Waiora Trading Limited v O'Sullivan

Case

[2014] NZHC 304

27 February 2014

No judgment structure available for this case.

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY

CIV-2013-404-3593 [2014] NZHC 304

BETWEEN

WAIORA TRADING LIMITED

Plaintiff

AND

GREGORY LAURENCE O'SULLIVAN First Defendant

IGOR ALEXANDROVICH M IKITASOV Second Defendant

Hearing: 26 February 2014

Appearances:

R C Mark for plaintiff

No appearance for first defendant (abides decision of Court) No appearance for second defendant

Judgment:

27 February 2014

JUDGMENT OF LANG J

[on application for judicial review]

This judgment was delivered by me on 27 February 2014 at 10.30 am, pursuant to Rule 11.5 of the High Court Rules.

Registrar/Deputy Registrar

Date……………

WAIORA TRADING LIMITED v O'SULLIVAN & MIKITASOV [2014] NZHC 304 [27 February 2014]

[1]      Mr Mikitasov owns a house property in Paihia.  In June 2009, he arranged for Mr John Nicholas to carry out urgent repairs to his property.  Mr Mikitasov was not satisfied with the standard of workmanship of the repairs, and he also considered that he  had  been  significantly  overcharged  in  relation  to  them.    This  has  led  to  a protracted dispute between Mr Mikitasov and Mr Nicholas that remains on foot nearly five years later.

[2]      In May 2010, Mr Mikitasov issued proceedings in the District Court.   He named both Mr Nicholas and the plaintiff, Waiora Trading Limited (“Waiora”), as defendants.     Mr  Nicholas  and  his  wife  are  the  directors  of  Waiora.    Those proceedings became protracted, and on 30 May 2013 Mr Mikitasov changed tack. Rather than proceed to trial in the District Court, he issued an adjudication claim against  both Waiora  and  Mr  Nicholas  under  the  provisions  of  the  Construction Contracts Act 2002 (“the Act”).  The first defendant, Mr O’Sullivan, was appointed to adjudicate the claim.

[3]      Mr Nicholas and Waiora both defended the claim.  Waiora contended that it has nothing to do with Mr Nicholas’ building activities, and that it was therefore never a party to the construction contract between Mr Mikitasov and Mr Nicholas.

[4]      Mr O’Sullivan released his determination on 21 June 2013.  He held that Mr Mikitasov was entitled to be paid the sum of $30,362 inclusive of GST.  He said that that sum was to be payable “by the respondent”.  The adjudicator did not address, however, Waiora’s defence based on the assertion that it was not a party to the construction contract.

[5]      Waiora  now  seeks  judicial  review  of  the  adjudicator’s  determination.    It contends that the adjudicator erred in law in several respects when he failed to deal with its defence to the claim by Mr Mikitasov.   Waiora asks the Court to set the adjudicator’s determination aside to the extent that it purports to render Waiora liable to Mr Mikitasov.

[6]      The adjudicator abides by the decision of the Court.  Mr Mikitasov took no steps  to  defend  the  application  for  judicial  review,  and  the  proceeding  was

accordingly set down for hearing on a formal proof basis.   Two days before the hearing, Mr Mikitasov filed an affidavit in opposition to the application, but he did not appear when the application was called on 26 February 2014.

Scope of judicial review in this context

[7]      There has been some debate regarding the extent to which judicial review is available to challenge a determination made by an adjudicator under the Act.  The issue was effectively settled, however, by the decision of the Court of Appeal in Rees v Firth.1   In that case, the Court of Appeal held that judicial review is not restricted to situations where the applicant alleges that the adjudicator has acted outside his or her jurisdiction.  The Court of Appeal emphasised, however, that Judges should be careful not to allow judicial review proceedings to cut across the scheme of the Act and thereby undermine its objectives.  In this context the Court said:2

