Stead Construction Limited v Chillex Mid Island Limited

Link copied
Case Copied 14 min read

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY

CIV-2015-404-3053 [2016] NZHC 594

UNDER the Companies Act 1993 section 290

IN THE MATTER OF

an application to set aside a statutory demand

BETWEEN

STEAD CONSTRUCTION LIMITED Applicant

AND

CHILLEX MID ISLAND LIMITED Respondent

Hearing: 5 April 2016

Appearances:

J T Burley for the Applicant
J S Cooper for Respondent

Judgment:

5 April 2016

ORAL JUDGMENT OF ASSOCIATE JUDGE R M BELL

Solicitors:

Sainsbury Logan Williams (Nathan Gray), Napier, for Applicant

Jones Young (David O Jones), Auckland, for Respondent

Counsel:

J T Burley, Auckland, for Applicant

J S Cooper, Auckland, for Respondent

STEAD CONSTRUCTION LIMITED v CHILLEX MID ISLAND LIMITED [2016] NZHC 594 [5 April 2016]

[1]      Stead Construction Ltd applies under s 290 of the Companies Act 1993 to set aside a statutory demand of Chillex Mid Island Ltd of 3 December 2015 requiring payment  of  the  sum  of  $223,207.63.    The  ground  of  the  application  is  under s 290(4)(a) that there is a genuine and substantial dispute as to the debt claimed in the demand.

[2]      Chillex  Mid  Island  Ltd  was  formerly  known  as  Mid  Island  Mechanical (2010) Ltd.  I shall refer to it as MIM.  Its claim is based on payment claims it gave to Stead Construction Ltd under the Construction Contracts Act 2002.  Its case is that Stead Construction Ltd did not reply in time with payment schedules under the act. It accordingly relies on ss 22 and 23 of the act to say that the sums set out in the payment claims have now fallen due.

[3]      Stead Construction Ltd says that there is a substantial dispute.  It contests the validity of the payment claims.  It says that they are defective on two grounds:

(a)       that the construction work was not adequately identified; and

(b)that the payment claims do not relate entirely to construction work under the act.  As I will explain later, that ground alleges that MIM is claiming for work that it did not carry out.

Preliminary matters

[4]      The application was made within time under s 290 of the Companies Act.  In its initial affidavits Stead signalled that it would file evidence from a quantity surveyor to show that MIM had claimed for more than the value of the work actually carried out.  An affidavit from a quantity surveyor was filed on 26 January 2016. MIM objected to the affidavit on the grounds that it was out of time and that it was irrelevant.  I admit the affidavit.

[5]      As to the complaint of the affidavit being out of time, it is necessary to bear in mind that the time for filing applications under s 290 of the Companies Act is

limited to 10 working days after service of the statutory demand.  It is not always possible to assemble all the evidence which the applicant may wish to rely on to challenge the statutory demand.   In my view it is acceptable to follow the course taken by Stead here, when it signalled…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Stead Construction Limited v Chillex Mid Island Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2016] NZHC 594
Decision Date

CaseChat Overview and Summary

Stead Construction Limited sought to set aside a statutory demand made by Chillex Mid Island Limited under the Companies Act 1993. The demand was for the payment of $223,207.63, stemming from alleged defaults under a construction contract governed by the Construction Contracts Act 2002. Stead contested the validity of Chillex's payment claims, asserting that there was an adequate identification of the work claimed and that the claims did not relate entirely to construction work under the Act. The court had to determine whether Stead had a reasonably arguable case to contest the validity of the payment claims, which would allow it to set aside the statutory demand.

The court found that payment claims are inherently contestable and must meet the requirements set out in the Construction Contracts Act. The court noted that the claims followed a familiar format, which had been accepted by the Court of Appeal in previous cases. Each claim itemised the work and provided a percentage of completion, which was applied against the quoted value to determine the amount claimed. Although Stead argued that the claims did not adequately distinguish between work carried out for stage 1 and work for stage 2, the court held that the claims met the requirement to identify the construction work. The court also rejected Stead's argument that Chillex had claimed for work that it had not carried out, finding that the matter was one of measurement rather than validity.

Having found that Stead did not have a reasonably arguable case to contest the validity of the payment claims, the court upheld the statutory demand. Stead Construction Limited was ordered to pay Chillex Mid Island Limited $223,207.63 by a specified date, or face potential liquidation. The court also addressed the issue of costs, directing the parties' counsel to confer and attempt to agree on the costs to be awarded to Chillex.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.