The Rintoul Group Limited v Far North District Council

Link copied
Case Copied 18 min read

IN THE HIGH COURT OF NEW ZEALAND WHANGAREI REGISTRY

CIV-2016-488-130 [2017] NZHC 364

UNDER The Arbitration Act 1996

IN THE MATTER

of an arbitration before John Walton

BETWEEN

THE RINTOUL GROUP LIMITED Plaintiff

AND

THE FAR NORTH DISTRICT COUNCIL Defendant

Hearing: 10 February 2017

Counsel:

R C Mark for Plaintiff
G J Christie for Defendant

Judgment:

9 March 2017

JUDGMENT OF WHATA J

This judgment was delivered by me on Tuesday 9 March 2017 at 4.00 pm pursuant to Rule 11.5 of the High Court Rules.

Registrar/Deputy Registrar

Date:………………………….

Counsel/Solicitors:

R C Mark, Barrister, Kerikeri

G J Christie, Simpson Grierson, Auckland

THE RINTOUL GROUP LIMITED v THE FAR NORTH DISTRICT COUNCIL [2017] NZHC 364 [9 March

2017]

[1]      The Rintoul Group Limited (Rintoul) and the Far North District Council (FNDC) arbitrated a dispute about a construction contract.  The arbitrator resolved all issues in favour of the FNDC.  Rintoul now seeks leave to appeal in respect of four issues, namely:

(a)      Whether  the  arbitrator  was  correct  to  find  that  the  defendant’s requirement  for  a  producer  statement  design  (PS1)  for  temporary piling was not a variation of the contract;

(b)      Whether the arbitrator was correct to find that the FNDC was not

required to procure the plaintiff’s access to the site;

(c)      Whether   the   arbitrator   was   correct   to   determine   the   FNDC’s counterclaim was proven, simply on the grounds that Rintoul’s claim failed; and

(d)Whether the arbitrator erred in finding that the FNDC was entitled to liquidated damages.

[2]      I have resolved to not allow leave to appeal.  My reasons follow.

Background

[3] During July, August and September 2014, there was an extreme weather event which caused a number of slips in the Far North. Two of these slips were on Mangakahia Road. The FNDC tendered for contracts for the two slips together, as the traffic management plans for the two contracts would overlap due to the proximity of the two slips. The documentation provided that one live lane of traffic was to be maintained at all times during the work. The contractor would also have to comply with all statutory requirements, including the Building Act 2004, and the requirements of the Code of Practice for Temporary Traffic Management (CoPTTM), published by the NZTA.

[4]      Rintoul was the preferred tenderer.  The dispute which was the subject of the arbitration concerned only the two contracts referred to at [3] (contracts 7-14-115 and 7-14-116).

[5]      Issues arose as to Rintoul’s proposed traffic management plan for contract

115, particularly in relation to visibility for two lanes of traffic and insufficient width. The FNDC rejected an initial proposed traffic management plan as it believed it did not properly deal with the period for installation of temporary works (steel piling) and it pointed out that as the steel piling was to retain the road, a PS1 would be required under the Building Act 2004. A revised traffic management plan was later approved by the FNDC, subject however to agreement being reached with Downer to provide traffic control while…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read The Rintoul Group Limited v Far North District Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2017] NZHC 364
Decision Date

CaseChat Overview and Summary

The Rintoul Group Limited (Rintoul) sought leave to appeal an arbitration decision in its dispute with the Far North District Council (FNDC) over a construction contract. The High Court, presided over by Whata J, considered four issues raised by Rintoul regarding the arbitration outcome. These were: whether the requirement for a producer statement design (PS1) for temporary piling was a variation of the contract; whether the FNDC was required to procure the plaintiff's access to the site; whether the FNDC's counterclaim was proven simply on the grounds that Rintoul's claim failed; and whether the arbitrator erred in finding that the FNDC was entitled to liquidated damages. The Court found that Rintoul had not demonstrated a sufficiently strong case on any of these issues to warrant leave to appeal. The Court held that the FNDC was entitled to require a PS1 as it was entirely reasonable to point out that a PS1 was necessary. The Court also found that it was Rintoul's responsibility to manage traffic and that the FNDC was not required to procure the plaintiff's access to the site. Regarding the counterclaim, the Court held that the arbitrator's reasoning was sufficient and that the only issue was one of quantum, which did not present a question of law. Finally, the Court held that the claim for liquidated damages was properly resolved by the arbitrator as it was pleaded and the issue of jurisdiction was not deficient. The Court dismissed the application for leave to appeal and granted the application to enter the awards as judgments.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established