Southland and Indoor Leisure Centre Charitable Trust v Invercargill City Council

Case

[2015] NZHC 1983

20 August 2015

No judgment structure available for this case.

IN THE HIGH COURT OF NEW ZEALAND CHRISTCHURCH REGISTRY

CIV-2010-425-000588 [2015] NZHC 1983

BETWEEN

SOUTHLAND INDOOR LEISURE

CENTRE CHARITABLE TRUST Plaintiff

AND

INVERCARGILL CITY COUNCIL First Defendant

AND

A S MAJOR Second Defendant

AND

OMAHA INVESTMENTS NO. 1
LIMITED
First Third Party

AND

MAURICE JOHN HARRIS Second Third Party

Hearing: 22, 23, 29 and 30 June, 1-3, 7-9, 14, 15, 21-23 July 2015

Appearances:

M G Ring QC, C J Jamieson and D R Weatherleyfor Plaintiff D J Heaney QC and K B Dillion and S J Wethey for First Defendant

Judgment:

20 August 2015

JUDGMENT OF DUNNINGHAM J

Summary of findings

A.The Council owed a duty of care to the Trust when issuing the code compliance certificate (CCC) and there are no reasons to distinguish the majority decision of the Supreme Court in Spencer on Byron, which held that a territorial authority’s duties under the Building Act 1991 were owed to both original and subsequent owners “regardless of the nature of the

premises”.

SOUTHLAND INDOOR LEISURE CENTRE CHARITABLE TRUST v INVERCARGILL CITY COUNCIL [2015] NZHC 1983 [20 August 2015]

B.       The Council was negligent in issuing a CCC on 20 November 2000, for remedial works to the stadium roof trusses, when it had no information before it on which it could have reasonably concluded the work complied with the building code.

C.      The Council’s negligence was causative of the loss as there was no subsequent  point  where  the  Council  could  show  that  it  could  have properly issued the CCC and yet the damage would still have inevitably occurred.  This is primarily because condition 4 of the building consent was never satisfied, and a reasonable and prudent Council would have required it to be before a CCC was issued.  If it had been satisfied, it is likely that the defects would have been detected.

D.The Trust was not contributorily negligent by failing to implement all the recommendations made by HCL in its letter dated 9 June 2006, as the advice did not put the Trust on notice of the potential safety risk the trusses posed.

E.The indemnity in the lease between the Council and the Trust does not apply to this claim, as it was not drafted so broadly as to cover claims of negligence against the Council which arose independently of the parties’ respective rights and obligations as lessor and lessee of reserve land.

F.       The  Trust’s  loss,  which  was  fixed  at  $15,126,665.35  by  agreement, should be discounted by $750,000, to reflect betterment to the Trust in terms of saved maintenance costs on those components of the stadium where the Trust saved the cost of one cycle of refurbishment or replacement of that component within the term of the lease.

G.GST should not be added to the judgment sum because this is a compensatory payment, not a taxable supply, and so should only reflect the net loss to the Trust.  Section 5(13) of the GST Act does not change that position as the damages award is not a “payment under the insurance contract”.

H.In respect of the Council’s cross-claim against Mr Major, the Council is entitled to a 90 per cent indemnity from Mr Major.

Contents

Introduction ............................................................................................................[1] The events leading to the collapse .........................................................................[8] A stadium for Southland [8]

A problem arises and the Trust responds  [13] Meanwhile, back at the Council  [21] Building consent for the remedial works  [26] Implementation of the remedial works  [34] The Council asks Mr Major to “please explain”  [37] The issue of the code compliance certificate for the remedial works              [44]

The subsequent provision of information to support the code compliance certificate  [50]

The collapse and its aftermath..............................................................................[58] The Department of Building and House investigation  [64] The IPENZ investigation of Mr Major’s role  [69] The issues for determination ................................................................................[74] Are any aspects of the claim precluded by limitation defences? .........................[75] Does the Council owe the Trust a duty of care?...................................................[82] Why does the Council say no duty of care is owed?     [82] Why does the Trust say a duty of care is owed?  [91]

Is a duty of care owed?  [94]

Did the Council own the stadium, and if so, does this negate the imposition

of a duty of care?  [100] Did the Council breach its duty of care to the Trust?......................................... [113] The statutory framework for issuing a CCC  [115] Standard of care  [118] Did Council breach its duty of care on 19 November 2000?  [122]

Was the negligent issue of the CCC in November 2000 causative of the

Trust’s loss? ........................................................................................................[125]

Would Council have breached its duty of care if it issued a CCC for the

remedial works on 28 November 2001?  [127] Discussion  [139] Was the Trust contributorily negligent? .............................................................[149] What was the advice the Council says the Trust should have followed?  [150]

The principles of contributory negligence  [162] Was the Trust contributorily negligent in these circumstances?  [167] Does the indemnity in the lease preclude the Trust’s claim from succeeding?..[173] Quantum .............................................................................................................[186] Is the Council entitled to a deduction for betterment? .......................................[189] The Council’s position     [189] The Trust’s position  [194] Legal principles applying to betterment  [197] How should the principles apply in this case?  [201]

Is GST payable on the damages award?.............................................................[218] Why the Trust says GST should be added to the damages award                 [220] Why the Council says GST should be excluded from the damages award     [225] Should GST be added to the award of damages?  [226]

Should GST be added to the interest inclusive, or interest exclusive, judgment sum?     [235]

Summary of quantum award ..............................................................................[238] Indemnity as between the First and Second Defendant .....................................[239] Costs ...................................................................................................................[242]

Introduction

[1]      On  the  morning  of   Saturday,   18   September  2010,   snow   arrived   in Invercargill.  However, Stadium Southland opened as normal.  Roey Bugden was on reception, and Brad Sycamore set up for the morning’s tennis on the community courts.    Joanne  Smith,  the  secretary  of  a  local  tennis  club,  arrived  with  her three children and other junior members for their tennis coaching session.

