| IN THE COURT OF APPEAL OF NEW ZEALAND I TE KŌTI PĪRA O AOTEAROA |
| CA695/2022 [2023] NZCA 377 |
| BETWEEN | UNITED CIVIL CONSTRUCTION LIMITED |
| AND | HAYFIELD SHA LIMITED (IN LIQUIDATION) |
| Hearing: | 24 July 2023 |
Court: | Collins, Lang and Woolford JJ |
Counsel: | P F Dalkie and M Holland for Appellant |
Judgment: | 22 August 2023 at 9.30 am |
JUDGMENT OF THE COURT
AThe appeal is dismissed.
BThe appellant must pay the respondent costs on a Band A basis for a standard appeal together with usual disbursements. We certify for second counsel.
____________________________________________________________________
REASONS OF THE COURT
(Given by Lang J)
The appellant, United Civil Construction Ltd (United Civil), is the principal creditor in the liquidation of the respondent, Hayfield SHA Ltd (in liquidation) (Hayfield). The sum owing to United Civil currently amounts to approximately 80 per cent of Hayfield’s total indebtedness to creditors.
United Civil is dissatisfied with the actions, or lack of action, taken by the liquidators in several respects. It applied to the High Court for orders under the Companies Act 1993 (the Act) that it contended were necessary to resolve its concerns.
In a judgment delivered on 28 November 2022, Associate Judge Gardiner dismissed each of United Civil’s applications.[1] United Civil appeals against the Associate Judge’s decision.
Background
[1]United Civil Construction Ltd v Hayfield SHA Ltd (in liq) [2022] NZHC 3130 [High Court judgment].
Hayfield was incorporated to assist 14 landowners to obtain a change of zoning so as to permit the development of land situated in Karaka for residential housing. The landowners entered into contracts with Hayfield under which they agreed to fund the construction of water supply and wastewater reticulation systems that were necessary to enable the land to be developed for that purpose. Hayfield then entered into a contract with United Civil for the construction of the infrastructure.
The work was to be carried out in two stages. However, difficulties arose on several fronts. United Civil ceased work under the construction contract in December 2018 and formally suspended work in February 2019. Hayfield was then placed in receivership on 4 April 2019 and in liquidation the following day. The receivers subsequently retired after recovering the amount owing to the secured creditor by whom they were appointed. They paid the sum of approximately $277,000 to the liquidators.
The liquidators have endeavoured to continue with the work necessary to complete the installation of the infrastructure. This involved negotiating with stage one and stage two landowners to recover amounts owing under the funding agreements. The liquidators have now recovered those sums from all but one of the stage one landowners. However, they have found it difficult to recover sums owing by the stage two landowners.
United Civil contends the time has now come for the liquidators to cease negotiating with landowners in default. It wants the liquidators to issue proceedings in the High Court to recover any sums that remain owing. It sought an order under s 284(1)(b)…
Keep reading for free
Create a free CaseChat account to read United Civil Construction Limited v Hayfield Sha Limited (in... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2023] NZCA 377
- Decision Date
CaseChat Overview and Summary
The Court of Appeal found that the liquidators' decision to continue negotiating with the landowners was not unreasonable, as negotiation was a sensible strategy given the complex situation and the landowners' incentives to complete the infrastructure. The Court held that the delay in resolving the issues did not justify switching to litigation, as litigation would be expensive, uncertain, and time-consuming. The Court also found that the liquidators' decision to not permit adjudication proceedings was appropriate, as most of the claims could be resolved through negotiation or referral to the adjudicator. Finally, the Court held that there was no good reason to order the liquidators to provide copies of the funding agreements, as United Civil could not demonstrate how access to those agreements would materially assist it.
The Court of Appeal dismissed the appeal and ordered United Civil to pay the respondent's costs. The Court certified for second counsel.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi