appeal's interpretation that disturbance must have a detrimental impact on the conservation status of the species at population level. Instead, the Court found that a case-by-case approach is needed, taking into account the specific characteristics of the species concerned and the situation.

Regarding the second issue, the Court concluded that the regulatory committee of Hampshire County Council did not properly consider the requirements of the Habitats Directive when granting planning permission for the busway project. The Court found that the committee members did not make an independent assessment of whether the development would or would not occasion disturbance to bats in breach of article 12(1)(b) of the Directive. As a result, the Supreme Court allowed the appeal and quashed the planning permission granted by the Hampshire County Council.