[2]      The coaching session with the juniors finished at around 11.00 am.  Families then began packing up to go home before the snow created travel problems.  As the stadium emptied out, and the snow continued, staff decided they should get approval to close the stadium down early so they, too, could get home.

[3]      At around 11.20 am, and before the stadium had closed, Mrs Smith heard “a really big bang”, but “it wasn’t a short sound, it was quite long – a massive rumbling”.  Ms Bugden also said “It wasn’t just one bang.  There were successive noises but within a very short timeframe”.   It sounded like “thunder or an earthquake”, or even “a tornado”.  Before she knew what was happening, Mrs Smith said “stuff came spinning towards me.  The doors from events courts 1 and 2 blew open with the wind”.   When she looked into the community courts she could see daylight at the east end and knew that the roof had fallen.

[4]      There were about eight people in the building at the time.  All the occupants ran for their lives, but, as Mrs Smith says, “it felt like the collapse chased us out”. Miraculously, all escaped unscathed.    When Ryan Sycamore, the stadium administrator, arrived shortly afterwards, he recalled “you could immediately see that the main structure on the front had failed … The fire doors at the front were wide open.   It looked like they had been blown open”.   It was clear once the occupants gathered outside, that the stadium roof had collapsed.   Indeed, the expulsion of air caused by the collapse was so strong that loose items, like a chilly bin that was inside the building, were blown outside.

[5]      The roof collapse was a huge blow for the Southland Indoor Leisure Centre Charitable Trust (the Trust).  It had overseen the proposal for an indoor stadium for Southland, and had been responsible for its funding and construction.  As predicted,

the stadium had proved to be a valued community facility and the Trust, with the support of the Council, committed to rebuilding it.   The stadium is now rebuilt, bigger and better than before, but at significant cost.  It is the question of who should bear the repair costs which is at the heart of these proceedings.

[6]      Unlike many building defect disputes, there is no dispute over how and why the stadium roof failed.  The combination of poor quality welding and a failure to follow the plans and specifications for remedial work to the roof trusses meant the roof was unable to carry the snow loadings experienced that day.

[7]      What  is  in  issue  is  whether  the  Council  breached  a  duty  to  exercise reasonable skill and care in issuing a code compliance certificate for remedial works to the trusses for the stadium roof and, if it did, whether it should be liable for the repair costs sought by the Trust.  In determining that question I must also consider the various defences raised by the Council, including whether there has been contributory  negligence  by  the  Trust,  and  whether  the  provisions  of  the  lease between the Trust and the Council preclude a successful claim.

The events leading to the collapse

A stadium for Southland

[8]      The  Trust  was  established  in  1998  at  the  instigation  of  the  Invercargill Licensing Trust.   The Invercargill Licensing Trust had formed a committee which established there was strong interest in a covered stadium and leisure centre for Invercargill.   It then commissioned a concept design for the stadium and recommended the establishment of an incorporated charitable trust to progress the proposal.

[9]      The Trust was constituted by deed dated 29 April 1998.  It was governed by a voluntary board of trustees which included representatives from the following organisations:

(a) the Invercargill Licensing Trust;

(b) the Community Trust of Southland; (c) the Invercargill City Council;

(d) the Southland Building Society; (e) Sport Southland; and

(f) the Southland District Council.

[10]     Once   sufficient   funding   was   obtained   through   donations   and   grants, McCulloch Architects Limited (McCulloch Architects) was engaged to design the stadium and to project manage its construction.   McCulloch Architects engaged a local engineer, Mr Tony Major, as the consulting engineer for the project.

[11]     The  location  of  the  stadium  was  the  subject  of  discussion  between  the Council and the Trust.  They eventually agreed that Surrey Park, a centrally located Council reserve with existing facilities for sport and recreation, was the preferred site.  On 7 July 1999 the Trust signed a lease with the Council for the area of land on which the stadium was to be erected.  Work on construction could then get underway in earnest.

[12]     The main building consents were issued in 1999 and the majority of the building work was undertaken during that year.

A problem arises and the Trust responds

[13]     The  stadium  the  Trust  built  was  a  large,  generally  rectangular  building. Along one side of it were two large events courts plus a reception area, squash courts, toilets and changing rooms.  Within the large open area on the other side of the building, were five smaller community courts.

[14]     In November 1999, when the large roof over the community courts was partly completed, the trustees became aware that some of the trusses in that part of the stadium roof were sagging under their own load.

[15]     In  late  November  1999,  both  the  Council,  through  its  principal  building officer, Mr Simon Tonkin, and the Trust, through Mr Ray Harper, its chairman, put these concerns in writing to the architect.   Responsibly, the Trust required an independent engineer to be involved in the design of the remedial works and it sought  “[a]n  assurance  from  both  yourself  and  the  engineer  that  the  resulting structure [after remedial work] has integrity, is safe, complies with acceptable design standards, and will remain intact for the expected life of the building”.

[16]     As a consequence, Mr Maurice Harris, of Harris Consulting Limited (HCL) in  Auckland,  was  instructed  by  the  Trust  to  review  the  engineering  for  the community court roof trusses and “to certify that the structure following the remedial action is sound, complies with acceptable design standards, and may be safely accepted by the trustees and will remain intact for the expected life of the building”. In the course of doing that work the Trust also sought an explanation from HCL of the exact nature of the problem and its cause, and of the remedial action which was necessary.

[17]   After visiting the stadium on 8 December 1999, Mr Harris provided a preliminary report to the Trust.  That report identified there had been a “mistake in the computer input for the roof trusses” and, as a result, “the community court trusses, and their supporting structure have been designed for lighter loads than required and do not meet New Zealand Code requirements”.

[18]     His full report, provided in late December 1999, identified 11 elements in the structural elements of the building which did not meet the strength and serviceability limits prescribed by the New Zealand Building Code.  The critical concerns related to the community court trusses.  He said:

These  trusses  have  been  designed  without  taking  the  full  loading  into account.  In addition some trusses chords were reduced in what appears to be a “cost cutting exercise”.

As a result the 6 mm thick top and bottom chords are too light and require strengthening.    End web members are also too light and require strengthening.

Because the trusses were relatively shallow for their span, deflections under dead load were high and these were exaggerated by the construction method adopted whereby the trusses were lifted in pairs, (with purlins, and roofing attached) and were simply supported with dead load deflection already occurring before being fixed to the columns.

Because the design was so critical the construction methodology should have been clearly outlined and monitored by the design engineer.

[19]     The report also proposed a remedial option.   The remedial work included jacking the existing trusses, cutting them at three points and aligning them to achieve an upwards precamber of 225 mm at the midpoint, welding in steel plates at the cut points, and then welding steel strengthening plates, end to end, along the top and bottom chord of each truss.

[20]     The report concluded by saying:

The problems that have arisen are design problems and appear to be due to the following reasons:

(1) Lack of checking.

(2) Failure to carry out sufficient seismic analysis.

(3) Insufficient   detailed   design   input   into   connections   and   member slenderness.

(4) Failure to follow design codes.

(5) Pressure to reduce structure costs without detailed re-analysis.

However it also concluded that “[f]ollowing remedial work we believe the building

will meet the structural requirements of the New Zealand Building Code”.

Meanwhile, back at the Council

[21]     It was not just the Trust which was concerned to know why there appeared to be a design flaw in the building. The Council, too, was proactive about the issue. As soon as Mr Tonkin was aware of the problem, he wrote to the architects seeking a report  on  the cause of the sag,  the structural  stability of the building,  and  any remedial measures to rectify the sag and to recamber the roof structure.  Mr Tonkin also sought, by return fax an assurance that, “there is no immediate danger from collapse of the structure”.

[22]     On 15 December, in the absence of response, Mr Tonkin again faxed the architects saying “this matter now requires urgent attention”.  A week later a further fax was sent to the architects for a response.  A day later, on 23 December 1999, Mr Tonkin again faxed the architects, requiring a response before 10.00 am  the following day.

[23]     McCulloch Architects finally responded that afternoon advising that the HCL report had been commissioned but not yet received.   It enclosed the plan of the proposed remedial work which the Trust’s engineer, Mr Major, and the review engineer from HCL, had agreed was appropriate.   It also confirmed that both engineers advised that the building was not in danger of collapsing saying it was “deflections rather than structural integrity that is the issue”.

[24]     On 24 December 1999 Mr Tonkin acknowledged the architects’ letter of

23 December 1999  and  the  plan  for  remedial  work.    He  also  recorded  that  an amendment to the building consent must be applied for and that a peer-reviewed producer  statement  would  be  required  from  the  engineers  on  the  cause  of  the problem and the proposed rectification.  Finally, he stated that Council reserved the option to engage a further independent engineer to review the consulting engineer’s report.

[25]     That same afternoon, the HCL report became available, and the architect provided a copy to Mr Tonkin on a “read only” basis.   The final step taken by Mr Tonkin  that  day was to  write to  Mr Major  asking him  to  “advise  what  the problem was with your design [for the trusses] and how the error came about” and advising that “Council will review how we handle your producer statements after we receive the above information”.

Building consent for the remedial works

[26]     There  was  some  urgency  to  implement  the  remedial  works  because  the official    opening,    to    be    attended    by    the    then    Prime    Minister,    the Rt Honourable Helen Clark, was scheduled for 25 March 2000.  Indeed, the Council said in its 24 December 1999 facsimile to the architects, that if they wished to carry on with remedial work, the Council would not stop the work, but it would not give

approval to it until it had the required information to enable it to issue a building consent for it.

[27]     On 4 January 2000, HCL prepared a producer statement in respect of its design review of the planned remedial work on the community court trusses.1   HCL also prepared an accompanying explanatory letter which it advised “should remain attached to the producer statement”.  Importantly, it provided detailed commentary on how the proposed remediation should be implemented, both on the six trusses constructed of 6 mm thick square hollow section (SHS) steel, and on the three

trusses fabricated using 9 mm thick SHS steel.   The letter set out precise measurements for the precamber to be achieved before the internal props were removed, and for the net precamber, under normal conditions, once the remedial works were complete.  It concluded by saying:

Please ensure the contractor and supervising engineer has a copy of drawing

97139 and this letter prior to beginning repairs.

Complete the first truss and review results prior to completing other trusses in the same manner.

Please contact us if you have any queries or any aspects of the repair work do not comply with the deflections indicated.

[28]     On 6 January 2000, Mr Tonkin met on site with the engineer, the architects, and the builders, where they discussed the proposed remedial works, and how the construction methodology contributed to the original problem.   The Council was advised that an application for an amended building consent for the remedial works would follow shortly.

[29]     Once it received and reviewed Mr Major’s producer statement for the design of the remedial works (or PS1), and Mr Harris’ producer statement for review of that design (or PS2) and his accompanying letter, Council issued a building consent on

14 January 2000.

[30]     The  conditions  of  the  building  consent  for  the  remedial  works  were  as follows:

1      Known as a PS2.

a)The provisions of the New Zealand Building Code override anything that  is  inconsistent  in  these  specifications  and  plans  must  be complied with.

b)Please  note  that  the  consent  fees  paid  allow  for  the  number  of inspections noted on the orange inspection card.   Any extra inspections required will be charged prior to the issue of a Code Compliance Certificate.

c)Please  note  that  any  deviation  from  the  approved  documents  is subject  to  an  amendment  to  the  Building  Consent.    Application forms are available at the Building Consents counter of the Administration building in Esk Street.

d)Consulting Engineer, Mr Major to confirm in writing to Council that the 6 Community Court trusses precamber is in line with Harris Consulting letter dated 4.01.2000, and individual trusses measurements are to be included in the record.

e)Producer Statement Construction Review required from Mr Major for remedial work to the 6 Community Court trusses.

[31]     The first three conditions appeared to be generic conditions included in any building consent issued by the Council.  Indeed, as no inspections were proposed by the Council for this work, condition 2 was not even applicable.

[32]     Condition 4 referred back to the HCL letter of 4 January 2000.  I consider it was  intended  to  capture  the  express  instructions  in  that  letter  regarding  the precamber to be achieved while the remedial works were undertaken, and regarding the net precamber which should be present once the props were removed and the trusses were experiencing a normal load.   However, the condition appears to have only picked up on the instructions for the six lighter weight trusses, even though the letter gave instructions for the remedial work which was required on all nine of them.

[33]     Condition 5 required Mr Major to review the construction process and to provide a producer statement (PS4) confirming that the remedial work had been carried out in accordance with the design.

Implementation of the remedial works

[34]     Work to effect the repairs to the trusses progressed quickly.  When Mr Tonkin visited the site on 21 January 2000 for a general inspection, he noted that:

At present they are still correcting the trusses in the community courts. Seven have been done.  They are not a gentle round they are more in lines and still a bit twisted and up and down a bit, but with a gentle camber up in the middle.

[35]     Although the Council was not planning to inspect the remedial welding work, as neither Mr Tonkin nor his staff felt they had the appropriate expertise to do so, its building staff nevertheless continued with their inspections of the overall building work, and where they saw items that did not appear satisfactory, they raised their concerns with the architect.

[36]     For example, on 27 January 2000, a fax was sent to McCulloch Architects listing five  items  that  were  noted  on  a  general  visit  and  that  “appeared  not  in accordance with the building code”.  One of those related to the community court trusses, with Mr Tonkin noting “connections at truss 1-9 to truss 10, some bottom connections  not  welded  yet  and  standard  of  additional  plates  and  welding questionable on other connections.   Please have consulting engineer check and comment”.  In the same facsimile, Mr Tonkin also sought a response to the six items he had identified of concern, in an earlier facsimile dated 10 January 2000, and which had been followed up by a facsimile of 21 January.

The Council asks Mr Major to “please explain”

[37]     While the works were underway, the Council’s Director of Environmental and Planning Services  wrote to Mr Major on 2 February 2000, following up on Mr Tonkin’s earlier letter requesting an explanation for the problem with the roof trusses in the leisure centre and why they were not designed to comply with the building code.  Importantly, the letter concluded that “unless and until we receive an explanation from you that is satisfactory to us, I believe it would be improper for us to accept any future producer statements”.

[38]     On 4 February 2000, Mr Major responded to the Council’s letter explaining that the discernible sag in the roof was quickly identified by HCL as being “a mistake in my assessment of the live load requirement”.   He explained that, as originally designed, with the chord members being made out of 9 mm thick SHS, “the trusses were sufficiently strong to function as simply supported elements …

even with the full live load allowance”.  However, at the time of tendering he agreed to a reduction in the gauge of the chord members to 6 mm thick SHS.  Given this, along with his error in calculating the live load allowance, and the damage sustained at  the  precast  column  heads  which  the  trusses  were  connected  to,  it  was recommended that all the trusses be strengthened.

[39]     Mr  Major’s  letter  of  explanation  was  referred  to  Mr  Miller,  a  Council engineer, who seemed unimpressed by Mr Major’s explanation.   He noted on the letter that “this is no reason for an  error to occur”.   Nevertheless, the Council responded to Mr Major, acknowledging his letter, and saying “it will take us a little while to consider your explanation but I will get back to you as soon as possible”.

[40]     On 8 February 2000, Mr Tonkin again followed up with the architect seeking responses  to  his  letters  and  facsimiles  of  10,  21  and  27  January  2000.    On

9 February 2000, the Council received responses from both McCulloch Architects and  from  Mr  Major  to  its  queries.    Relevantly,  the  architect’s  response  to  the Council’s   observation   that   the   “standard   of   additional   plates   and   welding questionable on other connections”, was that “[r]emedial work has superseded this observation”.

