IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
CIV-2024-404-000499
[2024] NZHC 2462
UNDER Section 290 of the Companies Act 1993 and Part 19 of the High Court Rules 2016 IN THE MATTER
of an application to set aside a statutory demand
BETWEEN
YOUR BUILDER LIMITED
Applicant
AND
DMITRY RUBAN and ALEXANDRA MATVEEVA
Respondents
Hearing: 19 August 2024 Appearances:
K R Narayan / N Toma for the Applicant D A Cowan for the Respondents
Judgment:
29 August 2024
JUDGMENT OF ASSOCIATE JUDGE GARDINER
This judgment was delivered by me on 29 August 2024 at 4.00 p.m. pursuant to Rule 11.5 of the High Court Rules.
Registrar/Deputy Registrar
Date.......................................
Solicitors:
Martelli McKegg, Auckland D A Cowan, Auckland
YOUR BUILDER LTD v RUBAN [2024] NZHC 2462 [29 August 2024]
Introduction
[1] Dmitry Ruban and Alexandra Matveeva (the Owners) engaged Your Builder Ltd (Your Builder) to renovate and extend their house and construct swimming and spa pools on their property in Mt Eden. They paid a deposit and building work began.
[2] Work was suspended after around four months to renegotiate the scope of works. Then, the Owners purported to cancel the building contract on the basis that Your Builder’s work was defective. Your Builder disputed that the Owners were entitled to cancel the building contract, and purported to cancel the building contract themselves, forfeiting the deposit and applying it towards unpaid invoices, interest, lost profit, and legal fees.
[3] The Owners issued a statutory demand demanding repayment of the deposit. Your Builder applies to set aside the statutory demand on the grounds that it is solvent, and the debt claimed in the statutory demand is disputed. The Owners say that a statutory demand may be issued where a creditor is solvent, and there is no dispute that Your Builder is indebted to them for the deposit.
[4] The Owners have referred the wider dispute to adjudication under the Construction Contracts Act 2002.
[5] The issue for determination here is whether there is a genuine and substantial dispute that the deposit is owing and due to the Owners as a debt.
Further background
[6] On 24 July 2022, Your Builder and the Owners entered into a New Zealand Certified Builders Association Cost & Mark-Up (Renovations) contract (the building contract). The estimate for the scope of work was $1,244,786.62. The expected completion date was 16 August 2023, with allowances for automatic extensions of time for variations and unforeseen physical conditions (amongst other things).
[7] On or around 9 February 2023, the Owners paid the deposit required under cl 6.2 of the building contract in the sum of $124,478.66. Work commenced on or about 8 February 2023.
Work informally suspended
[8] In June 2023, an issue arose relating to the Owners’ budget for the work. On or about 8 June 2023, the Owners advised that they would not be able to pay more than $1,209,301.61. Work paused. The parties amended the…
Continue reading Your Builder Limited v Ruban
Sign in free to access the full text
- AGLC
- Your Builder Limited v Ruban [2024] NZHC 2462
- Case
- [2024] NZHC 2462
- Decision Date
CaseChat Overview and Summary
The court held that there was a genuine and substantial dispute regarding whether the deposit was owed to the Owners as a debt. The dispute primarily centered on whether the Owners were entitled to cancel the building contract due to alleged defects, and if Your Builder had a right to retain the deposit for damages, including lost profit. The court found that there were factual disputes about the nature and extent of the defects, whether Your Builder was given a reasonable opportunity to remedy any defects, and whether the defects could have been rectified by the completion date. These disputes were not suitable for resolution in a statutory demand proceeding and would be determined in the adjudication proceeding. Consequently, the court set aside the statutory demand, finding that there was a genuine and substantial dispute over the existence of the debt.
In conclusion, the statutory demand issued by the Owners on 23 February 2024 was set aside. The court determined that the genuine and substantial disputes regarding the nature of the defects, the opportunity to remedy them, and the potential for rectification by the completion date warranted setting aside the demand. The court also noted that Your Builder was entitled to costs as the successful party.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.