Wharepapa v Fulton Hogan Limited HC Ak CIV 2009-404-4539

Case

[2009] NZHC 2491

1 December 2009

No judgment structure available for this case.

IN THE HIGH COURT OF NEW ZEALAND

AUCKLAND REGISTRY

CIV 2009-404-4539

BETWEEN  MAXWELL WHAREPAPA

Plaintiff

AND  FULTON HOGAN LIMITED Respondent

Hearing:         18 November 2009

Appearances:  A D Banbrook for the Plaintiff

C J Booth for the Respondent

Judgment:      1 December 2009 at 4.30 pm

RESERVED JUDGMENT OF PRIESTLEY J

This judgment was delivered by me on 1 December 2009 at 4.30 pm

pursuant to Rule 11.5 of the High Court Rules.

Registrar/Deputy Registrar

Date:………………………….

Counsel/Solicitors:
A D Banbrook, P O Box 3600, Shortland Street, Auckland 1140.  Fax: 09 377 0762

Holmes Dangen & Associates Limited, P O Box 3600, Auckland 1140.  Fax: 09 309 2554

C J Booth, Kensington Swan, Private Bag 92101, Victoria Street West, Auckland 1142

Fax: 09 309 4276

WHAREPAPA V FULTON HOGAN LTD HC AK CIV 2009-404-4539  1 December 2009

Introduction

[1]      The parties entered into a written subcontract agreement which was dated 1

September 2006.

[2]      The respondent was the head contractor for the construction of the extension

to State Highway 20 through Mt Roskill.

[3]      The  appellant’s  agreed  responsibilities,  in  general  terms,  were  to  carry  out earthworks  specified  by  the  respondent  in  respect  of  the  highway’s  construction. The  appellant  was  to  provide  a  workforce  of  operators  and  labourers  and,  as  the workforce’s  employer,  was  responsible  for  payment  of  their  wages.   The  contract entitled the appellant to charge the respondent for the supplied labour at an agreed hourly rate.

[4]      The  contract  obliged  the  respondent  to  pay  the  appellant  $35  per  hour exclusive of GST “or such greater or lesser sum as shall become payable under the subcontract documents” in respect of the labour supplied.

[5]      The  appellant  had, by 1 September 2006, been working  on  the  highway construction site for approximately four weeks. Despite the contract’s date, its actual execution was probably somewhat later. The respondent had written on 1 September

2006 to the appellant enclosing the contract documents for signature and specifying a

1 September start date at the agreed rate of $35, GST exclusive.  An executed copy

of the contract was returned to the appellant by the respondent on 3 October 2006. Nothing hangs on the date of execution.

[6]      This letter, which both counsel accept, forms part of the contract, provided the agreement could be terminated with one day’s written notice by either party.  In the event the appellant used this mechanism to terminate the contract by letter dated 18 September 2007.

[7]      Just over a month into the contract’s term, in early October 2006, there was a meeting between the parties’ representatives.  As a result of that meeting the hourly

rate invoiced to the respondent by the appellant (which the respondent paid) reduced from $35 per hour to $30 per hour, GST exclusive.

[8]      The  dispute  between  the  parties  is  whether  the  $5.00  reduction  of  the specified contractual hourly rate flowed from an agreed variation of their contract, or whether  instead  the  higher  $35  rate  remained  afoot  as  a  contractual  obligation enforceable against the respondent.

[9]      The  appellant  contended  that  he  was  entitled  to  the  stipulated  $35  hourly contract sum. He sued the respondent in the Auckland District Court seeking damages for breach of contract (effectively the alleged arrears) of $91,782.   Judge A A  Sinclair  presided  over  the  ensuing  trial  in  April  2009  and  heard  the  parties’ witnesses.   In a reserved judgment, delivered on 22 June 2009, the Judge dismissed the  appellant’s  claim  and  awarded  the  respondent  costs. This  appeal  challenges Judge Sinclair’s judgment.

Background

[10]     The Judge,  in addition to   considering   the   evidence   from   the   parties’

witnesses, also considered relevant documents.  Because these documents are central

to the appellant’s submissions, I briefly describe them.

[11]     I have already dealt with the relevant terms of the printed 1 September 2006

subcontract document.

