Weyerhaeuser New Zealand Incorporated v Alan Rigg Contracting Limited HC Nelson Civ-2007-442-142

Case

[2007] NZHC 1711

30 March 2007

No judgment structure available for this case.

IN THE HIGH COURT OF NEW ZEALAND NELSON REGISTRY

CIV-2007-442-000142

BETWEEN  WEYERHAEUSER NEW ZEALAND INCORPORATED

Applicant

AND  ALAN RIGG CONTRACTING LIMITED TONY BUTLER CONTRACTING LIMITED

Respondents

Hearing:         29 March 2007

Appearances: F M Farr for Applicant

G M Downing for Respondents

Judgment:      30 March 2007

JUDGMENT OF ASSOCIATE JUDGE CHRISTIANSEN Upon Application to Set Aside Statutory Demand

The Contract

[1]      Weyerhaeuser  and  the  respondents  (Riggs  and  Butler)  were  parties  to  a contract for the supply of earthworks and roading works by Riggs and Butler in the Nelson region.  The contract was subject to written agreement.  Weyerhaeuser was to pay for the works in accordance with a “rate notification”.   The works contract required Riggs and Butler to invoice Weyerhaeuser based on the hours of operation of the machines utilised in the works.

[2]      By  those  contracts  Weyerhaeuser  has  paid  Riggs  and  Butler  more  than

$8,375,000 to date.

WEYERHAEUSER NEW ZEALAND INCORPORATED V ALAN RIGG CONTRACTING LIMITED AND ANOR HC NEL CIV-2007-442-000142  30 March 2007

The Dispute

[3]      A dispute has arisen regarding Weyerhaeuser’s liability to pay invoices in the sum of $220,137.80 for invoices dated February 2007.  Prior to that, and for nearly three years, Riggs and Butler had issued invoices which were promptly paid.   The issue over the February 2007 invoices highlighted, for Weyerhaeuser, concerns they say they had for the accuracy of invoice charging.  Weyerhaeuser claims that from about mid-2006 it became concerned that the number of hours being invoiced by Riggs and Butler exceeded the number of hours recorded on monitors installed on Riggs and Butler equipment.  There was a discussion between the parties on about

15  August  2006.   Before then,  Weyerhaeuser  states,  they resolved  to  engage  a suitably qualified professional to conduct a comparison of records from independent sources with the hours charged by Riggs and Butler.   This inquiry also compared machine hours invoiced against machine hours recorded on each machine’s monitor. In the result of those investigations, Weyerhaeuser claims Riggs and Butler have overcharged by a sum exceeding considerably the amount Riggs and Butler claims was due by their February invoice.

[4]      Following discussions between the parties, Weyerhaeuser offered to pay the February 2007 invoices less a sum of about $88,000 which they claimed was overcharged and  for  which  no  explanation  could  be  given.    This  was  to  occur pending further investigations.

[5]      Those further  investigations, they say,  concerned the  fact  that  Riggs and Butler were charging machine use time over that period during which its employees were taking “smoko”.  Further checks, they state, reveal charges for a period of time when the machines were not in use but rather were “warm-ups” or “warm-downs”. Those factors were additional to the “unexplained” $88,000 which Weyerhaeuser refused to pay.

[6]      Weyerhaeuser had employed the services of a private investigator, Mr Milne. His report indicated a “pattern of substantial overcharging”.

[7]      When Weyerhaeuser would not pay the February invoice they were served with a statutory demand.   In defence of an application to set that aside Riggs and Butler claim:

i)        No  genuine  dispute  arises  concerning  the  debt.     It  is  a liquidated sum due under a monthly invoice that has not been challenged and in fact in the past has been accepted as due and payable.

ii)       Weyerhaeuser’s    counterclaim    is    speculative,     for    an unliquidated damages sum, is without foundation, and is rigorously disputed.

iii)      The  counterclaim  quantum  does  not  equal  or  exceed  the quantum of the debt.  Elements of unfairness or undue pressure come from Weyerhaeuser and not from Riggs and Butler.

The Evidence

[8]      Ms Riggs has provided an affidavit on behalf of Riggs and Butler.   She is responsible  for the accounting  and  invoicing of the contract  works.    She  states Weyerhaeuser has until now always paid their invoices each month, after checking invoices supplied.   Further, Weyerhaeuser did regular audits on a three-monthly basis, following which no concerns have ever been raised.

