T & T Drainage Limited v Rennell HC Auckland CIV 2009-404-1506

Case

[2010] NZHC 398

11 March 2010

No judgment structure available for this case.

IN THE HIGH COURT OF NEW ZEALAND

AUCKLAND REGISTRY

CIV-2009-404-001506

BETWEEN  T & T DRAINAGE LIMITED

Appellant

ANDJOHN ALFRED RENNELL AND JUDITH PENELOPE RENNELL

First Respondent And Cross Appellant

ANDEDWARD RITCHIE MICHELL Second Respondent

Hearing:         17 September 2009

Appearances:  B O'Callahan for Appellant

K F Gould for Respondent

Judgment:      11 March 2010 at 4:00 pm

RESERVED JUDGMENT OF COURTNEY J

This judgment was delivered by Justice Courtney

on 11 March 2010 at 4:00 pm pursuant to R 11.5 of the High Court Rules.

Registrar / Deputy Registrar

Date………………………

Solicitors:           Rice Craig, P O Box 72-440, Papakura 2244

Fax: (09) 295-1701
Wilson McKay, P O Box 28-347, Remuera, Auckland
Fax: (09) 524-0397

Counsel:             B O’Callahan, Carter & Partners, P O Box 2137, Auckland

Fax: (09) 366-1363 – [email protected]
K F Gould, P O Box 1011, Shortland Street, Auckland 1140

Fax: (09)358-3093 – [email protected]

T & T DRAINAGE LTD V RENNELL & ANOR HC AK CIV-2009-404-001506  11 March 2010

Tableof Contents

No.

Introduction  [1]

Appeal by T & T on Mr and Mrs Rennell’s counterclaim

Were Mr and Mrs Rennell entitled to counterlciam in their

personal capacities?  [6] Was T & T liable for work not completed?  [13] Did T & T cause damage to the property through negligence

and breach of contract?  [24] Betterment / Unnecessary work  [50] Defences of contributory negligence and volenti  [57] Measure of damages  [61]

Cross-appeal by Mr and Mrs Rennell on counterclaim

Personal liability of Mr Michell  [77]

Interest on counterclaim  [96]
Costs  [97]

Appeal by Mr and Mrs Rennell on T & T’s claim

Valueless work  [102]

Result  [105]

Introduction

[1]      In  early  2005  Mr  and  Mrs  Rennell  engaged  T  &  T  Drainage  Limited  to undertake  work  on  a  property  in  Karaka  which  they  wanted  to  develop  as  an equestrian  centre.   The  work  involved  building  an  arena  and  stables  area  together with  the  associated  drainage  and  earthworks.               T  &  T  ceased  work  after  several months  because  of  non-payment  of  invoices.   Following  a  hearing  before  Andree Wiltens  DCJ  it  obtained  judgment  against  Mr  and  Mrs  Rennell  for  $90,349.52. However,  Mr  and  Mrs  Rennell  successfully  counterclaimed  against  T  &  T  for $247,064.85 being the cost of completing the contract works and remedying damage T  &  T  had  done  to  the  property  during  the  course  of  its  work.  A  counterclaim against T & T’s director, Mr Michell, failed.  T & T and Mr and Mrs Rennell have, respectively,   appealed   and   cross-appealed   the   decision   on   the   counterclaim. Mr and Mrs Rennell have appealed the decision on T & T’s claim.

[2]      On  a  general  appeal  such  as  this  the  appellate  judge  has  an  obligation  to consider the matter afresh and reach his or her own view of the evidence.[1]   However, many of the grounds of appeal, particularly those raised by T & T, relate to factual findings and turned on the assessment of witnesses.   In undertaking my assessment of  the  evidence  I  have  recognised  that  the  Judge  had  the  benefit  of  observing  the witnesses over several days.  In some instances I have, for this reason, deferred to the trial Judge’s factual findings.

[1] Austin Nichols & Co v Stitching Lodestar [2008] 2 NZLR 141

[3]      On  its  appeal  against  the  decision  on  Mr  and  Mrs  Rennell’s  counterclaim, T & T asserts error by the Judge in:

a)        Finding that Mr and Mrs Rennell were entitled to sue in their personal capacities for damage to the property;

b)Finding that Mr and Mrs Rennell could recover the cost of completing work T & T had agreed to do but had neither done nor charged for;

c)        Finding that T & T was negligent in spilling or leaving stones on the property and/or had a contractual obligation to remove the stones;

d)Failing to make a sufficient deduction for betterment as a result of the remedial works;

e)        Applying the wrong measure of damages;

f)        Not accepting T & T’s expert witnesses.

[4]      On their cross-appeal Mr and Mrs Rennell say that the Judge erred in:

a)        Finding that Mr Michell was not personally liable;

b)        Reducing the counterclaim for betterment;

c)        Selecting the date from which interest would run; and d)       Refusing to award costs in their favour.

[5]      On their appeal against the decision on T & T’s claim Mr and Mrs Rennell assert that the Judge erred in finding that any money was owed to T & T in light of the finding of negligence and poor workmanship in breach of implied terms of the contract.

Appeal by T & T on Mr and Mrs Rennell’s counterclaim

Were Mr and Mrs Rennell entitled to counterclaim in their personal capacities?

[6]      T  &  T  had  sued  Mr  and  Mrs  Rennell  personally,  insisting  that  it  had contracted with them in their personal capacities and at trial their counsel conceded that they were personally liable on the contract with T & T.   The counterclaim was also  brought  by  Mr  and  Mrs  Rennell  in  their  personal  capacities. However,  the property  was  owned  by  the  trustees  of  the  J  &  P  Rennell  Family  Trust,  (Mr  and Mrs Rennell and J & P Trustee Co Limited).  The evidence showed that Mr Rennell negotiated  directly  with  T  &  T  and,  in  doing  so,  gave  no  indication  that  he  was

acting other than for himself and his wife in their personal capacities.  There appears not  to  have  been  any  specific  discussion  regarding  ownership  of  the  property. Nevertheless, Mr Rennell gave unchallenged evidence that he had acted throughout in  his  capacity as  a  trustee  and  payments  to  T  &  T  were  made  by cheques  in  the name of the family trust.

[7]      T & T argued that Mr and Mrs Rennell had not suffered any loss personally and therefore could not recover in respect of damage to the property.   It is not clear from the judgment the extent to which this issue was argued at trial, and the Judge did not deal with it directly.  At [31] of the judgment the Judge said:

I find that the Defendants did not make known to the Plaintiff that he was dealing with them as trustees of a Family Trust. All relevant documentation was in the name of the Defendants as individuals, save for the cheques used to make the payments that I have listed earlier.  Despite such cheques being on  behalf  of  the  Trust,  I  am  not  prepared  to  substitute  the  Defendants  as trustees of a Family Trust for them as individuals even though I note that all dealings in relation to the remediation work does appear to have been done with  Mr  and  Mrs  Rennell  as  trustees. I  am  fortified  in  reaching  that conclusion  as,  in  her  final  submissions,  Ms  Meechan  conceded  that  any liability to the Plaintiff must have been incurred by the Mr and Mrs Rennell personally.

[8]      In submitting that Mr and Mrs Rennell had not suffered any loss for which they could sue Mr O’Callahan relied on the decision in Panatown Limited v Alford McAlpine  Construction  Limited[2],  a  case  in  which  the  plaintiff  had  engaged  a contractor to undertake building work on land owned by a third party.   Lord Millett said at [154]:

It is impossible on any logical basis to justify the recovery of compensatory damages by a person who has not suffered the loss in respect of which they are awarded unless he is accountable for them to the person who has.

[2] Panatown Limited v  Alford Construction  Limited  [2000] 4 All ER 97 applied in New Zealand in

Santa Barbara  Homes Limited v  Cozzolino  &  Anor  HC  AK  CIV-2002-404-002577 12  May 2004

Santa Barbara Homes Limited v Cozzolino HC AK CIV-2002-404-002577 16 September 2004

[9]      The general rule that a contracting party cannot recover damages in respect of loss suffered by a third party, however, is subject to certain exceptions, one of which

is a claim by an agent on behalf of an undisclosed principal.[3]   The authors of Law of

[3] Woodar  Investment  Development Limited v  Wimpey Construction  (UK)  Limited [1980]  1  All  ER

571; Panatown Limited v Alford McAlpine Construction Limited [2000] 4 All ER 97

Contract in New Zealand state that:[4]

Where an agent, having authority to contract on behalf of another, makes the contract in his or her own name, concealing the fact that he or she is a mere representative, the doctrine of the undisclosed principle comes into play.

[4] Burrows, Finn & Todd, Law of Contract in New Zealand (3rd  ed, 2007)

[10]     The  relevant  principles  of  the  doctrine  of  the  undisclosed  principal  were summarised by the Privy Council in Siu Yin Kwan & Anor v Eastern Insurance Co Limited:[5]

For present purposes the law can be summarised shortly as follows.  (1) An undisclosed principal may sue and be sued on a contract made by an agent on his behalf, acting within the scope of his actual authority.  (2) In entering into the contract, the agent must intend to act on the principal’s behalf.   (3) The  agent  of  the  undisclosed  principal  may  also  sue  and  be  sued  on  the contract.   Any defence which the third party may have against the agent is available against his principal.  (4) The terms of the contract may, expressly or by implication, exclude the principal’s right to sue and his liability to be sued.  The contract itself or the circumstances surrounding the contract may show that the agent is the true and only principal.

[5] Siu Yin Kwan & Anor v Eastern Insurance Co Limited [1994] 1 All ER (PC) 213 at 219 (PC)

[11]     By the  terms  of  the  trust  deed  the  trustees  had  the  power  to  improve  trust property and to act by a majority if they could not agree unanimously.  Mr Rennell’s assertion  that  he  acted  in  his  capacity as  a  trustee  was  unchallenged  either  by the other trustees or by T & T.   There is no dispute that the trustees paid for both the contracted work and the remedial work.  Although not contended for, I am satisfied on  the  evidence  that  Mr  Rennell  both  had  the  authority to,  and  did,  contract  with T & T on behalf of the trustees.  I conclude that at all material times Mr Rennell was acting as agent for undisclosed principals, namely the trustees of the trust.

[12]     The fact that Mr Rennell was acting as  agent for the trustees does not preclude  personal  liability, as is clear from Siu Yin  Kwan &  Anor v Eastern Insurance Co Limited, so the concession made at trial that Mr and Mrs Rennell were personally liable  was  properly  made. However, they were  entitled to recover damages personally (though  obliged to account  for  monies  received). Ideally this matter would have been dealt with by having the  trustees  joined  as  parties  to  the

proceeding at an earlier  stage.   However, their absence did not preclude the Judge dealing with the matter in the way that he did.

Was T & T liable for work not completed?

