| IN THE COURT OF APPEAL OF NEW ZEALAND |
| CA40/2017 [2017] NZCA 305 |
| BETWEEN | ZHANLI TANG WEINMIN ZHOU |
| AND | BODY CORPORATE 183930 SYNERGISTIC INVESTMENTS LIMITED |
| Hearing: | 26 June 2017 |
Court: | No appearance for Appellants |
Counsel: | Miller, Lang and Mander JJ |
Judgment: | 18 July 2017 at 3.00 pm |
JUDGMENT OF THE COURT
A The application for leave to adduce new evidence is granted.
B The cross-appeal is allowed.
CThe scheme approved by the High Court is varied to the extent that the revised sch 3 shall be the schedule referred to in cl 8 of sch 1 to the scheme approved by that Court on 14 December 2016.
____________________________________________________________________
REASONS OF THE COURT
(Given by Lang J)
This appeal concerns a residential apartment complex known as “Tuscany Towers”. The complex comprises 97 units constructed in 16 separate blocks.
The complex has suffered significant damage through water ingress. Body Corporate 183930, the body corporate constituted under the Unit Titles Act 2010 (the Act) to manage the affairs of the complex, began the remedial work necessary to repair that damage. The body corporate initially paid for the remedial work by means of levies imposed on unit owners and funds recovered through the settlement of proceedings it had issued in the Weathertight Homes Tribunal against third parties involved in the construction of the complex (the WHT proceeding). Matters reached the point, however, where the settlement proceeds were exhausted before the repairs had been completed.
The body corporate and one of the unit owners then applied to the High Court for approval of a scheme under s 74 of the Act. This would authorise the body corporate to complete the balance of the repairs and to impose further levies on unit owners to meet the resulting costs.
Wylie J approved the proposed scheme in an interim judgment issued on 3 September 2015 (the interim judgment)[1] and a final judgment delivered on 14 December 2016 (the final judgment).[2] The appellants, both of whom are the owners of units in the complex, filed an appeal seeking to challenge several aspects of the final judgment. Ultimately, however, they abandoned their appeal.
[1]Body Corporate 183930 v Chua [2015] NZHC 2122 [HC Interim Judgment].
The body corporate cross-appealed against one aspect of the final judgment. It seeks to pursue the cross-appeal notwithstanding the abandonment of the appeal by the appellants. The appellants have withdrawn their opposition to the body corporate’s cross-appeal. As a result the cross-appeal was argued without opposition.
Background
One of the issues the unit owners were required to determine was the manner in which the cost of the repairs was to be allocated among unit owners. Nine of the unit owners had not been part of the WHT proceeding. Those owners have always acknowledged that they will be required to meet their share of the cost of…
Keep reading for free
Create a free CaseChat account to read Tang v Body Corporate 183930 and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] NZCA 305
- Decision Date
CaseChat Overview and Summary
The central legal issue in the cross-appeal was the appropriate schedule for determining the allocation of repair costs among unit owners. The Remedial Works Agreement (RWA) initially proposed a schedule for contributory negligence percentages, which was later revised. The revised schedule reduced the percentage contributions of some negligent unit owners. The Judge accepted that any shortfall should be funded by negligent owners but decided that the original schedule should govern the scheme. The Court of Appeal, however, allowed the cross-appeal and varied the scheme to adopt the revised schedule.
The Court of Appeal granted leave for new evidence to address the deficiencies in the trial evidence, particularly the explanation for the differing figures in the schedules and when unit owners received the revised schedule. The new evidence, provided by Mr Roger Levie, confirmed that the revised schedule was circulated to all unit owners in June 2011, effectively replacing the original schedule. The revised schedule accurately reflected the matters considered during the mediation and the contributions made towards the settlement sum. It also recognised that funds received from third parties pursued by negligent owners would augment the pool of available funds, mitigating the impact on other unit owners.
Based on the new evidence, the Court of Appeal concluded that the revised schedule should be the operative schedule in the approved scheme. The cross-appeal was allowed, and the scheme was varied to reflect this decision.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.