Teak Construction Group Limited v KMJB Harris Limited

Link copied
Case Copied 24 min read

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY

I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE

CIV-2024-404-2336

[2025] NZHC 700

UNDER the Companies Act 1993

IN THE MATTER

of an application to set aside a statutory demand

BETWEEN

TEAK CONSTRUCTION GROUP LIMITED

Applicant

AND

KMJB HARRIS LIMITED

Respondent

Hearing: 4 March 2025

Appearances:

A J B Holmes for Applicant

N P Tetzlaff and D R Lang for Respondent

Judgment:

28 March 2025


JUDGMENT OF ASSOCIATE JUDGE PAULSEN


This judgment was delivered by me on 28 March 2025 at 3.00 pm pursuant to r 11.5 of the High Court Rules.

Registrar/Deputy Registrar Date:

TEAK CONSTRUCTION GROUP LIMITED v KMJB HARRIS LIMITED [2025] NZHC 700 [28 March 2025]

[1]                  Teak Construction Ltd (Teak) was engaged to build a factory extension at Penrose. KMJB Harris Ltd (KMJB) undertook earthworks for Teak on the project and issued monthly payment claims. KMJB issued a statutory demand to Teak in respect to its payment claim 22. This judgment concerns Teak’s application to set aside the statutory demand.

[2]                  KMJB says Teak failed to respond to payment claim 22 with a payment schedule within 20 working days as required by s 22 of the Construction Contracts Act 2002 (the Act) and became liable to pay the claimed amount which, under s 23 of the Act, is a debt due.

[3]                  Teak says under its subcontract with KMJB it was to provide payment schedules within 25 working days from the last day of the month in which payment claims were served, and it did so. It also says its payment schedule 22 certified that the amount to be paid was a negative sum and there is no amount due and owing to KMJB.1 In the alternative, Teak says that if the parties did not enter into a subcontract because they failed to agree on essential terms the Act does not apply and KMJB is limited to a claim in quantum meruit.2

[4]                  The issue is whether Teak has established it is fairly arguable that the amount of payment claim 22 is not due and owing. This requires consideration of whether Teak and KMJB entered into a subcontract for the performance of the earthworks, and if so on what payment terms.

Background facts

[5]                  The facts were helpfully set out in Mr Holmes’ written synopsis, which for present purposes I have utilised with changes where necessary.


1      Construction Contracts Act, s 24. Counsel for KMJB confirmed that the statutory demand relies upon the alleged failure by Teak to respond to the payment claim on time. I understand it is accepted by KMJB that if that argument fails the sum demanded is genuinely disputed.

2      Canam Construction (1995) Ltd v LaHatte [2010] 1 NZLR 848 (HC) at [41]–[46]; M van der Wal Builders & Contractors Ltd v Walker HC Auckland CIV-2011-004-083 at [84]; and Finesse Residential Ltd v Vasanthan [2013] NZHC 3202.

[6]                  Teak is a construction company and engaged KMJB as a subcontractor for excavation and…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Teak Construction Group Limited v KMJB Harris Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2025] NZHC 700
Decision Date

CaseChat Overview and Summary

Teak Construction Group Limited (Teak) applied to the High Court of New Zealand to set aside a statutory demand issued by KMJB Harris Limited (KMJB) for an amount of $401,215.06. The dispute arose from a subcontract between Teak and KMJB for earthworks on the Penrose Project. KMJB claimed Teak failed to respond to payment claim 22 within the required time frame under the Construction Contracts Act 2002, making the claimed amount a debt due. Teak argued it provided payment schedules within the terms agreed in their subcontract, and the amount claimed was disputed. The central issue was whether Teak and KMJB entered into a binding subcontract and, if so, on what payment terms.

The court found that it was fairly arguable that Teak and KMJB entered into a subcontract agreement, with payment terms specified in the subcontract agreement provided by Teak on 25 October 2022. The court noted that Teak had consistently provided payment schedules within the terms agreed in their subcontract, including in response to payment claim 22. The court rejected KMJB’s argument that the payment terms of the New Zealand Standard (NZS) 3910:2013 applied, finding no evidence that the parties intended to contract on that basis. The court concluded that Teak had demonstrated a substantial dispute over its liability for the amount claimed, and thus the statutory demand was set aside under s 290(4)(a) of the Companies Act 1993. The court also noted that Teak would likely be entitled to costs.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.