IN THE HIGH COURT OF NEW ZEALAND WHANGAREI REGISTRY
CIV-2016-488-130 [2017] NZHC 364
UNDER The Arbitration Act 1996 IN THE MATTER
of an arbitration before John Walton
BETWEEN
THE RINTOUL GROUP LIMITED Plaintiff
AND
THE FAR NORTH DISTRICT COUNCIL Defendant
Hearing: 10 February 2017 Counsel:
R C Mark for Plaintiff
G J Christie for DefendantJudgment:
9 March 2017
JUDGMENT OF WHATA J
This judgment was delivered by me on Tuesday 9 March 2017 at 4.00 pm pursuant to Rule 11.5 of the High Court Rules.
Registrar/Deputy Registrar
Date:………………………….
Counsel/Solicitors:
R C Mark, Barrister, Kerikeri
G J Christie, Simpson Grierson, Auckland
THE RINTOUL GROUP LIMITED v THE FAR NORTH DISTRICT COUNCIL [2017] NZHC 364 [9 March
2017]
[1] The Rintoul Group Limited (Rintoul) and the Far North District Council (FNDC) arbitrated a dispute about a construction contract. The arbitrator resolved all issues in favour of the FNDC. Rintoul now seeks leave to appeal in respect of four issues, namely:
(a) Whether the arbitrator was correct to find that the defendant’s requirement for a producer statement design (PS1) for temporary piling was not a variation of the contract;
(b) Whether the arbitrator was correct to find that the FNDC was not
required to procure the plaintiff’s access to the site;
(c) Whether the arbitrator was correct to determine the FNDC’s counterclaim was proven, simply on the grounds that Rintoul’s claim failed; and
(d)Whether the arbitrator erred in finding that the FNDC was entitled to liquidated damages.
[2] I have resolved to not allow leave to appeal. My reasons follow.
Background
[3] During July, August and September 2014, there was an extreme weather event which caused a number of slips in the Far North. Two of these slips were on Mangakahia Road. The FNDC tendered for contracts for the two slips together, as the traffic management plans for the two contracts would overlap due to the proximity of the two slips. The documentation provided that one live lane of traffic was to be maintained at all times during the work. The contractor would also have to comply with all statutory requirements, including the Building Act 2004, and the requirements of the Code of Practice for Temporary Traffic Management (CoPTTM), published by the NZTA.
[4] Rintoul was the preferred tenderer. The dispute which was the subject of the arbitration concerned only the two contracts referred to at [3] (contracts 7-14-115 and 7-14-116).
[5] Issues arose as to Rintoul’s proposed traffic management plan for contract
115, particularly in relation to visibility for two lanes of traffic and insufficient width. The FNDC rejected an initial proposed traffic management plan as it believed it did not properly deal with the period for installation of temporary works (steel piling) and it pointed out that as the steel piling was to retain the road, a PS1 would be required under the Building Act 2004. A revised traffic management plan was later approved by the FNDC, subject however to agreement being reached with Downer to provide traffic control while…
Keep reading for free
Create a free CaseChat account to read The Rintoul Group Limited v Far North District Council and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] NZHC 364
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi