IN THE HIGH COURT OF NEW ZEALAND WELLINGTON REGISTRY
CIV-2014-485-001474 [2014] NZHC 213
UNDER the Judicature Amendment Act 1972
IN THE MATTER of an Application for Judicial Review
BETWEEN TELCO TECHNOLOGY SERVICES LIMITED
Applicant
ANDMINISTRY OF EDUCATION Respondent
Hearing: 17 February 2014
Counsel: V L Heine and B A Davies for Applicant
A Williams with C Fleming and R Wanigasekera for
Respondent
Judgment: 19 February 2014
JUDGMENT OF COLLINS J
Introduction
[1] Telco Technology Services Ltd (Telco) has applied for an interim injunction. The interim injunction seeks to prevent the Ministry of Education (the Ministry) from giving effect to its decision to appoint another company to be solely responsible for implementing the final phase of The Schools’ Network Upgrade Project (the project).1
[2] I have decided to grant an interim injunction because Telco has established:
(1)There is a serious question to be tried in relation to its application for judicial review.
1 Referred to in the contract documents as the SNUP project.
TELCO TECHNOLOGY SERVICES LIMITED v MINISTRY OF EDUCATION [2014] NZHC 213 [19
February 2014]
(2) An interim injunction is necessary to preserve Telco’s position.
(3)The overall justice of the case favours the granting of an interim injunction.
[3] Telco has established that it is seriously arguable it tendered on the basis that the Ministry’s Request for Proposals (RFP) said it intended to appoint two or three suppliers to complete the final phase of the project. After the tender process concluded the Ministry advised Telco only one supplier would be appointed. The basis on which Telco would have costed its proposal is likely to have been significantly different had it known the Ministry was willing to appoint one supplier. There is a serious question as to whether or not the Ministry’s RFP for the project created a procedural expectation that if only one provider was going to be appointed Telco would be given the opportunity to amend its proposal to reflect this change.
[4] Telco is likely to suffer from the lack of opportunity to have tendered for the final phase of the project on the basis that the Ministry was willing to appoint one supplier.
[5] Issuing an interim injunction will cause some delay, uncertainty and inconvenience. However, I am satisfied these consequences can be mitigated appropriately and that the overall justice of the case favours the granting of an interim injunction.
Context
[6] Telco provides information, communications and technology services to schools in New Zealand. Since 2010 Telco has been one of two companies appointed by the Ministry to deliver the first five phases of the project which is designed to provide 97.7 per cent of schools in New Zealand with ultrafast broadband by December 2015. Telco’s contract under the first five phases of the project is due to expire during the course of 2014.
[7] On 26 August 2013 the Ministry issued its RFP for the delivery of the final phase of the project. It is estimated that approximately 6002 schools will be provided with the…
Keep reading for free
Create a free CaseChat account to read Telco Technology Services Limited v Ministry of Education and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2014] NZHC 213
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi