- This appeal raises difficult and important issues about the effect of adjudication pursuant to provisions implied into a construction contract under section 108(5) of the Housing Grants, Construction and Regeneration Act 1996, read with the Scheme for Construction Contracts (England and Wales) Regulations 1998 (SI 1998 No 649). The construction contract (within the broad meaning assigned by section 104(2) of the 1996 Act) was a contract by the respondent, Aspect Contracts (Asbestos) Ltd ("Aspect"), to carry out an asbestos survey and report on blocks of maisonettes in Hounslow which the appellant building contractor, Higgins Construction Plc ("Higgins"), was considering redeveloping.
- The survey was conducted in March 2004 and the report was dated 27 April 2004. During the redevelopment in early 2005, Higgins allegedly found and had to have removed asbestos containing materials which had not been identified in the report. A dispute consequently arose with Aspect.
- Negotiation and mediation having failed, Higgins referred the dispute to adjudication, claiming £822,482 damages plus interest. The claim was for breach of contractual and/or conterminous tortious duties to exercise reasonable skill and care. By a decision dated 28 July 2009, the adjudicator, Ms Rosemary Jackson QC, concluded that Aspect had been in breach of such duties causing Higgins loss in various, though not all, respects alleged by Higgins, and ordered that Aspect pay Higgins £490,627, plus interest which amounted, at the date of the decision, to £166,421.05. She also ordered Aspect to pay her own fees of £8,750 plus VAT. On 6 August 2009 Aspect duly paid Higgins £658,017, a sum which included further interest from the date of the decision.
- Higgins did not commence any proceedings, whether to recover the balance of its claim, £331,855 plus interest, or otherwise. The limitation period expired on the face of it on or about 27 April 2010 for any action by Higgins founded on breach of the construction contract and at the very latest by early 2011 for any action founded on tort: Limitation Act 1980, sections 2 and 5. Higgins was evidently content to let matters rest. It did not, so far as appears, ask Aspect to agree, and Aspect did not agree, to treat the adjudicator's decision as final.
- Only after the expiry of both the above-mentioned limitation periods did Aspect on 3 February 2012 itself commence the present proceedings seeking to recover the sum it paid on 6 August 2009. It did so without giving prior notice that it was dissatisfied with Ms Jackson's decision…
Summary
Trinity Term
[2015] UKSC 38
On appeal from: [2013] EWCA Civ 1541
JUDGMENT
Aspect Contracts (Asbestos) Limited (Respondent) v Higgins Construction Plc (Appellant)
before
Lord Mance
Lord Wilson
Lord Sumption
Lord Reed
Lord Toulson
JUDGMENT GIVEN ON
17 June 2015
Heard on 14 and 15 April 2015
| Appellant Andrew Bartlett QC Isabel Hitching (Instructed by Silver Shemmings LLP) |
Respondent Fiona Sinclair QC Richard Liddell (Instructed by Mills & Reeve LLP) |
LORD MANCE: (with whom Lord Wilson, Lord Sumption, Lord Reed and Lord Toulson agree)
Introduction
Aspect's claim
Keep reading for free
Create a free CaseChat account to read Aspect Contracts (Asbestos) Ltd v Higgins Construction Plc and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2015] UKSC 38
- Decision Date
CaseChat Overview and Summary
AI summary not yet generated for this case.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.