[12]     On 27 November 2006 the respondent wrote  to the appellant the following terms:

Offer to vary our sub-contract agreement

We offer to vary our sub-contract agreement with you as follows:

The market for labour has only moved 4% over the last 12 months and fuel

to run your Ute is only a small percentage of your labour rate and would add only another 1% to your costs.

Consequently our offer to you is to vary your labour rates by 5%.

The  new  rates  associated  with  your  offer  will  take  effect  as  of  the  1st   of

December 2006 and will apply until the 30th  of November 2007.

Should you agree to this variation of the contract then simply increase your rate on your December invoice.

[13]     Although  expressed  as  an  offer  to  vary  the  subcontract,  that  letter  is  not central to the dispute.  Rather it relates to an entitlement the respondent had under its head  contract,  permitting  it  to  increase  its  rates  and  prices  which  the  respondent decided to  pass on  to its  subcontractors.   Significantly,  the  post-1 December 2006 invoices submitted by the appellant applied the 5% increase to the lower $30 figure.

[14]     On 14 June 2007 a Mr Dickens, the respondent’s project manager, wrote to the  appellant  to  address  certain  issues  raised  by  the  appellant.   By  that  stage,  for reasons  not  relevant,  the  working  relationship  between  the  parties  had  become uneasy.  The letter relevantly states:

I have investigated the issues you raised in your telephone conversation and comment as follows.   We intend to continue hiring your staff provided the price is right and the men are skilled and reliable….

Both Lou and Glen deny offering you any terms of engagement other than what is in our signed agreement. If you look at our hire Labour Hire agreement you will see that there is no guarantee of ongoing work for your firm. Both parties have the opportunity to terminate the agreement with one days (sic) notice. However the way to continue getting hire business from us

is  to  provide  a  reliable  service  with  skilled  men  that  solve  our  labour problem and so make your firm the best to deal with.

Another reason for the reduction in labour hire from your firm is the fact that the nature of the work on site is changing.   The screening has stopped and the  Quarry  work  is  much  reduced.    Hence  we  have  need  of  fewer  hired operators.  This is a fact of Project work.   We did try to redeploy your men as the screening and quarry work has wound down….

Competition in your business is also a fact of life. Other firms are undercutting your rate and we also retain the option of directly employing our own staff if we choose to. Glen tells me that he negotiated with you to charge a rate cheaper than the $35.00 noted in the hire agreement.  The proof of this is the fact that you have generally charged us at a rate less than $35 for the last several months.   Hence your request to back charge $75,000 on all the hours previously charged is declined on the basis that you chose to charge a lesser rate to remain competitive.

Should you wish to exercise your contractual right to charge $35.00 for all future hires then you should do so.  However it will most likely result in us moving our  business  to cheaper  and  more  reliable  companies  and thus  we will replace any of your men that we think is not worth the higher rate.

[15]     Mr Banbrook in his submissions placed great weight on the last paragraph of the  letter  in  which  the  $35  figure  is  described  as  a  “contractual  right”. He  also placed weight on the first sentence of the second paragraph, construing it as a denial that the terms of engagement were different from what was in the signed contract. But, as a reading of the letter suggests, the context in which those portions appear makes such blunt assertions problematic.

[16]     The final document is an undated letter written  by  the  appellant  to  the respondent covering a number of issues. The appellant’s evidence was that this was delivered to a member of the respondent’s secretarial staff in late May or early June

2007.  The Judge did not accept the appellant’s evidence so far as that delivery time was concerned.   The letter covers a number of issues but relevantly claims that the appellant seeks “back payment” for the agreed $35 hourly rate and that at the early October 2006 meeting (supra [7]) the appellant felt “misdirected and was placed in a very vulnerable position”.   The letter  purportedly attached  an invoice for the back payment.  No such invoice or copy of it was ever discovered.

The Judge’s findings

[17]     The  appellant,  suing  as  it  was  for  breach  of  contract,  had  to  discharge  the civil burden of proof in the District Court.  The respondent’s position was that, at the early October 2006 meeting, the parties agreed to vary the stipulated contract rate of $35 per hour to $30.  Such a variation was concluded orally and from thenceforth the parties applied the reduced rate.