[13]     Mr and Mrs Rennell’s counterclaim included a claim for $44,358.58 for work they claim T & T had originally agreed to undertake but did not, necessitating their engaging  another  contractor  to  do  so. T  &  T  maintains  that  the  Judge  erred  in allowing  this  part  of  the  claim  because  it  resulted  in  double  counting. Before  I consider this argument I outline the nature and scope of the work T & T agreed to do.

[14]     The  property  originally  comprised  about  five  hectares   situated   on   the southern side of Linwood Road in Karaka.  In 2006 it was amalgamated with part of

an adjoining property.  Access to the property was by a sealed driveway off Linwood Road  which  led  to  an  existing  dwelling.   The  property  was  to  be  fenced  into  ten paddocks, with paddock 1 adjacent to the road frontage, paddocks 2, 3 and 4 on the eastern  boundary which  adjoined  a  neighbouring  property,  paddocks  5,  6,  7  and  8 running more or less along the southern boundary.   Paddocks 9 and 10 were to be created immediately in front of the house, with an arena and stables situated between them and paddocks 6, 7 and 8.

[15]     The scope of the work was not recorded in a formal contract.  Nor did T & T commit  itself  to  a  quote.   The  work  initially  agreed  on  was  recorded  in  T  &  T’s undated estimate faxed to Mr Rennell on 18 March 2005, namely:

·Construct 60 x 20 metre horse arena with compacted platform for new stable area;

·40  x  1.5  metre  high  retaining  wall  behind  and  alongside  the  stable area;

·         Supply and install drainage to water course;

·Supply  and  install  driveway  access  approximately  150  metres  long with turning circle for horse trucks;

·Supply and  install  1  x  5000  gallon  water  tank  with  Grundfos  pump and water tap for site supply.

[16]     Some extra work was agreed later, namely increasing the width of the arena, removing the knoll in paddock 5 (re-using the top soil to level the lawn and build a haha in front of the house), removing debris and tidying up paddocks 5 and 6 and supplying a sand and rubber mix arena surface.

[17]     Although Mr Gould, for Mr and Mrs Rennell, submitted that the Judge had not found that the contract was on a charge-up basis, it is quite clear that this was the finding and that, on the evidence, it was correct:

[76]     …The   parties   entered   into   their   arrangement   with   the   clear understanding that the estimate prepared originally only related generally to the cost of the work then being considered; and all work over and above that would be separately charged for by the Plaintiff and paid by the Defendants – and further that if the actual work required was more difficult or costly that such additional costs would be borne by the Defendants.

[77]     A telling factor for me is that despite the Defendants’ claim that the estimate  was  a  “fixed  price”  they  have  clearly  paid  much  more  than  the estimated  figure,  even  taking  into  account  the  extras  the  Defendants  have accepted as being properly for them to pay.   The only rational explanation for such over-payment is that the final price was still undetermined.

[18]     A  good  deal  of  the  problems  between  the  parties  arose  as  a  result  of proceeding on  a  charge-up  basis.   The  scope of  the  work  was  ill-defined  and  it  is clear that T & T did not give the kind of careful thought to the likely cost as it would have  had  it  committed  itself  to  a  quoted  price.   The  Judge,  quite  understandably, expressed  his  astonishment  at  a  businessman  of  Mr  Rennell’s  experience  entering into such an arrangement.

[19]     Mr and Mrs Rennell sought $44,358.53 for work to the stormwater system, yard works, stable access road and arena.  The Judge found that:

[93]     The second aspect of this is  the  allegation  that  not  all  the  agreed work was actually done. In particular there was complaint regarding the lack

of installation of a water tank and a Grundfos pump.  The plaintiff accepted that these items were not installed, which I took to be acceptance of a breach

of contract.  However, by way of defence it was pointed out that these items were not charged for.   The Defendants have had to get another company to

complete this task and have now paid for the installation of such items.   As part  of their Counter  Claim the  Defendants  seek to recover such payment. The fact that no charge was made for this seems to me to be no answer to this allegation.

[94]     The third aspect of this allegation is that the plaintiff did not tidy up the site at the end of the contract.  Mr Michell accepts that this was not done; and  accepted  that  the  Defendants  had  a  right  to  expect  this  to  be  done. Again  it  has  been  pointed  out  that  this  has  not  been  charged  for. It  is effectively  part  of  the  Defendants’  Counter  Claim  as  the  work  has  been completed  subsequently  at  the  cost  of  the  Defendants.   I discount  the  fact that the Plaintiff was unable to complete this task due to being denied access –  it  should  have  been  done  as  part  of  the  agreed  work,  the  Plaintiff  had ample time to attend to this and it was later done by others at a cost to the Defendants. The  Defendants  should  in  my  view  be  compensated  for

something they have effectively paid twice for.

[95]     It is plain, as alleged, that when the Plaintiff ceased work at the site

it had not finished off properly the “berms” (the edges of the newly formed accessway).   The  evidence  suggests  they  could  have  been  better  finished although the contrary view was also advanced.  The fact that the project was undertaken during winter and the fact that the work to finish the berms was incomplete due to the dispute regarding payment means very little turns on this point.  The Plaintiff accepts that this was not completed but says it was not  afforded  the  opportunity  to  do  so.  The  time  and  cost  involved  in completing this aspect is unclear but in the overall scheme of things is not material.  In my view, this can be properly considered as part of the clean-up costs.

[96]     My conclusion therefore  is that the  Counter  Claim as  to  breach of contract has been made out in the sense that some of the matters agreed to be done for the estimated cost have not in fact been completed.  The Defendants are  therefore  entitled  to  claim  from  the  Plaintiff  the  reasonable  costs  of making good these matters.

[20]     Mr O’Callahan submitted that these findings  were  inconsistent  with  the Judge’s finding that the contract was on a charge-up basis rather than being a fixed price. There were certain items not charged for by T & T because it stopped work

for non-payment of  earlier  invoices. However,  Mr  O’Callahan  submitted  that  as

T & T had not charged for them it ought not be  liable for the cost of them having been done by the other party.  There could be no suggestion that Mr and Mrs Rennell were paying twice.

[21]     Mr  O’Callahan is correct that Mr  and  Mrs  Rennell  cannot  claim  for  work contracted to be done on a charge-up basis that was not done where T & T had not

rendered any charge for such work and the  cost  of  having  another  contractor complete  it  was  comparable  to  what  T  &  T  would  have  charged.   Whilst  T  &  T might  be  in  breach  of  its  contractual  obligation  to  do  the  work  that  it  would  have been entitled to charge  for, Mr and Mrs Rennell  cannot have suffered  any loss by paying someone else to complete the work.

[22]     It is, however, difficult on the basis of the evidence and submissions before me to ascertain what that figure is.  The Judge awarded a global figure in respect of the   counterclaim   of   $247,064.85   which   included   both   the   significant   cost   of remedying damage done to the site by T  & T,  as well as the cost of uncompleted work.  The Judge calculated the figure as follows:

Paid to Ace Construction Limited & Jesmond

Construction Limited (primarily)  $340,485.73

Less (i)  $ 10,501.00

Less (ii)  $ 49,846.00

Less (iii)  $   2,756.25

Less (iv)  $   1,202.63

Less (v)  $ 29,115.00

Total  $247,064.85

[23]     Of the disallowed items,  however,  only $2,756.25 for the  access-way drain and  $1,202.63  for  the  cesspit  in  the  stables  seem  to  correlate  to  the  items  and amounts claimed by Mr  and Mrs Rennell as work T  & T did not do.   I invite the parties to address this issue further in memoranda, if they are unable to agree on the amount that ought to be deducted as a result of the Judge’s error on this point.

Did  T  &  T  cause  damage  to  the  property  through  negligence  and  breach  of contract?

[24]     I turn next to what was the major issue at trial, namely whether T & T was liable either for breach of contract or in tort for negligence for damage done to the property as a result of its work. There were two main complaints.  The first was that there had been stone contamination and loss of topsoil in the paddocks which left the paddocks in a condition that was unsuitable for agisting horses. The second was that

some of the drainage work was poorly done  and had to be rectified.   Mr and Mrs Rennell expended a substantial sum to restore the site to its expected condition and sought to recover those costs.

[25]     The  specific  aspects  of  damage  alleged  to  have  been  done  or  work  not completed properly were:

·Stone damage in all the  paddocks such as to render them unsuitable for horses;

·Hard   fill,   stones,   rocks   and   clay  being   left   in   the   race   beside paddock 8;

·Stone  damage  to  the  races  on  the  eastern  side  of  paddocks  1-4  and between 4 and 5;

·         Deterioration or elimination of the depth of topsoil in paddocks 6-10;

·         Clay fill being dumped or being pushed on to paddocks 8-6 resulting

in poorly formed and steep contoured paddocks;

·Poor   method   used   to   bury   defective/condemned   hard   fill   in paddock 1;

·Novacoil  drain  in  paddock  6  being  incorrectly  installed  through  the use of inappropriate metal as a surround and insufficient gradient;

·Novacoil  drain  in  paddock  1  being  incorrectly installed  through  not being laid to sufficient depth, being laid with an insufficient gradient and with inappropriate metal used as a surround.

[26]     The Judge found that it was an implied term of the contract that T & T would exercise  reasonable  skill  and  care  in  the  execution  of  the  contract  works.      This finding is  not  challenged.   Mr  and  Mrs Rennell  pleaded  a  similar  duty in  tort  and there was no challenge to the existence of that duty either.   The Judge determined

this aspect of the counterclaim primarily on the basis of the tortious duty but making

it clear that the same conduct breached the implied term.

[27]     The initial question in relation to the damage said to have been done to the property  as  a  result  of  T  &  T’s  work  was  whether  T  &  T  had  any  obligation  to reinstate the property at all.  The nature of the work meant that substantial quantities of metal and stones would be brought on to the property.   Originally T & T was to access  the  property  through  a  neighbour’s  property  which  would  have  meant vehicles  entering  at  the  fence  line  between  paddocks  2  and  3. However,  that arrangement did not proceed and T & T had to make provision to access the property through paddock 1, which required some metal to be put down.  After a month or so, with winter weather setting in, T & T’s vehicles began to get stuck in the paddocks with three trucks having to dump their load  of metal and be dragged out.   At that point T & T stopped attempting to access the property with trucks and began using “maggot” machines.   Building material was brought to the entrance of paddock 1, stockpiled  and  from there  transported  by  the  “maggots”  to  other  parts  of  the property.

[28]     Messrs  Rogers  and  Long,  who  both  had  many  years  experience  in  civil construction and earthworks, gave evidence for Mr and Mrs Rennell to the effect that industry practice was that, in the absence of specific contractual provisions, any part of the property a contractor was not required to alter as part of the work should not be  altered  or  damaged  and  if  it  is  altered  or  damaged  it  must  be  restored  to  an equivalent  condition  to  the  condition  it  was  in  before  work  started.   Further,  any parts of a property intended to be altered as part of the work should be restored upon completion of the work to a condition equivalent to the condition the property was in before work started.