[9]      Ms  Riggs  says  Weyerhaeuser  approved  the  February  2007  invoices  for payment, but wanted to deduct about $88,000 plus GST by way of counterclaim.  To her mind Weyerhaeuser have not at all previously denied responsibility for payment. Vigorous correspondence was exchanged between the parties’ lawyers until the statutory demand was issued.

[10]     Ms   Riggs   offered   her   own   view   of   Weyerhaeuser’s   complaints   of overcharging.  When Riggs and Butler took over the contract from another in 2004 they started by using the previous contractors “bush docket” forms.  They were used as the basis for rendering monthly invoices to Weyerhaeuser.  The bush dockets were

an on-site recording of how much time was spent on site with each machine.  From those bush dockets, Ms Riggs constructed the monthly invoice to Weyerhaeuser. She used the hours from the dockets for each machine to invoice charges to Weyerhaeuser.  She said, “This is how things have always been done in the forestry industry”.  Ms Riggs says Weyerhaeuser regularly audited their invoices.  At no time until August 2006 was any concern raised regarding the invoices.  She added that the only matter discussed of any relevance to invoicing was an intention in the future to move to computer-generated invoicing from GPS technology, once such a system was available and once both parties agreed upon an appropriate system to be employed.

[11]   In August 2006 Ms Riggs assisted Mr Milne, Weyerhaeuser’s private investigator, with the provision of various information and documentation relating to the period from the beginning of the contract in 2004.   She says Riggs and Butler co-operated fully with Mr Milne’s investigation.

[12]     She recalls a meeting in December 2006 in which Mr Milne’s report was tabled.   She recalls a reference in the report in which Riggs and Butler’s charges were compared with individual machine hour clocks.   She recalls reference to a claim of overcharging in the figure estimated at $607,000.  Subsequently she spent some time with Mr Milne pointing out various errors and flaws with his calculations.

[13]     For the purposes of this proceeding her explanation is:

i)        As before, she had rendered invoices based upon bush docket hours.  She said there is no contractual obligation to charge on the basis of machine clock hours.  They were never asked to do otherwise.

ii)       It is industry practice to include a half-hour smoko each day in the charges rendered for use of machines.

iii)      It is industry practice to charge for “warm-ups” and “warm- downs” of machines.  It is a safety issue “and everyone does it”.

[14]     Ms Riggs does not accept there has been any overcharging at all.

[15]     This  month,  Ms  Riggs  has  undertaken  a  thorough  reconciliation  of  all invoices for the two and a half years to August 2006.  Any evidence of overcharging, she  says,  was  inconsequential.    That  reconciliation  compared  bush  dockets  to invoices issued.

[16]     Since  Weyerhaeuser  has  raised  its  allegations  Riggs  and  Butler  have indicated they would thereafter stop charging for “smokos”.  This notwithstanding, on 7 March 2007 Weyerhaeuser gave notice of termination of the contract.

Riggs and Butler submissions

[17]     Mr Downing, for Riggs and Butler, submits the alleged counterclaim (in an amount which exceeds the statutory demand amount) is speculative, is for an unliquidated damages claim and lacks merit.

[18]     He submits:

i)        Weyerhaeuser had always previously accepted invoices based upon charges calculated in accordance with “bush dockets”.

ii)       Not  until  August  2006  was  it  asserted  that  the  contract required  the  hourly  rates  to  be  based  on  a  reading  of mechanical hour clock time rather than being based on bush dockets.  There is no contractual basis for such a claim.

iii)      Previous charges based on bush dockets included charges for a half-hour smoko each day and for warm-ups and warm-downs of machines.   Those practices were also adopted by other contractors to Weyerhaeuser.

iv)      Because  Weyerhaeuser  paid  invoices  on  the  basis  of  past practice, they were stopped from challenging that  basis  for future payments.

[19]     Mr Downing submits Weyerhaeuser has the onus of establishing  it  has a fairly arguable basis to resist liability for the amount claimed.   He says something more is needed than an arguable case to set aside a statutory demand.  To impeach a statutory demand something more is needed than the mere assertion that there is an available set-off: there must be evidence showing a real basis for a claim of set-off, such that it is clear and persuasive.  Mr Downing refers to the accepted standard that the amount claimed by way of set-off must be equal to or exceed the opposite claim of the amount that is due.