[18]     The Judge heard conflicting evidence about the October 2006 meeting which appears to have taken place in the State Highway 20 site office at Hayr  Road, Mt Roskill. The respondent’s evidence was that it had discovered the $35 per hour rate was slightly above the market; that only five operators provided by the appellant were working on the site at that stage; that because of its need for more skilled operators, the respondents would continue to use labour provided by the appellant, provided the hourly rate  was  adjusted  downwards  to  $30. Although the contract gave no monopoly or exclusivity to the appellant, the respondent’s evidence was that it was prepared to hire additional skilled operators through the appellant for a longer

duration, provided the hourly rate was cut.  The respondent’s witnesses described the meeting as friendly and cordial.   They indicated to the appellant that if he was not prepared to drop the hourly rate they would continue to honour that sum in respect of the  five  operators  who  were  on  site,  but  would  look  elsewhere  for  further  skilled operators.

[19]     The appellant’s perception of the meeting was that he was very much “over a barrel”  and  had  little  choice  but  to  accept,  although  he  conceded  in  evidence  that there was a “gentleman’s agreement” to the effect that, for any skilled operator work on State Highway 20, the respondent would initially come to him.

[20]     The issues which confronted the Judge, other than credibility issues, were:

·    Whether the subcontract agreement had been varied.

·    Whether there was consideration.

·    Whether the variation was the product of duress.

·    Whether the respondent had admitted liability.

[21]     These  last  two  issues  were  not  pursued  on  appeal.   One  of  the  grounds  of appeal  challenged  the  Judge’s  findings  on  duress  which  in  turn  provoked  a  cross- appeal.  In  the  District  Court  the  appellant  had  not  pleaded  duress  but  the  Judge nonetheless allowed submissions on the topic.  The fourth of the above issues related to  a  settlement  proposal  from  the  respondent  to  settle  all  outstanding  differences, without recourse to litigation, by payment of the sum of $68,000.  The appellant was invited to invoice that sum but did not do so.  With the advantage of hindsight it is a pity the parties’ dispute was not settled on those terms.

[22]     The Judge reached her conclusion that the appellant’s claim had failed via the following route.  The judgment speaks for itself.  I replicate those portions which are relevant to the appeal:

[21]     The  plaintiff  submitted  that  there  was  no  written  variation  of  the Subcontract   Agreement   as   required   in   the   subcontract   conditions   or alternatively, in accordance with the defendant’s practice.   The Subcontract Agreement provides that any variation to the Subcontract Works can only be made  if  directed  in  writing  by  the  defendant.   However,  there  is  no  such restriction in respect of other contractual terms and accordingly the parties can  orally  agree  to  vary  those  terms.   The  plaintiff  points  to  the  Letter  of Acceptance and letter of 27 November 2006 as evidence of the defendant’s practice  to  reduce  such  matters  to  writing. However  no  evidence  was produced that this was the defendant’s usual practice or that the defendant had any prohibition on entering into oral agreements and/or oral variations to agreements.

[22]     The  plaintiff  refers  to  the  defendant’s  offer  to  settle  the  claim  and submits that this offer, combined with the defendant’s letter of 14 June 2007 “strongly  supports  the  conclusion  that  there  was  no  enforceable  variation agreement  ever  entered  into  between  the  parties  in  October  2006.” The plaintiff contends that the statement made by Mr Dickens that “Should you wish to exercise your contractual right to charge $35 for all future hires then you  should  do  so.”  comprises  a  frank  acknowledgement  that  the  plaintiff retained the contractual right to charge $35 per hour and by inference there was no enforceable variation in place reducing the hourly rate from $35 to $30 per hour.  I do not consider this statement to be an acknowledgement by the defendant of an existing contractual right. When viewed in the context of  the  letter  as  a whole, I am satisfied that  the  defendant  in  making  this statement, was focussed on future dealings and was simply emphasising to the plaintiff that if he wished to revert to the rate set out in the Subcontract Agreement for future hires then he should do so but it was unlikely he would get work.

[23]     Having had  the  opportunity to  hear and see the  witnesses,  I prefer the evidence of Mr Dickens, Mr Nelson and Mr Cole in all respects.  I found them to be reliable and credible witnesses.  Their evidence was detailed and consistent.  On the other hand, I found the plaintiff’s memory of events was poor at times and his evidence lacked particularity.