[29]     Mr O’Callahan put to both Mr Rogers and Mr Long in cross-examination that where  the  situation  confronting  a  contractor  develops  differently  from  what  was expected  because  of  weather  conditions  then  that  is  something  that  ought  to  be discussed and the question of who should bear the risk agreed on.   Both witnesses were clear that, absent any specific agreement, it was the contractor’s responsibility to ensure that the property was restored to the condition it had previously been in.

[30]     Mr  O’Callahan  was  critical  of  the  fact  that  Mr  Michell  was  not  cross- examined  as  to  the  standard  of  care  to  be  expected  of  a  reasonably  competent contractor.   It  is  true  that  the  cross-examination  of  Mr  Michell  did  not  cover  this particular aspect.  However, it is perfectly clear from Mr Michell’s evidence that he did  not  regard  himself  as  being  under  any  obligation  (whether  contractual  or otherwise)  to  restore  the  property. Mr  O’Callahan  was  able  to  put  this  view  to Mr and  Mrs  Rennell’s  witnesses. T  &  T  did  not  adduce  evidence  from  any independent contractor as to industry practice in this regard.

[31]     Given the nature of the work to be done I have no difficulty implying a term into T & T’s contract requiring it to reinstate the property so as to bring it back to a condition similar to what it was when the works began.  However, this finding does not deal with the real issue, namely whether the need to reinstate arose from T & T’s negligence/breach of contract.   Mr O’Callahan argued, correctly, that in the context of  a  charge-up  contract,  the  cost  of  removing  stones  brought  on  to  the  property without negligence would have been chargeable.   T & T’s position at trial, and on the   appeal,   was   that   the   spillage   of   stones   was   an   ordinary   and   reasonable consequence of the works and not the result of negligence or breach of contract.  As a  result,  the  Rennells  did  not  suffer  any  loss  by  paying  for  that  work  since  they would have had to pay T & T in any event.

[32] The findings under challenge appear at [98] and [106]. In considering

T & T’s assertion that the degree of spillage of stones was both unavoidable and to

be expected, given the volume of metal transported onto and across the property, the

Judge said at [98]:

The work being done was at all times known to be to improve the property and get it into a condition where it could be operated as an equestrian centre. Any spillage was therefore unacceptable...

[33]     Then,  having  rejected  T  &  T’s  argument  that  there  was  existing  stone contamination  on  the  property  and  found  that  stones  remained  on  the  property  in unacceptable areas and concentrations the Judge concluded at [106] and [107]:

I find that leaving stones on a property destined to be used for agisting and training horses is plainly negligent...I accept the evidence of Messrs Rogers and Long that contractors such as the plaintiff should generally leave the site

in the same condition as they found it when commencing work…Nor do I accept  the  suggestion  that  the  defendants  should  have  foreseen  spillage  of stones as a natural by-product of the work done.   In the circumstances, the implied term of the contract as to the Plaintiff being expected to operate with reasonable care and skill has also been breached.

[34]     Mr O’Callahan submitted that the Judge erroneously equated the spilling or leaving  of  stones  on  the  property  with  negligence  which  effectively  created  a contractual obligation to remove stones rather than a consideration of whether T & T had  exercised  reasonable  skill  or  care.   He  also  submitted  that  the  Judge  failed  to identify the acts or omissions that caused the stones to be spilled or left there and whether  such  acts  or  omissions  fell  below  the  reasonable  standard  of  persons undertaking  work  of  this  nature. He  further  argued  that  there  was  no  analysis  or discussion  in  the  judgment  of  the  standard  to  be  expected  of  a  reasonable  person undertaking this kind of work.

[35]     I agree that the Judge did not specifically consider the issue of negligence in these terms.  However, the evidence did clearly establish negligence by T & T.  The evidence as to cause came mainly from Mr Smith, a Chartered Professional Engineer with over 20 years experience.   The Judge regarded Mr Smith as a knowledgeable, fair  and  highly  reliable  witness  and,  in  my  view,  the  evidence  bears  out  that assessment.

[36]     Mr Smith spent considerable time inspecting the property and advising on the causes of the damage and options for remedial work. In his evidence he considered the problems that he observed in each paddock. He gave his opinion as to the cause

of  those  problems  and  offered  a  suggested  course  for  remediation. In  respect  of many  of  the  paddocks  Mr  Smith  was  critical  of  the  way  in  which  T  &  T  had undertaken its work, concluding that the paddocks could have been returned to their original form had reasonable care been taken.   Although he does not explicitly say so,  I  infer  from  his  evidence  that  this  meant  returning  the  paddock  to  its  original form at a cost well below the substantial amount ultimately spent.

[37]     Mr Smith based his assessment on the assumption the property had no or a minimal  amount  of  stones  on  it  before  T  &  T  started  work. T  &  T  maintained throughout that there were stones on the property before it started  work.

Mr O’Callahan  submitted  that  the  Judge  failed  to  take  into  account  the  body  of evidence pointing to the existence of stones on the property beforehand.  The Judge found,  on  the  evidence,  that  the  part  of  the  property  that  had  previously  been  the adjoining farm  had  been  stone-free  and  that  soil  in  the  Karaka  area  was  generally clear.  Further, Mr and Mrs Rennell had said that before the work began the property was grassed and in a suitable condition to be mown by a ride-on lawnmower.

[38]     I accept that the Judge should have taken  account of the known sources  of stone  Mr  Callahan  identifies.   In  particular,  the  aggregate  and  slag  in  the  sewage system in paddocks 9 and 10 were such as to make it likely that work done in those paddocks  would  inevitably  result  in  stone  contamination  at  an  unacceptable  level, even  without  additional  metal  brought  on  to  the  property  by  T  &  T. Otherwise, however,  the  Judge  was  entitled  to  make  a  general  finding  that  the  property  was either  stone-free  or  such  stones  as  did  exist  were  at  a  level  compatible  with equestrian activity.

[39]     Although not the only form of damage, the presence of stones throughout the paddocks was the major complaint, and the major part of the cost was their removal. Mr Smith inspected the property on many occasions in order to advise on the options

for remedial work.  Mr O’Callahan was generally critical of Mr Smith’s evidence on the   basis   that   it   did   not   sufficiently  detail   the   location   and   extent   of   stone contamination.  However,  I  consider  that  Mr  Smith’s  evidence  was  adequate. Mr Smith considered that:

The overriding difficulty is that the extent of damage to the paddocks cannot

be   accurately  ascertained.  Seemingly  the   stones   are   dispersed   almost everywhere but are in higher concentration in some locations than in others. This  has  been  confirmed  by  the  investigations  that  have  been  carried  out using both machine and hand methods and by the Rennells’ photographs.  In some locations there may be very few stones but I understand that even a few can pose a risk to horses that is untenable.

[40]     Mr Smith discussed the various options for remedying the damage.  One was the  Rennells’  preferred  option  which  was  replacement  of  the  whole  of  the  topsoil which   would   ensure   that   there   was   no   stone   in   the   paddocks. This   was unquestionably the most expensive option (in January 2006 a contractor had quoted $509,000 for that work).   An alternative was to  accept that small stones would be

present in the finished work.  If that were adopted it would allow screening processes

to be used. i.e. uplifting the existing topsoil, screening it, re-spreading and sowing grass.   The quote for that work was $268,000 but, although much less than a total replacement, the quoted price did not include the supplying additional new topsoil to make up for the losses from the screening operations.

[41]     Other  options  were  also  trialled.        These  included  a  Harley  rake  and  a rotadairon (a stone burying machine).   However, this was not an adequate solution given  the  typical  150  millimetre  topsoil  depth.     The  risk  was  that  during  winter months  a  horse  could  easily sink  100  millimetres  onto  a  buried  stone.   In  the  end Mr Smith   concluded   that   the   most   effective   solutions   were   either   complete replacement or sieving of the existing top soil and supplementing it with new topsoil. Given  that  stone  quality  and  distribution  varied  from  paddock  to  paddock  his recommendation also varied from paddock to paddock.

[42]     Mr  Smith’s  evidence  as  to  the  damage  to  the  various  paddocks  and  his opinion as to cause and remedial work can be summarised as follows:

·Paddock 1 – Although there had been some metal from a pre-existing drain the high number of stones and metal was due to a lack of care by T & T when filling the new drain and transporting stones, rock and fill onto the property. Mr  Smith  recommended  the  removal  of  the  top  50  millimetres  of  topsoil, excavation of areas of concentrated stone, screening of remaining topsoil and addition of further screened topsoil to a loose depth of 200 millimetres with preparation for sowing.

·         Paddock 2 – T & T suggested that there had been stones on the property from

an old farm race at the top of paddock 2 and around gateways.  The Judge did not accept this.  However, even if there had been it would not account for the dispersal of stones throughout the paddock that Mr Smith observed, including buried  stones  brought  to  the  surface  during  Rotadiron  trials,  which  he considered  indicated  the  presence  of  numerous  stones  below  the  surface  of the paddock.   Mr Smith considered the probable cause of stone damage was T  &  T’s  failure  to  take  reasonable  care  not  to  spill  stones  and  fill  being

transported  through  the  paddock  and  the  dispersal  of  stones  throughout  the paddock  by  harrowing  and  rolling  rather  than  uplifting  them. Mr  Smith recommended the same remedial work for this paddock as for paddock 1.

·Paddock 3 – Mr Smith observed stones over the entire area of this paddock and considered that their presence resulted from a failure to take reasonable care  when  transporting  materials  through  the  paddock  and  the  decision  to harrow  and  roll  rather  than  uplift  and  remove  stones. The  same  remedial work  as  recommended  for  paddocks  1  and  2  was  recommended  for  this paddock.

·         Paddock  4  –  No work was actually undertaken by T  &  T  in  paddock  4.

Nevertheless, Mr Smith observed stones visible in the paddock though not as prolific  as  with  paddocks  1-3.  Mr  Smith  considered  that  the  stones  in paddock  4  probably  came  to  be  there  through  the  dispersal  of  stones  from other areas by the harrowing and rolling operation rather than by direct spills. He recommended the same remedial work.

·Paddock  5  –  No  actual  work  was  undertaken  in  paddock  5  apart  from  the levelling of the knoll.   Mr Smith described the paddock as quite steep with stone present at the upper end.  He observed little or no topsoil, even though topsoil  would  have  been  removed  in  levelling  the  knoll. Mr  Michell suggested that stone was likely to have reached paddock 5 from the race-way to  the  south  of  the  arena  through  horses,  tractors  or  by harrow.   However, Mr Smith considered that the location of the stones indicated that the cause was lack of organisation and planning in protecting the clay substrate from stones used in other parts of the property.