[41]     On  17  February,  the  Director  of  Environmental  and  Planning  Services provided  his  response  to  Mr Major’s  explanation  for  the  design  errors  in  the community court trusses, saying:

You will appreciate that I had to ask for this explanation, in view of our original acceptance of your producer statement.   You will also no doubt appreciate that it is not appropriate for me to comment on the content of your explanation.

My concern is that from now on Council must have good reason to be satisfied that you  have  put in  place  quality control  procedures that  will ensure that these kind of problems will not recur.

For this reason, before we can accept another producer statement from you for new work, I will need a letter from you detailing what these revised quality control procedures are.

[42]     Mr Major’s response came on 28 February 2000 saying:

I have been engaged in private practise in Invercargill for over thirty years, and we are currently handling up to 300 projects a year.   Almost without exception, we have had no problems.

Given this, you will allow that I am no fool, and can rest assured that I have certainly learnt a great deal from the problems we have encountered over the last couple of months.

From now on I intend to:-

a)only accept commissions where adequate time is allowed for the design and documentation phases,

b)be rather more pedantic where savings in the structural content are requested,

c)prepare calculations to a standard that will allow an independent check to be carried out,

d)engage  an  independent  engineer  to  carry out  a full peer review, covering design philosophy and arithmetical check, for any major projects, or those which involve difficult or novel solutions.

[43]     The Council responded soon afterwards saying:

I accept that the procedures you have adopted will provide an improved level of quality control, and on that basis I am happy to withdraw our previously stated difficulties and reservations about accepting producer statements from you.

The issue of the code compliance certificate for the remedial works

[44]     The  remedial  work  on  the  community  trusses  was  completed  by  early

February, keeping the building on track for the opening on 25 March 2000.

[45]     On the understanding that the remedial work was complete, Mr Tonkin wrote to McCulloch Architects in mid February 2000 seeking provision of the documents required by conditions 4 and 5 of the building consent.

[46]     Formal  advice  of  completion  of  the  remedial  work  was  provided  to  the Council on 1 March 2000, with a request to issue a final code compliance certificate (CCC).  It is not clear why the request was not actioned then but instead went into abeyance until much later in 2000.  On 31 October 2000, the Council wrote to the architects listing the information that was still required under conditions 4 and 5 of

the building consent before a CCC could be granted for the remedial works.  That information was again sought by Mr Tonkin on 16 November 2000.

[47]     There   is   no   record   of   that   information   being   received,   yet   on

20 November 2000, a CCC for the remedial work was issued under the signature of a clerk working in the consents team.   What was not clear until it was revealed in cross-examination, was that Mr Tonkin had not authorised the issue of a CCC, but one was nevertheless issued by the Council, possibly because a CCC was required before the Trust could be issued with a liquor licence for an upcoming function in the stadium.

[48]     As Mr Tonkin frankly admitted:

The issue that I think we have here is that I actually can’t tell you why we issued that code compliance certificate, it is a possibility [that it was issued so the Trust could obtain an on-site licence] because there’s no notes from me to say, “please issue code compliance certificate”.

[49]     It seems no one from within the Council could now explain how the CCC came to be issued, with Mr Tonkin acknowledging that “all I can say is that I didn’t authorise the code compliance certificate”.

The subsequent provision of information to support the code compliance certificate

[50]     Although the CCC was issued in November 2000, the Council continued to seek the information required under conditions 4 and 5 of the building consent after that date.

[51]     On 17 January 2001, Council staff met with representatives of the Trust and the  construction  team  to  discuss  the  outstanding  requirements  in  order  for  the stadium, as a whole, to obtain a CCC.   It was noted by Mr Miller, the Council’s engineer, that Council was still waiting for Mr Major’s producer statement for the work on the community court trusses.  That prompted immediate action, because, on

22 January 2001, the Council received what was described as a “producer statement

– construction” and a covering letter dated 16 January 2001 from Mr Major.

[52]     The  covering  letter  detailed  the  methodology  which  was  adopted  to implement the community court truss repairs, noting what checks were done on site to “confirm that the result was visually acceptable”.  The PS4 provided by Mr Major was expressed in the following terms:

This Consulting Practice has been engaged by McCulloch Architects Ltd to provide structural observation services for the building work detailed in drawing NO 97139  and  the  relevant  specifications for  modifications  to existing trusses for a new building constructed for Southland Indoor Leisure Centre Charitable Trust at Surrey Park, Invercargill.

As a suitably qualified independent design professional, covered by a current policy of Professional Indemnity Insurance to a minimum value of $200,000

I hereby certify that the modifications have been generally constructed in accordance with the details shown in the above drawings and specifications.

[53]     On  26  January  2001,  Mr  Tonkin  referred  the  letter  and  the  PS4  from Mr Major to Mr Miller, with a request to “check if Council’s concerns have been addressed.  The community court truss amendment 00/00011 is tagged – please read condition”.   The advice  which  came back  from  Mr Miller the same day noted “conditions on consent should be referred to engineer, and appropriate comment received”.

[54]     That prompted a facsimile from Mr Tonkin to Mr Major on 30 January 2001 noting the terms of condition 4 on the building consent which required Mr Major to confirm in writing that the community court trusses precamber was in line with the HCL letter of 4 January 2000 and to provide the individual truss measurements in the record.  He asked Mr Major to resubmit his letter to satisfy that condition.