[24]     Having given careful consideration to all the evidence I am satisfied that  at  the  October  2006  meeting  the  plaintiff  did  agree  (for  the  reasons canvassed  below)  to  the  variation  in  his  rate  to  $30  per  hour  (plus  GST). Following  the  meeting  the  plaintiff  charged  at  the  reduced  rate  (plus escalation).   He did not express any concern about this rate until June 2007 when he met with Mr Dickens by which time difficulties being experienced with the plaintiff and operators supplied by him were coming to a head.  The plaintiff did produce an undated letter, which he said he had delivered to the defendant  possibly  in  late  May  or  early  June  seeking  back  payment  and enclosing an invoice.  Mr Dickens gave evidence that the defendant did not receive  this  letter.        Under  cross-examination  the  plaintiff  stated  that  the invoice which was not produced, was for $91000 (approx) being the amount owing on termination of the Subcontract.   I am satisfied therefore that  the letter (if sent at all) was sent considerably later in time than initially claimed

by the plaintiff.

(b)      Was there consideration?

[25]     The plaintiff alleges that  the promise by the defendant to fulfil  his obligations under the original agreement cannot constitute good consideration for a variation which had the unilateral effect of reducing the benefit  of  the  Subcontract  Agreement  to  the  plaintiff. The  defendant concedes that if there was a reduction in the rate in favour of the defendant without  any  corresponding  benefit  to  the  plaintiff  there  would  be  no consideration and the defendant could not enforce the varied agreement.

[26]     The   defendant   claims,   however,   that   there   was,   in   fact,   a corresponding  benefit  for  the  plaintiff  by  way  of  increased  work. The variation followed the defendant’s increased need for skilled operators and for a longer duration than had originally been anticipated.   By agreeing to the variation, the plaintiff secured that opportunity to supply those operators. The plaintiff went on to earn a substantial sum in the period from October

2006 to cancellation of the Subcontract Agreement on 18 September 2007.

[27]     In this case, I find that the variation to the Subcontract Agreement benefited  both  the  defendant  in  securing  a  reduced  rate  for  the  supply  of labour and the plaintiff in achieving an increased number of operators on site for a longer period.   I am satisfied, therefore, that there is consideration to support the agreement to vary the terms of the Subcontract Agreement.

Discussion

[23]     Mr  Banbrook  advanced  the  appellant’s  submissions  under  two  heads.   The first head was the Judge had erred in finding that in early October 2006 there had been a “consensual oral agreement” between the parties which varied the hourly rate stipulated  in  the  written  contract  from  $35  to  $30.   The  second  head  was  that  the variation was, in any   event,   not   legally   enforceable   because there was no consideration in the form of any enforceable benefit to the appellant.

No consensual variation of the agreement

[24]     Mr Banbrook placed great weight on the fact that the alleged reduction of the hourly rate to $30 had not been recorded or mentioned in writing. Although accepting that a variation of the parties’ subcontract could be oral, counsel nonetheless pointed to the documentary evidence. The 1 September 2006 written offer recorded the $35  rate. So  too  did  the  executed  agreement  returned  by  the respondent on 3 October  2006.   The respondent’s 14 June 2007 letter (supra [14]) expressly  referred  to  the  $35  rate  as  “your  contractual  right”. The  absence  of

anything recording the alleged variation in writing sat uneasily with the respondent’s

27  November  2006  letter  (supra  [12])  headed  “Offer  to  vary  our  sub-contract agreement”.

[25]     In  counsel’s  submission  the  evidence  of  the  appellant  at  trial  was  to  be preferred. Although  he  had  invoiced  the  respondent  at  the  lower  $30  rate  on  9 October 2006 (the first reduced invoice date), right through to termination some 11 months later, the appellant had never consented to the variation.

[26]     Objectively, submitted Mr Banbrook, the variation for which the respondent contended had not been made out.   Counsel referred to a passage from the Laws of New Zealand: Contract, Part II Formation of Contract which at [16] states:

Where  one  party  has  behaved  in  such  a  way  that  a  reasonable  bystander would  believe  that  that  party  is  unambiguously  assenting  to  the  terms  as proposed  by  the  other  party,  the  first  party  is  generally  precluded  from setting up a claim that he or she had some other intention.  Consequently that first party is bound by the contract as if he or she had intended to agree to the other party’s terms.   This will not be the case where the offeror knows that the  offeree  does  not  intend  to  accept  the  offer,  even  though  the  offeree’s conduct  is  such  that  a  reasonable  bystander  would  consider  that  it  was  in response to, and in acceptance of, the offer.