[27]    The courts must be vigilant to ensure that judicial review of adjudicators’ determinations does not cut across the scheme of the CCA and undermine its objectives. But this does not mean that judicial review should be limited to instances of “jurisdictional error”. In principle, any ground of judicial review may be raised, but an applicant must demonstrate that the court should intervene in the particular circumstances, and that will not be easy given the purpose and scheme of the CCA. Indeed, we consider that it will be very difficult to satisfy a court that intervention is necessary. As an example,  given  that  an  important  purpose  of  the  CCA is  to  provide  a mechanism to enable money flows to be maintained on the basis of preliminary and non-binding assessments of the merits, it is unlikely that errors of fact by adjudicators will give rise to successful applications for judicial review. In the great majority of cases where an adjudicator‘s determination is to be challenged, the appropriate course will be for the parties to submit the merits of the dispute to binding resolution through arbitration or litigation (or, of course, to go to mediation).

Decision

[8]      The  adjudicator  reached  his  decision  in  the  present  case  based  on  the documents filed by the parties.  These squarely raised the issue that lies at the heart of  the  present  application.     Mr  Mikitasov’s  claim  contained  the  following

paragraphs:

1      Rees v Firth [2011] NZCA 668.

2      Ibid.

4.In early March 2009, Mr Mikitasov and his family intended to live in another part of New Zealand for a few months.  During the time that Mr Mikitasov was to be out of the property, he appointed a property manager Mr SG Seed.

6.On 14 June 2009, the Mr Seed informed Mr Mikitasov that he had engaged Mr Nicholas trading as J Nicholas Builders to carry out the investigations and provide the quote.

7.On 19 June 2009, after the investigation was completed, Mr Mikitasov received an estimate of costs from Mr Nicholas for repairs of around

$30,000 (including materials).   The estimate was in respect of the remedial works specified in the Report and included the cost for the

additional repairs, investigated by Mr Nicholas.

9.On 25 June Mr Mikitasov entered into a contract (the Contract) with Mr Nicholas.   A cash advance payment of $5,000 was paid to Mr Nicholas through Mr Seed.  The Contract indicated that Mr Nicholas was the builder who would do the required remedial work and any other  work  Mr  Mikitasov  requested  of  him  as  directed  by  Mr Mikitasov (the Work).

14.Until  this  point,  interim  payments  for  the  Work  had  been  made through Mr Seed.  Mr Seed now said that all future payments for the Work should be paid directly to Mr Nicholas’ company and provided an encoded bank deposit slip for Waiora trading.

15.At this point Mr Nicholas told Mr Mikitasov that the work undertaken by him was undertaken on behalf of Waiora Trading Limited – his company and that his wife would deal with the accounting aspects.

[9]      The  response  filed  on  behalf  of  Mr  Nicholas  and  Waiora  contained  the following passage:

4.        In the claimant’s description of the dispute at the commencement of the adjudication claim, it is alleged that during the term of the contract Mr Nicholas variously represented himself as acting in his own right and trading as J Nicholas Builders, or as a director and shareholder of Waiora Trading Limited.   Mr Nicholas has never represented himself to Mr Mikitasov as acting in the capacity as director and shareholder of Waiora Trading Limited. Waiora Trading Limited is an entirely separate business, providing tourist accommodation  in  Paihia  and  is  operated  by  Mr  Nicholas’  wife.    Mr Nicholas simply requested that Mr Mikitasov pay Mr Nicholas by depositing funds in the Waiora bank account. The reason for this was that Mrs Nicholas could then administer the payments and pay Mr Seed and suppliers for material.

Mr Nicholas also provided the adjudicator with copies of invoices he had rendered in respect of the repairs. These were rendered by “J L Nicholas Builder”.

[10]     Section 45(c) and (d) of the Act require an adjudicator to consider both the adjudication claim and any response filed in relation to it. As noted above, however, the adjudicator’s determination made no reference at all to the issue of whether Mr Nicholas had entered into the construction contract on behalf of Waiora.   An affirmative answer to that question was obviously required if the adjudicator was to impose liability on Waiora under the contract.   If Waiora was not a party to the contract, it could not be liable to Mr Mikitasov under it.