[20]    Obviously a set-off or counterclaim in an unquantified sum will attract considerable scrutiny from a Court.  By Mr Downing’s estimation, Weyerhaeuser’s claim would at best amount to about $67,000 without the “smoko” factor (Ms Riggs claims the figure of $88,000 ought to be $67,000).  Regardless, either sum is well short of the liquidated sum claimed by the Riggs and Butler invoice.

[21]   Riggs and Butler’s fall-back position is that if the sum of $220,000 approximately is not due, then at least, by Weyerhaeuser’s own calculations, the sum of $121,000 approximately is to be paid.   Mr Downing says there is no dispute regarding payment of that sum.

Considerations and reasons for decision

[22]     The contracts binding the parties required charges based upon the hours of operation of the machines utilised by Riggs and Butler.  As well, Weyerhaeuser was required to pay “all ancillary costs associated with providing the services”.   The contract unhelpfully did not specify that charges could only be made for hours when the machine was at work.  Also, the parties clearly anticipated the continued use of the bush dockets when their contract was made.

[23]     For  some  time  prior  to  Weyerhaeuser’s  challenge  of  the  February  2007 invoices there had been communication and correspondence between the parties regarding the implementation of a system to supplant that based upon the issue of “bush dockets”.  It was agreed a qualified professional would be engaged to conduct a comparison of available records from independent sources, for comparison with the hours charged  by  Riggs  and  Butler.    Discussion  included  the  use  of electronic monitors available on the machines, satellite linked recording systems, and others.

[24]     Although Weyerhaeuser had faithfully met invoices rendered when due, the investigations which followed from August 2006 suggested a pattern of significant overcharging.  This investigation did not suggest deliberate overcharging, but rather the charging for use which may not be within acceptable trade practice.  The parties disagree whether machine use could be charged when smoko breaks were taken. That disagreement has much significance in this case, for it accounts for the single largest element of Weyerhaeuser’s calculation of $261,000 they claim was overcharged.

[25]     Weyerhaeuser states that  in March 2007  it  was resolved  it  would  in the interim deduct about $88,000 on account of perceived overcharging: it says pending further investigations.   Weyerhaeuser remains committed to the view the extent of overcharging not only equals, but may considerably exceed, the value of invoices already paid.  To describe that claim as unliquidated is to put a gloss on the effort made to calculate it.  It is based on a comparison of actual machine hours compared to hours invoiced.   Of the machines investigated, an overall average of 8.3% was calculated.  That is a significant factor.  And the enquiry still continues.

[26]     To impeach a statutory demand a company must be able to do more than simply assert there is an available set-off.   It must point to evidence showing a realistic basis for a claimed set-off.  In colloquial terms, it must be shown there is a “genuine and substantial dispute”.

[27]     I am of the clear view this matter is not properly one for a Company’s Act procedure, but rather should be adjudicated upon in the ordinary jurisdiction of this Court.

[28]     Complaints by Riggs and Butler that no action has until now been taken to challenge the accounts can be explained by the fact until recently no evidence has been provided as a basis for which that challenge could be made.  Also, the offer to pay the February invoices in a reduced sum did not  indicate acceptance of past charging practices.   The issue of the statutory demand appeared to harden Weyerhaeuser’s resolve to pay no more than might properly be due.

[29]     The evidence suggests that claims of industry practice permitting charges for “smoko” and “warm-ups” and “warm-downs” are, on the basis of evidence provided, at large.  If those charges are industry practice, then the custom of charging must be certain, it must be reasonable, and must be proved by clear and convincing evidence. I am not satisfied that evidence is available at this time.

[30]     My feeling is that a contract that requires for charges to be based upon the hours  of  machinery  operation  may  not  correspond  with  “bush  dockets”  which purports to record the hours for which invoices have issued.  It is an open question whether the “bush dockets” are consistent with the terms of the express contract.

Judgment

[31]     The application to set aside the statutory demand is granted.

[32]    Weyerhaeuser claims for costs on a solicitor and client basis.   That is inappropriate.   It is hardly surprising that Riggs and Butler would not accept Weyerhaeuser’s view of reasons why the statutory demand should be withdrawn. Before then, for two and a half years, their invoices had been unchallenged.   It matters not that Weyerhaeuser’s solicitors had invited Riggs and Butler’s solicitors to withdraw the statutory demand.   They could hardly have been criticised for not accepting that invitation.

[33]     Costs shall be payable to Weyerhaeuser on a category 2B basis together with disbursements as fixed by the Registrar.

Actions
Download as PDF Download as Word Document


Cases Citing This Decision

0

Cases Cited

0

Statutory Material Cited

0