[27]     The “reasonable bystander” concept was referred to by the Court of Appeal

in Meates v Attorney General [1983] NZLR 308, 378.

[28]     Additionally, submitted counsel, although the appellant had indeed invoiced

at the lower $30 rate, he had never accepted the reduced rate as his undated 2007 letter  (supra  [16])  showed.   On the appellant’s evidence he was  faced  with  an ultimatum from the respondent to which he acceded unwillingly.   He continued to protest the demand. As support for that submission, counsel again refer to the 14 June 2007 letter. The reference to $35 being the appellant’s “contractual  right” clearly showed that the respondent knew full well the appellant had never accepted the variation and that its contractual entitlement to the higher sum remained in force.

[29]     For similar reasons to those expressed by Judge Sinclair (supra [22]) I reject the appellant’s argument under this head.  I do so for the following reasons.

·    The Judge resolved credibility issues in favour of the respondent’s witnesses

(see her judgment [23]).

·The respondent’s evidence as it related to the October 2006 meeting was that, provided the appellant agreed to a reduction to $30 (then being paid to five of his workers on site), it would be to the appellant that the respondent would look  for  the  extra  operators it required. The respondent would  otherwise have  been  prepared  to  continue  to  pay  the  agreed  $35  rate  for  those  five workers  but  would,  in  those  circumstances,  have  looked  elsewhere  for  the extra operators it required for the highway development.

·    At no stage after early October 2006 did the appellant invoice the respondent

at  the  higher  amount. Nor  did  the  appellant  enter  any  form  of  protest indicating a stance that the contract rate of $35 remained afoot.

·The 5% upward adjustment applied by the respondent to the subcontract in the wake of the respondent’s 27 November 2006 letter was calculated by the appellant on the $30 rate not the $35 rate.

·In  the  months  that  followed  the  October  2006 variation, consistent  with  a variation which the parties had negotiated, the number of operators provided by the appellant engaged on the site increased considerably as did the number of hours worked. By way of example the number of  operators engaged  in September 2006 was between 3 and  5,  and  the  invoiced  sums  totalled

$20,120.   In November 2006 the numbers were 10 and $36,990.   By March

2007 the numbers were 12 and $77,161.

·    I agree with the Judge’s construction of the respondent’s 14 June 2007 letter.

I do not, in the context of that letter, construe the words “should you wish to exercise your contractual rights to charge $35 for future hires then you should

do so” as being a concession by the respondent that the contract had remained  unvaried. Rather  it  was  somewhat  loose language used by the author of the letter to set out what the appellant (who had clearly changed his stance some eight months later) took to be his contractual entitlement. The

earlier  portion  of  the  paragraph  in  which  those  words  appear  (supra  [14]) makes it very clear that the respondent’s position was that the contractual rate had indeed been varied.  The letter is totally consistent with the facts as the Judge found them, and with the respondent’s defence at trial.

[30]     I have not overlooked the  fact  that,  from  the  appellant’s  standpoint,  the  1

September  2006  contract  carried  some  risk.    The  first  risk  was  there  was  no guarantee that the appellant would have any exclusivity or priority in providing the operators  and  labourers  required  for  the  earthworks  on  the  respondent’s  site. The second risk  was  that  the  contract  could  be  terminated  by  the  respondent  for  any reason on one day’s notice.  But it was against that background, in a situation where the  respondent  was  looking  to  engage  more  operators  but  at  a  lower  rate,  that  a variation was negotiated and concluded.

[31]     In  the  absence  of  any  protest  or  reservation  of  rights  by  the  appellant,  the pattern  of  increasing  operators  and  revenue  supplied  by  the  appellant  under  the contract in the wake of the October 2006 variation, reinforces the Judge’s findings (supra [22]) about what the parties had negotiated.

[32]     It was the appellant who, as plaintiff in the District Court, had to prove on the balance of probabilities that the respondent had breached its contractual obligations. The Judge was clearly of the view that the original $35 hourly rate had been varied. Quite simply the appellant failed to  prove  its  case  so  far  as  the  variation  was concerned.  The reasons given by the Judge are correct.  The first head fails.

