IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
CIV-2018-404-2524
[2019] NZHC 3471
IN THE MATTER OF the Judicial Review Procedure Act 2016 AND
IN THE MATTER OF
the Construction Contracts Act 2002
BETWEEN
AHMED AMIN MAHMOUD YOUSSEF (AS TRUSTEE OF THE JAMESSEF TRUST) AND STEPHYN ST JAMES
Applicants
AND
RICHARD LINTON MAIDEN
First Respondent
BESPOKE DESIGN AND BUILD LIMITED
Second Respondent
Hearing: 1 April 2019
Further submissions received 15 and 17 April 2019
Appearances:
M R Taylor for Applicants
K R Narayanan for Second Respondent
Judgment:
20 December 2019
REASONS FOR JUDGMENT OF PETERS J
This judgment was delivered by Justice Peters on 20 December 2019 at 11.00 am pursuant to r 11.5 of the High Court Rules
Registrar/Deputy Registrar Date: ...................................
YOUSSEF v MAIDEN [2019] NZHC 3471 [20 December 2019]
Introduction
[1] The applicants, Mr Ahmed Youssef and Mr Stephyn St James, seek judicial review of a determination made by the first respondent, Mr Richard Maiden, on 15 October 2018 (“determination”).
[2] Mr Maiden made the determination as adjudicator under the Construction Contracts Act 2002 (“CCA”), in respect of a dispute between the applicants and the second respondent, Bespoke Design Limited (“Bespoke”).
[3] Mr Maiden abides the decision of the Court. Bespoke denies the applicants’ allegations, and opposes the application for review.
[4] On 31 October 2019, I issued a results judgment granting the application and quashing the determination.1 These are my reasons.
Background
[5] The applicants engaged Bespoke to build a house on their site in Mangawhai. The parties entered into the relevant contract on 17 or 18 August 2017 (“contract”). Work commenced in the second half of 2017 and the house was expected to be completed by mid-2018. Differences between the parties arose early in 2018, with matters coming to a head in a series of letters in April 2018.
[6] By email of 3 April 2018, the applicants advised Bespoke they considered it in breach of contract in several respects and that they would not pay for costs they considered resulted from inefficiencies.
[7] On 6 April 2018, Martelli McKegg, acting for Bespoke, notified the applicants that Bespoke was suspending work on site with immediate effect.
[8] By letter dated 9 April 2018, the applicants, by their counsel Mr Taylor, cancelled (or purported to cancel) the contract, on the basis Bespoke had repudiated
the contract or committed a fundamental breach of it, and said they would engage another builder to finish the work.
[9] On 11 April 2018, Bespoke rejected the applicants’ cancellation, and itself cancelled the contract.
Adjudication
[10] On or around 10 August 2018, Bespoke gave the applicants Notice of Adjudication under the CCA. In its Notice of Claim, setting out what it considered to be the issues, Bespoke sought:
(a)$90,106.42, including GST, it said was owed in respect of unpaid invoices;
(b)interest;
(c)lost profit of $61,267.02. Bespoke claimed this sum as the profit it would…
Continue reading Youssef v Maiden
Sign in free to access the full text
- AGLC
- Youssef v Maiden [2019] NZHC 3471
- Case
- [2019] NZHC 3471
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.