[11]     The adjudicator’s failure to address this issue was obviously an error, and it could be described in a number of ways.  First, it went to the question of jurisdiction. The adjudicator had no jurisdiction to find Waiora liable under the construction contract unless he first found that it was a party to that contract.   It could also be argued  that  the  adjudicator failed  to  take into  account  a  relevant  consideration, namely the facts raised by Waiora in support of its defence.

[12]     One possible interpretation of the determination is that the adjudicator held that Waiora was a party to the contract.   If that is the case, however, he gave no reasons for reaching that decision.   Failure to give reasons in relation to a critical contested issue of fact may also render the decision amenable to review.3    The fact that the adjudicator referred throughout his decision to Mr Nicholas and Waiora as “the respondent” suggests, however, that he never turned his mind to this critical issue.  He appears to have proceeded on the basis that Waiora and Mr Nicholas were one and the same legal entity, when that was patently not the case.

[13]     Regardless  of  how  the  adjudicator’s  error  is  described,  it  is  potentially amenable to review by the Court.   The only remaining issue to be determined is whether relief should be granted.  This requires the Court to consider whether the granting of relief in the present context would undermine the objects and purposes of

the Act.

3      See Canam Construction Ltd v La Hatte [2010] 1 NZLR 848 for a discussion of the scope of the duty to give reasons under s 47 of the Construction Contracts Act 2002.

[14]     Two factors are relevant in this context.   The first is that this particular construction contract is now at an end.  The cash flow considerations referred to in the passage cited above from Rees v Firth therefore do not arise.4   The second arises out of the fact  that  a  conclusion  reached  in  an  adjudication  under the Act  can properly  be  regarded  as  provisional,  in  the  sense  that  both  parties  are  free  to challenge it through subsequent litigation or arbitration.   As the Court of Appeal recognised in Rees v Firth in the same passage, the scheme of the Act anticipates that these  will  usually  be  the  most  appropriate  means  by  which  to  challenge  the

preliminary and non-binding conclusions reached by an adjudicator.

[15]     There  is,  of  course,  nothing  to  prevent  Waiora  from  issuing  a  fresh proceeding in the District Court or High Court seeking a declaration that it was not a party to the construction contract with Mr Mikitasov.   I do not consider, however, that it would cut across or undermine the objects and purposes of the Act if the Court was  to  make  an  order  in  the  present  proceeding  requiring  the  adjudicator  to determine that issue.  This is particularly so given the fact that the adjudicator ought to have considered and determined it as part of his original adjudication.

[16]     I have therefore  concluded  that  the issue of Waiora’s  liability should  be remitted to the adjudicator for determination.  Counsel for Waiora agrees that this is appropriate.  It would be wrong for the Court to go further and endeavour to decide a contested factual issue of this nature on the basis of the material on the Court file. That should properly be the task of the adjudicator, who has the ability to test and weigh the arguments for both parties.  In particular, the adjudicator will need to reach a view one way or another as to whether Mr Nicholas told Mr Mikitasov that he was undertaking the work on Waiora’s behalf.   That issue cannot realistically be determined in the context of the present proceeding.

Result

[17]     The application is granted.  The adjudicator’s determination is set aside to the extent that it purports to render Waiora liable to Mr Mikitasov.  The issue of whether

Waiora is liable to Mr Mikitasov is remitted to the adjudicator for determination.

4      Rees v Firth, above n 1.

Costs

[18]     Counsel for Waioroa does not seek an award of costs in his client’s favour. Costs will accordingly lie where they fall.

Lang J

Solicitors:

Actions
Download as PDF Download as Word Document


Cases Citing This Decision

0

Cases Cited

1

Statutory Material Cited

1

Rees v Firth [2011] NZCA 668