·Paddock 6 – In paddock 6 T & T constructed a sub-soil drain.   There were stones in this paddock which, according to Mr Smith, resulted from inadequate  preparation  for  construction of the drain and spillage of  stone from the drainlaying  operations. Mr Michell claimed that the drain  was disrupted by subsequent contractors and that later work has caused metal to

be scraped into the surrounding topsoil.  Mr Smith, however, considered that

the presence of stones resulted from inadequate preparation for construction

of the drain, spillage of stones from the drainlaying operation (judging by the type of stones) and spillage or general spreading of aggregate in the arena.

·         Paddock 7 – Mr Smith said that paddock 7 had stones through the upper part

of   the   paddock,   probably   caused   by   spillage   or   general   spreading   of aggregate  in  the  arena  and  its  surrounding  area. Two  light  cuts  proved sufficient to remove the stones from this paddock.

·Paddock 8 – Mr Smith observed stones through the upper half of the paddock and  a  severe  loss  of  topsoil  along  the  northern  boundary.   He  described  a mixture of clay and topsoil interspersed with stones that had apparently been placed   over   the   top   of   existing  topsoil   creating  a   potentially  unstable situation.   He described paddock 8 as one of the worst affected by T & T’s work.

·Paddocks 9 and 10 – These paddocks were not specifically referred to in the judgment.    Mr  Smith  considered,  from  his  observations,  that  the  existing contour   had   been   steepened   and   this   was   confirmed   by Mr Rennell. Mr Smith   then   expressed   views   about   the   probable   reason   for   the   re- contouring (connected with design) and expressed the view that re-contouring should  have  been  carried  out  in  a  manner  that  did  not  result  in  steeper paddocks than existed before.   He recommended the same kind of remedial work as for the other paddocks.

[43]     The Judge made a general finding that the unacceptable level of stones on the property was due to a lack of care by T & T.  I consider that the Judge was entitled to make that finding on the basis of Mr Smith’s evidence except for paddocks 8, 9 and 10, which I discuss separately in relation to the issue of betterment.

[44]     Not only did T & T exhibit a lack of care in actually undertaking the work, it was also negligent in its dealings with Mr and  Mrs Rennell.   It was obvious from

T & T’s own evidence that a major factor in the amount of stone and metal deposited

on the property was the difficulty in moving material around in winter conditions.  I

have already referred to the problems that T & T had in using trucks to get material

on  to  the  rear  paddocks.    Mr  Smith  considered  that  working  through  the  winter months was a significant factor in the cost of the remedial work that was ultimately needed.  He noted that T & T’s March 2005 quote was valid for acceptance for two months from 1 March 2005 which meant that T & T must have anticipated carrying out the work during the winter months.  Mr Smith observed:

85.      It  was inevitable that  working through winter would mean that the project would take longer to complete, be more difficult and cost more.  Any prudent  contractor  would  have  been  aware  of  this.  Had  the  work  been undertaken during the normal earthworks period (October to May) I estimate that the work would have taken six weeks instead of the five months T & T were on site working for.   Had the project been delayed until spring 2005 there  is  less  risk  that  T  &  T  would  have  encountered  difficult  working conditions.

86.      Also, had the work been undertaken in spring or summer the risk of damage  to  the  property  would  have  been  significantly  reduced.   T  &  T’s decision to work through winter is, I believe, the fundamental reason that so much damage has been caused to parts of the Rennells’ property outside the actual works area.  Trucks and machinery can easily travel across dry pasture without effect but will inevitably make a mess when ground conditions are wet.

[45]     Allied  to  the  problems  caused  by  working  through  the  winter  months Mr Smith  identified  a  lack  of  communication  by  T  &  T  with  the  Rennells  as contributing to the adverse outcome:

90.      Having perused T & T’s schedules of costs and the various items of correspondence, I am surprised that T & T did not advise the Rennells that commencing the project in May was unwise and that a better quality job with less  mess  would  be  achieved  if  the  start  time  was  delayed  until  the earthworks season.

91.      Furthermore, if the cost of temporary works (and removal of same) and  additional  machinery  costs  (for  winter  work)  were  not  built  into  the original  quote,  then  T  &  T  should  have  told  the  Rennells  this  before proceeding.     I  have  not  in  30  years  of  experience  seen  a  contract  price increase 250% without prior warning.

92.      To  summarise,  in  my  opinion,  the  major  factors  which  caused  or contributed to the costs blow-out by T & T were T & T’s failure to carry out

a geo-technical appraisal of the site; carrying out of the work through winter

when  this  was  not  required;  poor  design;  and lack of  communication  with the Rennells over the project.   In failing to take these steps T & T did not meet the standards I would expect from a reasonably prudent earthworks and drainage contractor…

[46]     I note that Mr Smith predicated his evidence on the incorrect assumption that the contract was based on a quoted price when it was, in fact, agreed on a charge-up basis.   However, the points that Mr Smith made regarding the decision to continue working  through  the  winter,  with  the  consequent  extraordinary  increase  from  the estimated cost to the actual cost, are unaffected by that mistaken assumption.

[47]     Although not the focus of Mr and Mrs Rennell’s counterclaim, the issue of

T & T’s failure to discuss the risks involved in working through winter was raised on the  pleadings;  in  the  second  amended  statement  of  defence  and  counterclaim  they alleged negligence in failing to keep them advised in relation to the progress and cost of the contract works and failing to have advised them of the increase in the cost of the works in sufficient time to allow them to stop the work.

[48]     On the evidence it is obvious that T & T was a very experienced earthworks and  drainage  contractor.   There  can  be  no  doubt  that  it  either  did  or  should  have recognised the likely result of attempting to cart significant quantities of stone and metal across the property in poor winter conditions.   Indeed Mr Michell’s evidence was  that  he  recognised  the  problems  and  raised  them  with  Mr  Rennell. The unavoidable consequence of more difficult and time consuming working conditions is increased cost.   T & T either did or should have realised that the estimated cost was going to escalate enormously.   It had a duty to alert Mr and Mrs Rennell to the fact that not only was the job going to be more difficult and take longer but the cost would be very significantly greater than originally estimated.[6]

[6] J & J Abrams Limited v Ancliffe [1981] 1 NZLR 244

[49]     Taking  all  of  the  circumstances  into  account  I  conclude  that  most  of  the damage to the property was caused through a lack of care by T & T in undertaking the work.  T & T also exhibited a serious lack of care in failing to raise with Mr and Mrs Rennell the inevitable increase in the cost over the original estimate as a result of workng in winter conditions.

Betterment / Unnecessary work

[50]     T & T argued that the property enjoyed a significant degree of betterment as

a result of the remedial work.   The Judge accepted that some of the work was not required  as  a  result  of  T  &  T’s  lack  of  care.           In  his  submissions  Mr  O’Callahan characterised  this  issue  as  betterment.  The  Judge  made  deductions  in  respect  of work  to  the  races  between  paddocks  4,  5  and  6  and  in  respect  of  paddock  8. Mr O’Callahan  argued  that  there  had  been  betterment  to  the  property  generally. However, it is apparent from my earlier discussion that with only three exceptions the value of the property was not enhanced through the remedial work, but merely reinstated to the appropriate standard.

[51]     An issue also arises  as to the correct amount of  the deductions.   Although, strictly, this arises in the context of Mr and Mrs Rennell’s cross-appeals, I deal with

it  here  for  convenience. The  Judge  had  difficulty  quantifying  the  work  that  he disallowed   on   account   of   betterment. Mr   Gould   submitted   that   the   Judge misunderstood the evidence and, as a result, deducted too much.

[52]         In  relation  to  the  race  between  paddocks  4,  5  and  6  the  Judge  deducted  a figure of $10,501 which he believed to be the quote for the work done.   However, the  document  to  which  the  Judge  was  referring  was  Harrison  Grierson’s  initial estimate of cost based on the first, more expensive option.  (complete replacement of the damaged topsoil).  The evidence was that Mr and Mrs Rennell elected to take the less  expensive  option  involving  the  removal  and  screening  of  the  topsoil  and  that Harrison Grierson produced a further estimate for that work which totalled $279,705 plus GST. Looking at the two estimates it is clear that the Judge has erroneously taken  the  figures  for  reduction  on  account  of  betterment  from  the  first  estimate whereas, on the evidence, the second estimate was the estimate on which the work actually done was based.  Under the revised estimate the cost for reinstating the races was  $9,661  and  this  is  the  figure  that  should have  been  reduced  rather  than  the $10,501 allowed at [131] of the decision.

[53]     Paddock 8 was very steep and, according to Mr Michell, was recognised by both T & T and by Mr Rennell as a suitable area for dumping debris and fill left from

work on other parts of the property. The Judge found that Mr Rennell had instructed that it was to be used for this purpose. The factors that the Judge noted in making this finding was that the paddock was the furthest from the house, that Mr Michell gave evidence of being instructed that all waste from the project was to be dumped

in  that  area  and  that  he  did  so  and  that  another  contractor  coming  to  the  site (Hydrotech  Drainage  &  Plumbing  Limited)  had  also  acted  on  the  expectation  that rubbish was to be dumped in that area.

[54]     The Judge did not accept Mr Rennell’s claim that the paddock was intended

for use for horses immediately after exercise.   The factors that the Judge took into account in reaching his decision are all logical and accord with the evidence.  It was one of the few issues on which the Judge did not accept Mr Rennell’s evidence.  I am not  prepared  to  interfere  with  his  finding.            Therefore,  the  cost  of  remediating paddock  8  could  not  be  attributable  to  any  fault  by  T  &  T.   However,  the  Judge reduced the damages on the counterclaim by $49,846 based on Harrison Grierson’s first  estimate. The  second  estimate,  which  reflected  the  work  actually  done  was $14,262.  That is the amount to be deducted in respect of paddock 8.

[55]     The Judge should also have considered the issue of betterment in relation to paddocks  9  and  10  which  were  not  specifically  referred  to  in  the  judgment. Mr Michell’s evidence was that the work T & T did in paddocks 9 and 10 resulted from the work undertaken in relation to the haha wall:

In  excavating  the  haha  we  found  backwash  drainage  pipes  and  overflows from the swimming pool.   They expired in the area to be filled.   Therefore, we extended them through paddock 10 to expire on to the open drain at the open road via soak holes…

When  filling  the  base  of  the  retaining  wall  on  the  uphill  side  with  scoria using a digger I spilled some scoria over the retaining wall into paddocks 9 and 10.  To clean this up I send a bobcat down to collect it but could not do a very  good  job  because  it  was  so  boggy…Across  paddocks  9  and  10  there were two old effluent lines from the septic tank.  There were horrible smells coming up so John Rennell asked me to determine what was wrong.   I dug holes to locate the line.  There was slag…in the existing lines.  This was dug out  to  inspect  the  lines  and  put  back.   As  a  result  of  this  there  was  slag material  left  near  the  surface.   That  is  not  unreasonable  given  the  boggy conditions and the fact this was being used as a thoroughfare for machinery and  for  fencing  contractors…The  existing  lines  were  found  to  be  full  of solids  and  basically  that  effluent  system  was  stuffed.   We  installed  a  new aerated effluent system.

I wish to note that with regards to paddocks 9 and 10 I would not be surprised  if  a  substantial  amount  of  metal  was  located  in  these paddocks.       There  were  after  all  three  40  metre  trenches  in  there amounting to approximately 24 metres³ of pre-existing metal/slag…

[56]     T & T’s evidence about the sewage overflow and slag found in the paddocks was  unchallenged. In  these  circumstances  there  is  no  basis  on  which  to  find  that remedial  work  to  these  paddocks  was  necessitated  by  any  lack  of  care by T & T. Harrison Grierson’s estimate  for  the  remedial  work  to  these  paddocks  totalled $11,208 and the counterclaim should be reduced by that amount.

Defences of contributory negligence and volenti

[57]     T & T raised defences of volenti and contributory negligence, alleging that it had advised Mr and Mrs Rennell that it was unwise to access the property through paddock 1 during winter and that Mr and Mrs Rennell were aware of the difficulties with   trucks   being   stuck   and   inevitable   damage   to   subsoil   and   risk   of   stone contamination but nevertheless instructed T & T to continue using that access route and declined to cease work during the winter months.

[58]         Mr  Rennell  was  cross-examined  on  whether  Mr  Michell  had  discussed  the impact of winter weather with him.   It was put to him that on the day in June 2005 when two trucks became stuck in paddock 1 Mr Michell explained that wet weather meant they would either need to stop work completely or until it was dry enough to get the trucks through which would probably be the end of winter.  It was also put to him  that  he  knew  then  that  the  nature  of  the  project  had  substantially  changed because  of  the onset  of  winter.   Mr Rennell  rejected both propositions saying that Mr Michell  had  never  suggested  that  T  &  T  stop  work  and  never  suggested  any change to the contract other than having to bring more metal to the property to make the access way more useable.  The Judge made factual findings on these issues early in  his  judgment  but  later  drew  conclusions  that  were  inconsistent.           The  factual findings were:

[33]     …the commencement date of the work was ill-advised.   It  is plain that the first steps taken on site started out of season (the correct season for such earthworks beginning November to end April).   That decision was the Plaintiff’s  but  the  Defendants  were  apparently  “delighted”  by  it…The Plaintiff now maintains that by commencing then it caused the blow-out of

costs  –  at  least  in  part.    The  Plaintiff  says  the  commencement  date  was driven by Mr Rennell’s sixtieth birthday (he is said to have wanted the work completed before that) – but there is simply insufficient evidence as to this.

[34]     Further, as an entity with some experience in this trade the Plaintiff could  and  probably  should  have  made  allowances  for  this  factor  in  the original estimate or subsequently.  It did not do so.

[35]     On the other hand, Mr Rennell was given the option when the rains commenced  (if  Mr  Michell  is  to  be  believed)  or  he  could  have  taken  the option to pause the work and await more settled weather at any time during the  works.   He  plainly  did  not  do  so  and  watched  the  trucks  coming  and going  across  his  fields,  spilling  metal  and  getting  stuck,  as  well  as  at  one point damaging the tarsealed driveway leading to the house.   He could and probably should have done something about that.

[36]     Faced with this conundrum the Court really has to decide that both parties  were  content  with  the  timing of  this  work and  remained content to continue  on  with  the  work  despite  the  winter  difficulties.  To  place  any blame on any party as against the other would be unfair.

[59]     The  effect  of  this  finding  is  that,  whether  or  not  Mr  Rennell  was  told  that work ought to stop during winter, he should have raised the issue himself, given the obvious difficulty trucks were having with access to the property.  One would expect this to result in a finding of contributory negligence by Mr and Mrs Rennell, but it did not.  The Judge rejected both defences:

[123]   [Contributory  negligence]  was  an  issue  that   arose  during  final submissions,   which   reflect   the   insignificant   emphasis   placed   on   the proposition  during  evidence. Considering  that  the  sub-contractors  were called by the Plaintiff to confirm the quality of what they did or supplied, it ill behoves the Plaintiff to now suggest that any of them was a contributory to  any  negligence  on  the  part  of  the  Plaintiff. I  did  not  understand  the submission   to   include   the   notion   that   the   Defendant   had   somehow contributed to their own detriment but having considered all the evidence, I am satisfied that there is insufficient material to support this conclusion…

And in relation to the defence of volenti:

[124]   …The Plaintiff was suggesting that the Defendants had accepted the risk of their property becoming stone-infested by commencing the work...

[126]   At no stage did the Plaintiff explain to the Defendants the likelihood

or even possibility of stone infestation.  There is no evidence to suggest the subject   was   even   mentioned.  I   am   not   satisfied   that   this   has   been established.

[60]     Mr   Rennell   had   no   experience   in   earthworks   contracting. He   was   a businessman.   However, it is plain that he was an experienced businessman and the

Judge was right to find that, faced with the scene of substantial quantities of stone and metal being carted across boggy paddocks in the middle of winter, it should have occurred to him to question the wisdom of continuing.  In my judgment Mr and Mrs Rennell must bear some, albeit a modest, level of responsibility in failing to take any action  to  protect  their  own  interests  in  the  face  of  a  situation  that  was  obviously worsening as time went by.   To the extent that damage was the result of continuing to work in adverse winter conditions, the responsibility lies mainly with T & T but there ought to be recognition of Mr and Mrs Rennell’s own failure to take reasonable steps to protect their interests by enquiring as to  the wisdom and consequences of continuing to work in such obviously poor  conditions. I fix  the  apportionment  at 90% to T & T and 10% to Mr and Mrs Rennell.

Measure of damages

[61]     Initially, the counterclaim was brought for the (then unspecified) diminution

in value of the property resulting from T & T’s work.   At trial, however, the claim was  for  the  actual  cost  of  the  remedial  work.   The  Judge  identified  both  possible bases for measuring damages and said:

[21]     I consider the statements of  principle set out in Bevan Investments Limited  v  Blackhall  &  Struthers  (No  2)  [1978] 2 NZLR 97 and Ruxley Electronics Limited v Forsyth [1996] AC 344 binding on me in this regard.

In  short,  I accept  that  the preferred  remedy  is  that  of  remediation  but  that care should be taken to ensure that any award should be proportionate to the loss actually suffered.

[62]     Mr O’Callahan submitted that the Judge’s  reliance  on  Bevan  Investments Limited v Blackhall & Struthers (No 2)[7] and Ruxley Electronics Limited v Forsyth[8] was incorrect and that the correct  position  was  as  stated  in  Taylor  (Wholesale)  v Hepworths.[9]  In particular, Mr O’Callahan pointed out that neither Bevan nor Ruxley involved damage to land but, rather, defective building work. Relying on the

[7] Bevan Investments Ltd v Blackhall & Struthers (No 2) [1978] 2 NZLR 97

[8] Ruxley Electronics Ltd v Forsyth[1996] AC 344

[9] [1977] 1 WLR 659 at 666B-667F

decision in Taylor( Wholesale) v Hepworths[10]  and statements from the 13th  edition of

[10] Taylor (Wholesale) v Hepworths [1977] 1 WLR 659

McGregor on Damages[11]  cited by May J in that case Mr O’Callahan submitted that

[11] McGregor on Damages, (13th ed, 1972)

the primary (and in this case correct) measure of damages was diminution in value.

[63]     I do not see significant  differences  between  the  statements  of  principle  in

Taylor as opposed to Ruxley (in which Taylor was cited).   The basic principles can

be stated simply.  If a person suffers damage to property through a tort or breach of contract he is entitled to be put in the same position as he would have been had the tort  or  breach  of  contract  not  occurred,  so  far  as  that  is  possible. However,  any damages awarded must be reasonable as between plaintiff and defendant.  If the cost of reinstatement would  be out of proportion to the benefit then a  court  will assess damages based on diminution in value.  If, however, it is reasonable to reinstate the property then the plaintiff will be entitled to that cost.

[64]     However,  I agree  that  the  Judge  wrongly rejected  diminution  of  value  as  a possibility without considering the valuation evidence:

[32]     …The  alternative  method  of  assessing  quantum  in  relation  to  the Counter  Claim,  namely  the  diminution  of  value  is  a  matter  I  need  not concern  myself  with.    I  will  deal  with  quantum  on  the  basis  of  the remediation done and whether such was required and if so, whether it was reasonable in the circumstances – as per the authorities mentioned above.

[65]     This  approach  is  incorrect  because  the  question  of  whether  diminution  of value  was  the  correct  measure  of  damages  turns  on  whether  reinstatement  was reasonable.   So diminution in value could not be eliminated as a possible measure until the issue of whether reinstatement was reasonable had been resolved.   It was apparent from the rest of the judgment that the question whether reinstatement was reasonable was not adequately considered.

[66]         Mr O’Callahan asserted that the evidence showed that there was no diminution in value of the property as a result of the presence of stones throughout the paddocks. Having reviewed the evidence I do not think that that conclusion is justified. There was valuation evidence from two valuers,   Mr   Darroch,   for Mr and Mrs Rennell, and Mr Irwin, for T & T. In addition, a valuation obtained by Mr  and  Mrs  Rennell  from  Property  Valuations  Limited  in  March  2007  was  in

evidence.   Although the Judge expressed views about Mr Darroch and Mr Irwin as witnesses, he did not analyse their valuation evidence.

[67]     Mr  Darroch  had  an  advantage  over  Mr  Irwin  in  that  he  had  been  able  to physically inspect the property.  He had walked over it in late 2007 and observed the affected  areas.           He  considered  that  diminution  in  value  based  on  sales  evidence would be difficult to prove.  However, he considered that the concentration of stones and  loss  of  topsoil  made  the  property  unsuitable  for  agisting  valuable  horses. Although that was not the only potential use for the property, it was the purpose for which the property had been developed.   In those circumstances, he considered that the  proper  approach  was  to  make  an  allowance  for  the  cost  of  remedial  work  and treat that as the diminution in value.  Of Mr Darroch, the Judge said that:

I found  him to  be  plainly sensible  and  believable…He  expressed the view that  the  re-contouring  of  the  property  which  has  occurred  due  to  the remediation work was not significant in his view.   He also commented on the fact  that  the stones he had seen on the property made it unsuitable for agisting horses.  I accepted both those views, bearing in mind he had cast his experienced eyes over the property before and after.

[68]     Mr  Irwin  pointed  out,  correctly,  that  the  cost  of  improvements  may  be  a useful  tool  to  indicate  value  but  was  not  definitive  in  terms  of  assessing  value. However, Mr Irwin did not have the benefit of having inspected the property.   His conclusion that there was no diminution in value turned mainly on the fact that in March  2007  the  property  was  valued  at  $3.8m  and  in  June  2008  it  was  sold  for $3.8m and the valuation  did not identify any issues with stones.   Of Mr  Irwin the Judge said:

To me, he made more sense than Mr Darroch (in fact he undermines him) regarding the  theory of  diminished  value in  that  he said that  there  was  no such diminution in this case.   I noted that he was not permitted to visit the site but that was not his fault.  He considered it hard to conceive of a former farm absolutely free of stones – due to races, stones in gateways and around drinking troughs.  However, as he did not enter the property he was not in a position to comment with actual knowledge.  As I did not need to address the diminution of value his evidence was of limited value to me.