[55]     Nearly six months later, on 23 July 2001, Mr Tonkin wrote to the architects requesting, among other things, the “datum heights of the community court trusses” so that a final CCC could be granted for the building structure. A further fax chasing up datum heights for the community court trusses and other matters was sent by the Council on 12 September 2001.   It seems the very precise requirements of HCL’s letter  of  4  January 2000,  which  were  embodied  in  condition  4  of  the  building consent, had evolved over time into no more than a request for the heights of the trusses as a benchmark against which future deflections could be checked.

[56]     On 30 October 2001 a plan was provided to the Council showing the heights from floor level of the community courts to the underside of each truss.  It did not, however, confirm that the precamber measurements complied with HCL’s letter of

4 January 2000.  Indeed there was a considerable variation in the heights shown on the plan.   For example, truss 2 actually had a sag of 54 mm, rather than a net precamber of 85 mm as recommended by HCL.

[57]     However, provision of the plan which showed only the height of each truss from the floor, appeared to satisfy Council’s inquiries.   No further requests for information were made and no check was made of the plan to see how it compared with the HCL precamber requirements.  A CCC for the stage 4 building consent for the stadium, dealing with structure and plumbing, was issued on 9 April 2003.

The collapse and its aftermath

[58]     When  the  building  collapsed  on  the  morning  of  18  September  2010,  it triggered an investigation into the cause of the collapse. The Department of Building and  Housing  commissioned  the  National  Institute  of  Water  and  Atmospheric Research Limited (NIWA) to report on the snowstorm and the ground snow loading. A data collection campaign was undertaken by NIWA on 19 September 2010 in order to establish the snow loading experienced in Invercargill on the day of the collapse and to assist in assessing the basis for snow loading requirements for buildings in this region.

[59]     Dr Jordy Hendrikx, who at the time was a snow and ice research scientist for NIWA, prepared a report on the findings, dated October 2010.   In that report, he explained that the assessment of snow loading was based on measurements taken in the field adjacent to Stadium Southland on 19 September 2010. The initial report did not make any conclusions regarding the actual snow loading experienced on the roof of this or any other building in Invercargill.

[60]     In his brief of evidence exchanged before the hearing Dr Hendrikx explained that his initial field work assessed the ground snow loading adjacent to Stadium Southland on 19 September 2010 at .45 kPa, with a mean range of .41 to .48 kPa and a  minimum  and  maximum  ground  snow  load  of  .38  to  .59  kPa  respectively.

However, Dr Hendrikx noted that the load on the roof on 18 September at approximately midday would be less than the ground snow load observed in the NIWA report on 19 September and it would be between .85 to 1.0 of the ground snow load, giving a range of approximately .35 kPa to .48 kPa for the roof snow loading.    He also  observed  that  there would  be a “slightly lower  ground  snow loading on 18 September 2010”, but he could not accurately quantify that.

[61]     Dr Hendrikx then undertook further work to quantify the relative percentage of precipitation which fell before midday on 18 September 2010, and between then and 3.00 pm on 19 September 2010, and, by the time of the hearing he felt able to quantify the difference in ground snow load, and therefore in the roof snow load, between the time of collapse around 18 September 2010 and the time the ground snow load on the adjacent field was measured on 19 September 2010.  That resulted in a revised assessment of roof snow load at the time of collapse of .30 kPa (but with a range of between .21 kPa to .33 kPa).  Those measurements were agreed to in the course of expert witness conferencing and I accept them as providing a reliable range for the roof snow loading at the time of collapse.

[62]     The relevance of this information is that it demonstrates that the roof snow loading did not exceed the snow loading which the building was designed to withstand under the relevant building code standards of the time.   The expert engineers agreed that the theoretical snow loading capacity of the building, as designed, should have been about .50 kPa with no more than a 1 per cent probability of failing at that load.

[63]     In short, if the stadium had been properly constructed as designed, it should have  been  able  to  withstand  the  roof  snow  loading  experienced  during  the

18 September snowfall event, so that was not the cause of the collapse.

The Department of Building and House investigation

[64]    The Department of Building and Housing commissioned two consulting engineers to investigate and report on the collapse of Stadium Southland.  One of the engineers, Dr Clark Hyland, appeared as an expert witness to explain the findings of the investigation.   The Court also heard evidence from Mr Charles Wheeler, an

expert welding inspector, who examined the welds in the community court trusses salvaged from the collapse of Stadium Southland, in order to identify whether they complied with the relevant New Zealand Welding Standards.

[65]     The findings of that investigation were not in dispute.  The stadium collapse was likely to have been initiated by the compression failure of the defective mid- span top chord splice in the roof truss at the eastern end of the community courts. The collapse then progressed through other roof trusses, causing a westward displacement of the trusses in the supporting columns.  As the building displaced westward, the bottom chord bolts that were connecting the spine trusses to the two eastern most columns, fractured.  The spine trusses then fell to the ground as the two western most support columns collapsed.  One of the trusses at the western end of the community courts then fell to the floor soon after.   The welds failed and strengthening plates peeled away on some of the roof trusses.

[66]     The report concluded that the remedial work, as designed, was compliant in terms of strength, but would “have been complex and difficult to achieve [to the necessary level of quality] without skilled and experienced steel construction personnel and appropriate supervision”.

[67]     Critically,  there  were  a  number  of  construction  defects  identified.    They included the following:

(a) The welding was visibly deficient in that:

(i) The cut faces of the top chord box sections had not been prepared for welding where packet plates were to be installed.