No consideration

[33]     It was common ground  between  the  parties  that,  for  any  variation  of  a contract  to  be  legally  enforceable,  there  must  be  consideration. If  there  was  no consideration then the variation is at law unenforceable.

[34]     Mr Banbrook’s argument under this head was simple. If there was an oral variation of the contract in early October 2006 then the sole benefit of that variation flowed to the respondent by way of a reduced hourly rate. There was absolutely no

benefit to the appellant because all the other terms of the 1 September 2006 contract remained unvaried and in force.

[35]     In that regard counsel referred to Chitty on Contracts (29th  ed 2004) paras 3-

079 and 3-080.  Citing from the first of these paragraphs:

…it has been held that there is no consideration for variation which, though capable of benefitting either party, is in fact made wholly with the benefit of one.  For example a variation as to the place at which a debt is to be paid is capable  of  benefitting  either  party;  where  such  a  variation  was  introduced solely for the benefit of the debtor there was held to be no consideration for a promise by the creditor.

[36]     Counsel cited the New South Wales Court of Appeal judgment of T A Sundell

& Sons Pty Ltd v Emm Yannoulatos (Overseas) Pty Ltd (1956) SR (NSW) 323 and

North Ocean Shipping Co Ltd v Hyundai Construction Co Ltd – The Atlantic Baron

[1978] 3 All ER 1170.

[37] The Judge found that there was consideration moving both ways (see her judgment [27]). I consider she was correct in so doing. If the parties’ variation agreement had been limited solely to a reduction to an hourly rate of $30 without more, then there would be force in Mr Banbrook’s submission.

[38]         But that was not the case.  The evidence which the Judge clearly accepted (in preference  to  the  appellant’s  evidence)  was  that  although  the  respondent  was prepared at the October 2006 meeting to continue to pay the five operators on site the agreed $35 rate, it would, in that situation, stand on the non-exclusivity aspect of the contract and look for cheaper operators elsewhere.  The quid pro quo accepted by the  appellant  was  that,  in  return  for  the  reduction  to  the  lower  rate,  the  appellant, provided  his  operators  were  of  acceptable  quality,  would  be  the  respondent’s  first port  of  call.   That  is  exactly what  happened.   The  number  of  operators  increased. The respondent’s 14 January 2007 letter (supra [14]) echoes the varied arrangement.

[39]     So,  focusing  on  the  consideration  requirement  of  the  contractual  variation, the benefit flowing to the respondent was a lower rate.   The benefit flowing to the appellant was an increasing number of operators and labourers for which he could charge.

[40]     I am mindful of Mr Banbrook’s submission that, as a matter of principle, the fact that the appellant’s revenue increased significantly in the months after October

2006 is irrelevant so far as the consideration submission is concerned.  That might be the case if there were no consideration.  But as the Judge found, and correctly, there was on the facts before her consideration moving both ways.

[41]     For these reasons the second head of the appellant’s argument fails.

Result

[42]     I   conclude,   for   the   reasons   given,  that  the  Judge   was   correct   in   her determination of the issues before her. On the facts as she found them, and indeed

on  the  construction  of  the  various  documents  before  her,  the  only  permissible conclusion was that the parties to the 1 September 2006 contract had orally agreed to reduce the hourly rate from $35 to $30.  The appellant was thus unable to make out his claim for breach of contract.

[43]     Accordingly the appeal is dismissed.

Costs

[44]     As the successful party the respondent is entitled to costs on a 2B basis.

[45]     Because the appellant abandoned its third ground of appeal based on duress the respondent did not pursue its cross-appeal.  The appellant indicated this modified stance, so counsel inform me, on 4 November 2009.   Mr Booth seeks costs for the respondent on the cross-appeal up to that date.   Mr Banbrook accepts this claim is proper.  Thus, in addition to 2B costs on the appeal I award the respondent 2B costs on the cross-appeal up to 4 November 2009.

[46]     Counsel did not indicate any difficulty in calculating the relevant figures.

.......................................… Priestley J

Actions
Download as PDF Download as Word Document


Cases Citing This Decision

0

Cases Cited

0

Statutory Material Cited

1