[69]     However, I consider that Mr Irwin’s  evidence  did  not  take  account  of  the following facts.   First, in relation to the valuation obtained in March 2007, there is

no indication as to the extent of the valuer’s inspection of the paddocks and whether

he was aware of the level of stone contamination.   The description of the land (as opposed to the improvements) is very general and there is a reservation to the effect that:

Substances such as asbestos,   other   chemicals,   toxic   wastes   or   other potentially hazardous materials could, if present, adversely affect the value

of  the  property. The  stated  estimate  is  on  the  assumption  that  there  is  no

material on or in the   property  that   would   cause  loss  in   value. No responsibility  is  assumed  for  any  such  conditions  and  the  recipient  of  this report is advised that the Valuer is not qualified to detect such substances, quantify the impact on values or estimate the remedial cost.

[70]     Secondly,  Mr  Irwin’s  evidence  did  not  consider  the  possibility  that  the property was unsuitable for agisting horses (which was the effect of evidence from Mr Ewen which the Judge  accepted).   Whether there was any diminution in value turns  very  much  on  whether  the  property  was  suitable  for  agisting  for  horses notwithstanding the stones.  If the presence of stones made little difference to the use of the property for equestrian purposes then one would conclude that there had been no  diminution  in  value.           If  it  did  make  a  difference  then  reinstating  the  property would more  readily be  viewed  as reasonable  because that cost  would approximate the diminution in value.

[71]     Mr  O’Callahan  submitted  that  the  property  was  suitable  for  other  than equestrian uses.  As a result, it was unnecessary (and unreasonable) to embark on the level of remedial work that was undertaken.  In this regard he also points to the fact that  Mr  and  Mrs  Rennell  had  decided  to  sell  before  they  undertook  the  remedial work; the evidence showed that the remedial work to remove stones from the fields which  comprised  most  of  the  cost,  was  not  undertaken  until  late  November  2007- early 2008.  Mr Rennell gave evidence about the stress to he and his wife caused by the  situation,  with  the  effect  that  they did  not  wish  to  remain  on  the  property.   In March  2008  they  put  the  property  on  the  market  and  it  sold  in  June  2008. It  is apparent  from  the  sequence  of  events  that  the  remedial  work  was  undertaken  at  a time when the Rennells anticipated selling the property.

[72]     Although it was implicit in the valuation evidence that a purchaser need not purchase the property for equestrian use for the reasons already discussed, it seems highly likely that any purchaser of this property would buy it with that use in mind.

This was the effect of Mr Darroch’s evidence.  Further, it is apparent from the March

2007 valuation that many of the comparable properties considered by the valuer had

no equestrian aspect and  were  valued  at  less  than  the  Rennell  property. The valuation indicated that the barn/stable complex, arena and fencing comprised about

10 percent of the value of the improvements on the property. Therefore, purchasers wishing to buy in this area for general use had plenty to choose from at a generally lower price than properties offering equestrian facilities. The result is that, although, theoretically, this property could be used for general purposes, a purchaser looking to obtain value from it would, more likely than not, buy it for its equestrian facilities.

[73]     Both parties called evidence from veterinarians regarding the extent to which the  presence  of  stones  was  acceptable  at  an  equine  facility.   Mr  and  Mrs  Rennell called  Mr  Ewen,  an  equine  veterinarian  for  over  35  years  who  practices  in  South Auckland.   He  considered  that  the  presence  of  stones  creates  unnecessary risks  to horses in the form of sole bruises and resultant abscesses.   In his experience most lameness in horses is caused by sole bruises and abscesses.  The Judge found him to be a “good, safe, reliable witness”.

[74]     T & T called Mr Cottle who has been involved in equestrian sport in various capacities for over 30 years.   In addition, Mr Cottle has had many years experience

as an earth works contractor.  Amongst his current business interests is the supply of

a European arena surface product to the New Zealand market and he has advised on the construction of horse arenas in South Auckland.  Mr Cottle confirmed that horses can suffer bruising and other injuries if hooves come into contact with sharp objects. But he considered that stones of less than 20 millimetres did not pose any risk.   He confirmed  that  sharp  stones  rather  than  rounded  stones  are  more  likely  to  cause damage.   However, he placed some significance on the way stone is managed on a property.           He  also  considered  that  it  is  to  be  expected  that  some  stone  would  be present after the completion of work of the kind T & T had undertaken and that that is a risk the owner bears.   He considered that an earthworks contractor can take as much care as they reasonably can but some stone will nevertheless remain.

[75]     Mr Cottle’s evidence regarding the  danger  to  horses  from  stones  was  not really inconsistent with that of Mr Ewen; while it is to be expected that there may be

some level of stones as Mr Ewen suggests around troughs and gateways, Mr Cottle’s evidence  generally  supported  the  conclusion  that  sharp  stones  in  paddocks  in  any significant number will be a problem.  Although neither witness specifically said so, one  could  not  reasonably  expect  every  last  stone  to  be  removed. However,  the evidence  overall  certainly  supported  the  conclusion  that  stones  in  any  significant number will pose a risk to horses.

[76]     I conclude that, given the  specialist  nature  of  the  development  the  March

2007 valuation assumed that the property was suitable for that use.  Further in order

to secure a price, at or near the March 2007 valuation, the property would need to have  been  in  a  condition  that  was  suitable  for  agisting horses.   The  level  of  stone contamination  precluded  this. Although  horses  had  been  kept  on  the  property between 2006 and 2008 the evidence supported Mr Rennell’s contention that a full- scale  agistment  operation  for  valuable  horses  was  not  possible. As  a  result,  the decision to reinstate was reasonable.

Cross-appeal by Mr and Mrs Rennell on counterclaim

Personal liability of Mr Michell

[77]     Mr  and  Mrs  Rennell  brought  their  counterclaim  against  both  T  &  T  and Mr Michell.  The duties alleged to have been owed by Mr Michell personally can be summarised as follows:

a)        Duties to exercise skill,  care and  judgment in providing the original quote  including  providing  reliable  information  about  the  cost  of  the contract works.

b)Instructing and supervising the subcontractors, ensuring that materials were fit for their purpose and ensuring that any parts of the property not intended to be modified were not modified or damaged and if they were   then   ensuring   that   they   were   restored   to   their   equivalent condition.

[78]     The Judge disposed of the claim against Mr Michell at an early stage in the judgment on the ground that he had not assumed any personal duty of care towards Mr and Mrs Rennell:

[28]     …The  plaintiff  is  a  limited  liability  company.      In  my  view,  all negotiation, discussion and work undertaken was done by, in the name of, and for the company.  Mr Michell did some of that but by no means all – in fact the Defendants assert very little was actually done by Mr Michell and there is support for that suggestion.

[29]     In my view, the proposition advanced by the Defendants regarding Mr Michell’s personal liability does not take into account that sole Director companies  abound,  and  that  sole  Directors  are  in  a  different  position  to Directors  of  larger  entities. I  respectfully  agree  with  the  statements  in Trevor Ivory Limited v Anderson [1992] 2 NZLR 517 and Body Corporate 202254 v Taylor CA205/06 20 November 2007, 22 August 2008. Only if Mr Michell takes over responsibility as an individual can a finding be made on  this  ground  against  him  personally. I  note  that  during  his  evidence Mr Rennell stated that he regarded Mr Michell as T & T and vice versa – he was unable to differentiate between the two.

[30]     I  assess  that  what  Mr  Michell  did  was  done  in  his  capacity  as  a director of the Plaintiff.   I have decided that  he did not assume a personal duty of care.   There is therefore no  basis for a  personal action against the Second  Counterclaim  Defendant.  He  is  entitled  to  his  corporate  shield; Saloman v Saloman & Co Limited [1897] AC 22.

[79]     For  Mr  and  Mrs  Rennell,  Mr  Gould  submitted  that  the  Judge  misdirected himself as to the law in asserting that sole directors are in a different position from directors of larger entities.   He also submitted that the evidence showed a level of involvement by Mr Michell that warranted a finding of personal liability.

[80]     The basis for personal  liability of a company director  for  negligence  was clearly  described in Morton v Douglas  Homes  Limited  where  Hardie-Boys  J considered a claim against company directors for damage  caused  through  the negligent construction of a building. He considered that a director is personally liable

for his own torts and that any duty of care owed by him personally would arise by reason  of  proximity  between  him  and  the  plaintiff,  not  by  reason  of  his  status  as director:[12]

[12] [1984] 2 NZLR 548 at 593-594

The principle of limited liability protects shareholders and not directors, and

a director is as responsible for his own torts as any other servant or agent

(see for example Yullie v B & B Fisheries (Leigh) Limited [1958] 2 Lloyd’s

Rep 596, 619).  His liability to the person injured is personal, and unaffected by any right of indemnity he may have against the company.   Nonetheless, the separate corporate identity of the company must not be lost sight of, for the directors are not personally liable for the company’s torts, except in the limited  type  of  case  discussed  by  Lord  Buckmaster  in  Rainham  Chemical Works Limited v Belvedere Fish Guano Co [1921] 2 AC 465, 476, namely where the company’s wrongful acts were expressly directed by them. Apart from this kind of situation, whilst a director may be liable in negligence to a person with whom the company is dealing, it will only be where he personally, as distinct from the company, owed a duty of care, and failed to observe it. His liability then arises not by reason of his office of director but by reason of a relationship of proximity or neighbourhood existing between him and the plaintiff. It may well be that because he is a director that the relationship arises, but the fact that he is a director does not of itself create the relationship…

[81]     Hardie-Boys  J  then  went  on  to  consider  the  decision  Callaghan  v  Robert Ronayne  Limited[13]    in  which Speight J referred to the concept   of  control in establishing negligence by a director that would give rise to personal liability:

[13] Auckland A1112/76 17 September 1979

To  establish  personal  liability  proof  is  required  that  the  directors  were  the actual tortfeasors, in which case their status as directors is irrelevant.   It is their personal liability.  In the present case it will be noted that most if not all of  the  particulars  of  negligence  and  breach  of  statutory  duty  alleged  are allegations of matters of default, that is to say failure rather than commission of  tortious  acts.   There  has  been  no  proof  here  of  any  individual  acts  of neglect.        The  defective  work  was  in  all  cases  done  by  workmen   or subcontractors  employed  by  the  company. Had  there  been  evidence  of personal  control  and  instruction  by  one  or  more  of  the  individual  second defendants  then  in  respect  of  such  failure  by  him  in  the  role  of  controller which  might  be  proved  which  had  led  to  defects  then  liability  might  have been  established  but  there  were  four  of  these  people  and  the  evidence showed  little  more  than  that  individual  ones  of  them  were  present  at  the scene  from  time  to  time.   There  was  little  specific  evidence  of  individual participation  by  them  or  any  of  them  and  to  the  extent  that  there  is  any suggestion   that   directors   were   sometimes   on   the   scene   there   is   no distinguishing evidence as to who did what and I cannot see that this claim can succeed.