(ii) The packer plates had not been welded all around to the box section.

The top face of the boxed plate connection (including the plate to plate connection) had not been welded.

(iii)The packer plates had not been ground back before installing the strengthening plates to the side of the box section.  The packer plates

therefore protruded beyond the profile of the box section.  This meant the strengthened plates had been installed on either side of the packer plates and did not, as intended, continue across the packer plate joint.

(iv)Where the box section was welded to the packer plate, incomplete penetration butt welds had been used.

(v) Side strengthening plate segments were not butt welded together.

(vi)Side  strengthening  plates  were  poorly  stitch-welded  to  the  box sections.

(b) The  cutting  and  packing  of  the  truss  top  chords  had  in  many  cases resulted in poor chord alignment at the joint.

(c) The removal of bolts from where the trusses connected to the top of the southern columns was poorly carried out, with some being gas cut and then not replaced, and others not being reinstalled, as evidenced by the TCM thread inserts being filled with grout.

(d) The cutting of the cleats connecting the trusses to the main gantry, and the subsequent reinstatement, was in some instances extremely poor.

(e) Solid steel washers were not welded to the gantry as required by the design.

[68]     It  was  also  identified  that  if  there  had  been  an  adequate  construction monitoring  regime  in  place,  the  deficiencies  should  have  been  identified  and corrected at the time of construction.  Those conclusions were not contested in the hearing.

The IPENZ investigation of Mr Major’s role

[69]     Mr Major had an integral role in the stadium construction.   He was  the consulting engineer to the project, and it was his design error that led to the need for

the remedial work on the community court trusses.  He, in conjunction with HCL, prepared  the  plan  and  specifications  for  the  remedial  work.    Furthermore,  the Council, when issuing the building consent for the remedial work, chose not to have its own inspectors inspect that work themselves, but to have Mr Major provide a PS4, or producer statement for construction review, confirming that the work “has

been carried out in accordance with certain technical specifications”.2

[70]     The Department of Building and Housing’s report raised concerns about the skills and competencies of the parties involved in the design and construction of the stadium.  As a consequence, the Institute of Professional Engineers of New Zealand (IPENZ) initiated an “own motion” complaint against Mr Major, alleging that he had carried out engineering activities in a careless or incompetent manner, which resulted in the collapse of Stadium Southland.

[71]   After conducting an investigation, the IPENZ investigating committee determined that Mr Major did not sufficiently recognise the importance of construction monitoring during the truss modification work.  It concluded he should have:

(a) formally clarified the actions and timings of monitoring inspections that he required, to allow him to visually check samples of the work actually carried out; and

(b) fully documented the work done, e.g. photographs, for signing off purposes.

[72]     IPENZ found that Mr Major did not visually inspect the truss modification work, particularly the work to the top chord before access staging was removed by the contractor.  Instead, he simply accepted the steel-work fabricator’s word as to the sufficiency of the work done.  The committee concluded “Mr Major’s issuing of a PS4 covering this aspect of the work in the manner he did was unacceptable, given the reliance that others such as the owner and regulator would be placing on it”.  As

a consequence, Mr Major was expelled from membership of IPENZ.

2      Building Act 1991, s 2.

[73]     Mr Major is named as the second defendant in these proceedings, but took no active part in them.   He has agreed to contribute $1,000,000 to the Trust’s claim against him.  The Council has cross-claimed against him and seeks a finding that the Council is entitled to a full indemnity against him if it is held liable.

The issues for determination

[74]     In light of that complex  set of background circumstances, the issues  for determination are:

(a) Does the Council owe the Trust a duty of care in these circumstances? (b) If so, was there a breach?

(c) If there was a breach, was it causative of the Council’s loss?

(d) Is the claim precluded by a limitation defence?

(e) Is the claim precluded because Council owns the stadium? (f) Was the Trust contributorily negligent?

(g) If so, to what extent should it be held liable for the loss it suffered?

(h) Is the claim extinguished or otherwise met by the indemnity contained in clause 23 of the lease?

(i)  What is the Council’s loss and should it be reduced for betterment?

(j)  Should GST be payable on the loss and, if so, is it added to the claim before or after the interest is added?

Are any aspects of the claim precluded by limitation defences?

[75]     The Trust’s pleadings allege that the Council failed to exercise reasonable

care and skill in performing its functions under the Building Act 1991 with regard to

the community court truss modification work, including in relation to obligations it had during the period in which the construction work was undertaken.

[76]     However, the collapse did not occur until September 2010, and the claim was not filed until 19 November 2010.  The Council has therefore pleaded that claims which  relate  to  any  acts  or  omissions  of  the  Council  occurring  on  or  before

19 November 2000   are   time-barred   pursuant   to   ss   91   and   393   of   the

Building Acts 1991 and 2004.

[77]    I address this issue at the outset because it is sensible to exclude from consideration any claim that is time-barred under the relevant legislation.

[78] Section 393 of the Building Act 2004 provides:

393     Limitation defences

(1)        The Limitation Act 2010 applies to civil proceedings against any person if those proceedings arise from—

(a)       building work associated with the design, construction, alteration, demolition, or removal of any building; or

(b)       the  performance  of  a  function  under  this  Act  or  a  previous enactment relating to the construction, alteration, demolition, or removal of the building.

(2)        However, no relief may be granted in respect of civil proceedings relating to building work if those proceedings are brought against a person after

10 years  or  more  from  the  date  of  the  act  or  omission  on  which  the proceedings are based.