[82]     Drawing  on  Speight  J’s  concept  of  control,  Hardie-Boys  J  proceeded  to summarise that:

The  relevance  of  the  degree  of  control  which  a  director  has  over  the operations  of  the  company  is  that  it  provides  a  test  of  whether  or  not  his personal carelessness may be likely to cause damage to a third party, so that he becomes subject to a duty of care.   It is not the fact that he is a director that creates the control but rather that the fact of control, however derived, may create the duty.  There is therefore no essential difference in this respect between  a  director  and  a  general  manager  or  indeed  a  more  humble

employee of the company.   Each is under a duty of care both to those with whom  he  deals  on  the  company’s  behalf  and  to  those  with  whom  the company deals insofar as that dealing is subject to his control.

[83]     Confusion arose subsequently, however,  as a  result of statements in Trevor Ivory  Limited  v  Anderson  which  also  concerned  the  basis  for  personal  liability  of directors,  but  in  the  context  of  a  negligent  misstatement  claim.[14]     In  Trevor  Ivory Hardie-Boys J said that clear evidence was needed to displace the “basic premise” that the effect of incorporation is that the acts of a director are usually identified with the   company   and   do   not   give   rise   to personal liability   but   that   there   are circumstances  in  which  a  director  may  be  liable  personally  for  acts  for  which  the company is also liable:[15]

[14] [1992] 2 NZLR 517 (CA)

[15] At 527

An agent is in general personally liable for his own tortious acts: Bowstead

on Agency (15th  ed 1985) at p490.   But one cannot from that conclude that whenever a company’s liability in tort arises through the act or omission of a director,  he,  because  he  must  be  either  an  agent  or  an  employee,  will  be primarily  liable,  and  the  company  liable  only  vicariously.   In  the  area  of negligence, what must always first be determined is the existence of a duty of care… In the policy area, I find no difficulty in the imposition of personal liability on a director in appropriate circumstances.

To make a director liable for his personal negligence does not in my opinion run  counter  to  the  purposes  and  effect  of  incorporation.   Those  purposes relevantly include protection of shareholders from the company’s liabilities, but that affords no reason to protect directors from the consequences of their own acts and omissions.  What does run counter to the purposes and effect of incorporation is a failure to recognise the two capacities in which directors may act; that in appropriate circumstances they are to be identified with the company itself, so that their acts are in truth the company’s acts.   Indeed, I consider   that   the   nature   of   corporate   personality   requires   that   this identification  normally  be  the  basic  premise  and  that  clear  evidence  be needed  to  displace  it  with  a  finding  that  a  director  is  acting  not  as  the company but as the company’s agent or servant in a way that renders him personally liable.

Essentially I think the test is, or at least includes, whether there has been an assumption of responsibility, actual or imputed.   That is an appropriate test for the personal liability of both a director and an employee…

[84]     On the question of what  might  amount  to  an  assumption  of  responsibility

McGechan J said at 532:

When it comes to assumption of responsibility, I do not accept a company director of a one-man company is to be regarded as automatically accepting

tort  responsibility  for  advice  given  on  behalf  of  the  company  by  himself. There  may  be  situations  where  such  liability  tends  to  arise,  particularly perhaps where the director as a person is highly prominent and his company is barely visible, resulting in a focus predominantly on the man himself.  All will  depend  upon  the  facts  of  individual  cases  and  the  degree  of  implicit assumption  of  responsibility,  with  no  doubt  some  policy  elements  also

applying.   I do not think this is such a case…There was no representation, express   or   implicit   of   personal   involvement,   as   distinct   from   routine involvement  for  and  through  his  company.   There  was  no  single  feature which  would  justify  a  belief  that  Mr  Ivory  was  accepting a personal commitment as opposed to the known company obligation.

[85]     Morton   was   specifically  discussed   in   Trevor   Ivory   with   the   confusing indication  that  it  was  to  be  regarded  as  an  example  of  liability resulting  from  the assumption of responsibility.  Cooke P said:[16]

[16] At [523]

So far as there were findings in [Morton] of personal liability on the part of directors,  I  am  content  to  accept  that  on  the  particular  facts  there  was  an assumption of responsibility.   Clearly the judgment was not intended to lay down a general rule in building negligence cases; and it would be unsafe to try and argue from one particular set of facts to another.

[86]     And at page 527 McGechan J observed:

Assumption of responsibility  may  well  arise  or  be  imputed  where  the director or employee exercises particular control or control over a particular operation  or  activity…This  is  perhaps  more  likely  to  arise  within a  large company where there are clear allocations of responsibility, than in a small one.  It arose however in the case of a small company in Morton v Douglas Homes Limited [1984] 2 NZLR 548, 593FF…

[87]     Finding  a  consistent,  principled  approach  that  reconciles  Trevor  Ivory  and Morton  has  proved  difficult. However,  the  judgment  of  William  Young  P  and Arnold J in Body Corporate 202254 v City Rental Trustees Ltd & Ors[17]  provides a comprehensive discussion about the reasoning in Trevor Ivory in which the Judges conclude that an “elements of the tort” approach is to be preferred and make it clear that Trevor Ivory does not apply to cases in which assumption of responsibility is not an element of the tort:

[17] [2008] NZCA 317

[33]     … The “elements of the tort” approach… was the rationale primarily adopted  by  McGechan  J  in  Trevor  Ivory  and  treated  by  Lord  Steyn  in Williams as the ratio of the case, see 836.[18]    In a situation where assumption of  responsibility  is  an  element  of  tortious  liability,  an  employee  who  is

[18] Williams v Natural Life Health Foods Ltd [1998] 1 WLR 830 (HL)

acting on behalf of a principal can only be  liable  if  there  is  a  personal assumption of responsibility by that  employee. Further,  picking up  points already made, to preserve the existing framework of the law of contracts and the idea that a corporation has a legal identity which is separate from those of  the  individuals  involved  in  it,  considerable  caution  is  required  before concluding that an employee has assumed responsibility.

[34]     To put all of this into context, three further points need to be made:

(a)So restrictive an approach to employee responsibility is not taken in other cases which involve the provision of services of a professional or skilled kind, for instance social services provided by education authorities…

(b)      The Trevor Ivory and Williams decisions have no application

at all to cases in which assumption of responsibility is not an element of the tort…

(c)      Damage  to  property  typically  involves  liability  which  is independent  of  any  assumption  of  responsibility  (beyond what  is  implicitly  accepted  by  anyone  who  carried  out  a potentially dangerous activity).   So if Mr Ivory had himself sprayed the Andersons’ plants, he would probably have been personally liable.   He could certainly have been liable if, in the   course   of   spraying   the   Andersons’   plants   he   had damaged a neighbour’s plants.  The hesitation we have as to the first of the examples just given illustrates the distinction between  “purely”  economic  loss  associated  with  bargain disappointment and property damage is not always clear…

[88]     In  a  separate  judgment  Chambers  J  directed  his  attention  to  the  basis  for  a director’s   liability   for   negligent   acts   or   omissions   as   opposed   to   negligent misstatements.   Deliberately leaving aside the problems that Trevor Ivory presents, the Judge effectively applied the same “elements of the tort” approach to negligent acts and omissions:

[125]   The  law  in  New  Zealand  is  clear  that   if  a  builder  carelessly constructs a residential building and thereby causes damage, the owners of the residential building can sue the builder in negligence… ...That is really the long and the short of it.  If Mr Taylor was self-employed, no-one would have  a  moment’s  doubt  about  the  propriety  of  the  appellants  making  the above allegations against him.  It should make no difference whether or not he was employed at the time he allegedly did these careless things.  But the only relevance of his being employed is that his employer or employees may be  vicariously  liable  for  his  tort  committed  in  the  course  of  employment: Isaac and Todd “Directors’ Torts” in Rowe and Hawes (eds) Commercial Law Essays: A New Zealand Collection (2003) 39 at 50 and the cases there cited.  He and the employer would be joint tortfeasors.

[126]   All  of  this  was  stated  with  admirable  clarity  by  Hardie-Boys  J  in

Morton  v  Douglas  Homes  Ltd  [1984] 2 NZLR 548 (HC). Hardie-Boys J

made  it  clear  that,  if  the  company  directors  had  personal  control  over  the building operation, they could be personally liable…

[128]   In short, there is nothing in principle preventing a builder owing a duty of care to subsequent owners of the building.  Of course, in the present case,  Mr  Taylor  did  not  “build”  the  villas  on  his  own.   Others  will  have helped.   That  will  not  prevent  Mr Taylor  being liable  in  negligence.   It  is enough that his conduct “is a contributory cause; [it does not need to be] in some sense a main or primary cause”: see Todd (gen ed) The Law of Torts in New Zealand (4 ed 2005) at [21.2.02].

[89]     Later   in   his   judgment   Chambers   J   highlighted   the   difference   between negligent misstatement cases and cases based on negligent acts or omissions:

[144]   I  should  also  mention  Williams  v  Natural  Life  Health  Foods  Ltd

[1998] 1 WLR 830 (HL), a decision to which the President refers at length.

It, like Trevor Ivory, was a negligent misstatement case, not a case of pure negligence such as is pleaded here.  Negligent misstatement has always been

subject to special rules.  The reasons for this are set out by Todd at [5.8.02].

In order to contain liability for negligent misstatements the Courts have used various devices not necessary in conventional negligence cases.  Sometimes the  courts  have  referred  to  the  need  for  the  plaintiff  to  show  that  the defendant assumed responsibility for what he or she said.  At other times, the courts  have  referred  to  the  need  for  there  to  exist  a  “special  relationship” between the parties: see Todd at [5.8.04] – [5.8.05].  In Williams the House of Lords took the view that directors, employees and agents acting on behalf of a company were under no duty to take care in making statements to company clients unless they had assumed responsibility for their words. That is not relevant, however, to the present case, as a builder’s liability in negligence does not turn on assumption of responsibility. Rather, the builder is liable, as Todd states, “on ordinary principles of negligence for physical damage to property caused by faulty work of construction”: at 6.4. This

appears to be a difference between the majority and me.

[90]     The approach Chambers J describes to the imposition of personal liability for negligent  acts  or  omissions  is  consistent  with  the  House  of  Lords  decision in Standard Chartered Bank  v  Pakistan  National  Shipping  Corporation  & Ors[19].   In that case, the director of a company who had made a false statement argued that he should  not  be  personally  liable  because  his  statement  was  made  on  behalf  of  the company and  not  personally.   The  House  of  Lords  rejected  that  argument,  finding that   a   director   was   personally   liable   because   he   had   committed   a   fraud. Lord Hoffman said:

[19] [2003] 1 AC 959

Mr Mehra made a fraudulent misrepresentation intending SCB to rely upon

it and SCB did rely upon it. The fact that by virtue of the law of agency this representation and the knowledge with  which  he  made  it  would  also  be

attributed to Oak Prime would be of interest in an action against Oak Prime. But that cannot detract from the fact that they were his representation and his knowledge.  He   was   the   only   human   being   involved   in   making   the representation to SCB (apart from administrative assistance like someone to type the letter and carry the papers around to the bank).   It is true that SCB relied on Mr Mehra’s representation being attributable to Oak Prime because it was the beneficiary under the credit.  But they also relied upon it being Mr Mehra’s   representation,   because   otherwise   there   could   have   been   no representation and not attribution…

No-one can escape liability for his fraud by saying “I wish to make it clear that I’m committing this fraud on behalf of someone else and I am not to be personally  liable”.        Evans  LJ  [2000]  1  Lloyds  Rep  218,  230  framed  the question as being “whether the director may be held liable for the company’s tort”.   But Mr Mehra was not being sued for the company’s tort.   He was being sued for his own tort and all the elements of that tort were proved.

[91]         With  the  benefit  of  the  judgments  in  Taylor  to  which  I  have  referred  I proceed  on  the  basis  that,  in  relation  to  the  allegations  of  negligent  misstatement against  Mr  Michell  relating  to  the  estimate,  Mr  and  Mrs  Rennell  must  prove  that Mr Michell  personally  assumed  responsibility  for  the  negligent  statements.  The essence of the complaint regarding the estimate is that T & T provided an estimate that  was  completely  unrealistic  and  that  Mr  and  Mrs  Rennell  should  have  been warned  was  liable  to  increase  dramatically  as  a  result  of  having  to  work  through winter.

[92]     This case has similarities with the circumstances  of J  & J C Abrams Ltd v

Ancliffe, to which I have already referred in the discussion regarding negligence by T

& T.[20]   In that case the Court of Appeal accepted that a building company owed its client a duty of care in advising on the estimated cost of building.   Finding that the relationship between the building company and the client was distinguished by the special characteristics of trust and confidence reposed in the former to advise on the cost of building, the Court found that the building company should be liable for the negligent  failure  to  advise  that  the  price  would  greatly exceed  the  estimate  given. However,  there  was  no  attempt  to  impose  personal  liability on  the  director  of  the building  company  and  no  discussion  of  whether  the  director’s  acts  would  have resulted in personal liability.

[20] Supra at fn 6

[93]     The evidence in this case was clear that Mr Michell was negotiating on behalf

of T & T. There was nothing to indicate that he intended to go further and assume personal responsibility for any shortcomings in the estimated price. I therefore find that Mr Michell is not personally liable for the inaccurate estimate.

[94]     As  to  the  allegations  relating  to  undertaking  the  works  and  supervising subcontractors,  Mr  and  Mrs  Rennell  would  have  to  prove  that  Mr  Michell  owed them a duty of care as a result of the nature and extent of the work he did and that his conduct caused or contributed to the loss.  It is true that Mr Michell selected the sub- contractors and directed where materials were to go and in what order works were to be  undertaken.   However,  these  were  the  kinds  of  functions  one  would expect  the director  of  a  construction  and  earthworks  company  to  make  and  did  not  directly result in any defective work.  On the evidence, the damage was mostly caused by the lack of care in actually transporting the loads of metal across the property.  Although Mr  Michell  did  attend  on  the  site  sometimes  and  did  undertake  some  of  the  work himself he was not on site consistently and staff or subcontractors undertook much of  the  work  that  was  shown  to  be  defective. To  the  extent  that  Mr  Michell  did undertake work himself the evidence is insufficient to show that such work actually caused or contributed to the damage complained of.

[95]     I  find  that  Mr  Michell  was  not  personally  liable  for  any  of  the  losses sustained.

Interest on counterclaim

[96]     The Judge awarded interest to Mr and Mrs Rennell on their counterclaim from 12 July 2008.  This date was selected by the Judge as being the date of the final payment certificate given by Harrison Grierson and recognising that some payments were made before that date and some afterwards. Mr Gould submitted that interest should have been awarded from the date the cause of action accrued which, at the latest, would have been 29 October 2005 being the date on which T & T issued a stop-work  order. There is no invariable rule as to  when  interest  should run  from. Where, as in this case, the interest represents the loss of use on the money paid over

a period of time it is acceptable to find a date that strikes a fair mid-point in the time

line.   The alternative is that parties embark on a minute calculation of interest on a month-by-month basis.  So the general approach that the Judge took was acceptable.

Costs

[97]     Although both parties succeeded to  some  extent  in  the  District  Court,  the amount for which Mr and Mrs Rennell obtained judgment was more than twice that

of  the  judgment  obtained  by  T  &  T. Further,  most  of  the  evidence  at  trial  was directed  towards  Mr  and  Mrs  Rennells’  counterclaim. In  the  normal  course,  one would  expect  costs  to  follow  the  event  in  respect  of  both  claim  and  counterclaim with  the  result  that  Mr  and  Mrs  Rennell  would  obtain  a  net  costs  judgment. However, the Judge declined to make any costs award:

[138]   Although the Plaintiff has largely succeeded in its Claim, so have the Defendants. If  costs  are  appropriate, I would set them at  scale  2B.   The attempt to undermine the veracity of Mr Rennell on the basis of propensity was in my estimation ill-conceived and wholly unsupported by the evidence. That factor caused me to reflect long and hard in relation to costs.  In the end I have concluded that it is fair that each party bears its own costs.

[98]     Mr  and  Mrs  Rennell  have  challenged  the  decision  not  to  award  costs. Mr Gould submitted that there was no proper reasoning for the decision not to award costs, the general principle that a party who succeeds ought to obtain costs should apply and, further, that there was a particular reason for awarding costs in this case namely the cross-examination of Mr Rennell which the Judge himself described as ill-conceived and unsupported by evidence.  Mr O’Callahan simply submitted that as both parties succeeded in part the Judge’s decision was an acceptable exercise of his discretion.  T & T did not appeal the costs decision.

[99]     Although r 46 High Court Rules confers a discretion to award costs, in most cases costs ought to be awarded in accordance with the principles identified at r 47. Rule 46 is not to be regarded as a general discretion allowing a Judge to do what he

or she thinks is fair in the circumstances unless the proposed course accords with the principles and purposes of the costs rules.[21]    Rule 47(a) provides that the party who

[21] Glaister v Amalgamated Dairies Limited [2004] 2 NZLR 606 (CA) at [22], [24] and [28]

fails should pay costs to the party who succeeds.

[100]   This was a trial of some complexity which ran for nearly three weeks in the District Court.  The factual evidence was hotly disputed.  Extensive expert evidence was adduced and a number of legal issues required argument and determination.  As I have noted, the burden of most of the evidence and argument fell upon Mr and Mrs Rennell in support of their counterclaim.  The District Court Judge had no criticism for the manner in which their case was conducted.   In this regard I note the Judge’s criticism of the cross-examination by T & T’s counsel of Mr Rennell which, having reviewed the notes of evidence, I agree with.

[101]   I consider that the Judge did make an error in departing from the principle in

r  47(a)  and  that  there  was  no  principled  basis  on  which  to  decline  Mr  and  Mrs Rennell costs; costs on a 2B basis would have been appropriate.

Appeal by Mr and Mrs Rennell on T & T’s claim

Valueless work

[102]   Most of T & T’s claim related to its sub-contractor’s costs which included the earthworks found to have been undertaken negligently.  The Judge reduced the claim

of $85,230.89 to $69,677.92 but allowed the balance sought on the ground that the work had been done and T & T had paid the subcontractors.   Mr and Mrs Rennell appealed this finding.

[103]   The  basis  for  the  appeal  is  that  the  claim  related  to  the  very work  that  the Judge had found to have been carried out negligently and in breach of the contract. However, issues over the quality of the work and loss resulting from the negligence were resolved through the counterclaim.  If Mr and Mrs Rennell were relieved of the obligation to pay invoices for the work done they would, as a result of the recovery on the counterclaim, have effectively obtained the work at no cost.   I consider that the Judge was correct to allow recovery in the sum that he did.

[104]   I have concerns, however, over the Judge’s treatment of interest on this part

of T & T’s claim.  T & T had claimed interest at varying rates on the basis that it had borrowed the money to pay the subcontractors and secured the borrowing  against Mr Michell’s family home. Despite unsatisfactory aspects of the evidence the Judge

allowed the interest claim and Mr and Mrs Rennell did not appeal that finding.  The

Judge’s  calculation  of  the  amount  recovered  by T  & T   included   interest   of

$20,671.60, being the full amount of interest claimed on T & T’s original claim.  The calculation   should   have   reflected   interest   only  on   the   lower   amount   actually recovered.   I will leave  it to the parties to re-calculate that amount, since  I do not have sufficient information regarding the rates to do so myself.

Result

[105]   T & T has succeeded to a limited extent on its appeal against the decision on the Rennell’s counterclaim in that:

a)        The amount recovered on the counterclaim is to be reduced for work that was part of the contract but which T&T failed to do and did not charge  for.    Counsel  are  to  confer  to  identify  the  amount  of  such work;

b)A  reduction  of  $9,661  should  have  been  made  for  betterment  in respect of the races and $11,208 in respect of paddocks 9 and 10;

c)        Mr  and  Mrs  Rennell  should  bear  some  responsibility  for  failing  to take  any  steps  to  question  the  consequences  of  working  through winter.  The counterclaim should be further reduced by 10% to reflect that.

[106]   Mr and Mrs Rennell also succeed to a limited extent on the cross-appeal in respect of the counterclaim in that:

a)        The  deduction  for  betterment  in  respect  of  paddock  8  should  only have been $14,262;

b)        They should have been awarded costs on the counterclaim.

[107]   Mr  and  Mrs  Rennell’s  appeal  in  respect  of  T  &  T’s  claim  succeeds  to  a limited extent in that the interest allowed was not calculated on the actual amount recovered.

[108]   My  inclination  is  to  let  costs  lie  where  they  fall,  given  that  both  parties succeeded to a limited extent.  However, if either party wishes to apply they may file memoranda.

[109]   I  invite  counsel  to  confer  as  to  the  effect  of  these  findings  and  submit calculations  on  which  I  can  make  final  orders.  Memoranda  in  respect  of  both  the calculation as to the effect of my findings and costs (if necessary) may be filed by T & T and Mr and Mrs Rennell respectively within 21 and 28 days with any replies within a further 7 days.

P Courtney J


Actions
Download as PDF Download as Word Document


Cases Citing This Decision

0

Cases Cited

1

Statutory Material Cited

0