(3)        For the purposes of subsection (2), the date of the act or omission is,—

(a)       in the case of civil proceedings that are brought against a territorial authority, a building consent authority, a regional authority, or the chief executive in relation to the issue of a building consent or a code compliance certificate under Part 2 or a determination under Part   3,   the   date   of   issue   of   the   consent,   certificate,   or determination, as the case may be; and

(b)       in the case of civil proceedings that are brought against a person in relation to the issue of an energy work certificate, the date of the issue of the certificate.

[79]     Given the 10 year limitation on bringing claims imposed by the Building Act, the Council says the only act which is not time-barred is the issue of the CCC.  This restricts me to consideration of the information the Council had at the time of issue

of the CCC and whether it was negligent to issue the CCC in those circumstances and whether that was causative of any loss.  It does not allow me to enquire into the sufficiency of Council’s actions or inactions at any earlier point in time.

[80]     In the end, this point was less contentious than it seemed in the pleadings. The Trust accepts that it can only claim against the Council in relation to the issue of the CCC on 20 November 2001 and not any negligent acts or omissions which occurred before then.  However, I may need to look at events prior to that date to determine what information the Council had at that point in time and thus whether, on the information it relied on, the Council was negligent in issuing the CCC.

[81]     I have therefore proceeded on the basis that the Trust’s claim relates solely to the negligent issue of the CCC and not to any earlier acts or omissions, including the issue  of  the  building  consent  or  any  alleged  failures  or  shortcomings  in  the inspection process.

Does the Council owe the Trust a duty of care?

Why does the Council say no duty of care is owed?

[82]     The Council’s first challenge to the Trust’s claim was that it owed no duty of care to the Trust in issuing the CCC.   It argued that the case involved a “unique” factual matrix which took it outside the circumstances where the Supreme Court’s decision in Spencer on Byron, held there was a duty of care.3   Furthermore, looking carefully at the circumstances of this case, and applying the approach in the leading authority of South Pacific Manufacturing Co Ltd v New Zealand Security Consultant and Investigating Ltd,4 it argues that no duty arises.

[83]     In endeavouring to distinguish this case from cases such as Spencer on Byron

and Sunset Terraces,5 the Council pointed out that this is neither a traditional circumstance,  such  as  in  Invercargill  City  Council  v  Hamlin,6   where  a  modest

3      Body Corporate No 207624 v North Shore City Council [Spencer on Byron] [2012] NZSC 83, [2013] 2 NZLR 297.

4      South Pacific Manufacturing Co, Ltd v New Zealand Security Consultant and Investigating Ltd

[1992] 2 NZLR 282 (CA).

5      Body Corporate 188529 v North Shore City Council [2008] 3 NZLR 479 (HC).

6      Invercargill City Council v Hamlin [1994] 3 NZLR 513 (CA).

residential  house  is  the  subject  of  inspections,  nor  is  it  a  case  where  owners, including commercial owners, have purchased off a developer and where the Council has undertaken inspections.  Instead, the Council argues the Trust is effectively “the developer” and has engaged its own experts, and it is those experts, not the Council, which have inspected the work and provided the information on which the Council has issued the CCC.

[84]     Elaborating on the factual matrix which the Council says should exclude the existence of a duty of care in the present circumstances, the Council says the following considerations are relevant:

(a) The stadium is a community asset which is funded by the community, and which is insured against risk of loss, and the community should not have to “pay twice” by finding the Council liable.

(b) The terms of the lease with the Council are relevant, and point strongly to the Trust being responsible for building defects rather than the Council.

(c) Under the terms of the lease, the Council will either be the ultimate owner of the building through the provisions requiring vesting of the building in the Council at the end of the lease, or is already the owner as a consequence of the building being a fixture on the land.  In this situation, the Council says, it cannot owe a duty of care to itself as the owner, or subsequent owner, of the stadium.

(d) The Trust had full control of the building process, engaging the relevant contractors and exercising active day to day control of the project, unlike the subsequent purchasers in cases such as Sunset Terraces and Spencer on Byron.

(e) The building consent process differed because the Council did not inspect the work itself, but the works were always to be the subject of a PS4 provided by the Trust’s engineer.   The Council’s involvement and remuneration   was   negligible   compared   with   the   involvement   and

remuneration of Mr Major and this should be reflected in determining whether it should owe a duty.

(f)  Considerations of public interest should weigh in the mix.  Here, because the Trust has protected itself with insurance, it says the public interest does not dictate that the community, via the Council, should in turn have to meet that cost.

[85]     In this unusual factual scenario, the Council argues that there is no binding authority that a duty of care is owed and the question of whether it is reasonable to recognise a duty must be considered afresh, taking into account considerations of proximity and policy.  While acknowledging that the Council was in close proximity to the Trust, the Council argues that, having regard to the policy factors considered by Tipping J in Spencer on Byron, there were a number of policy considerations which pointed against a duty of care being imposed.

[86]     In Spencer on Byron, a factor telling in favour of a duty of care, was that it would be economically inefficient to require the owner of commercial premises to “have to engage a suitable professional to do exactly what the council is charged with doing under the Act”, saying “it is not unreasonable for owners of any kind of building to be able to rely on the council not to be negligent.  They should not have to pay twice to get that protection”.7   Here, the Council argues that, as Mr Major was engaged by the Trust for his services, including to observe the implementation of the remedial work, at a cost of around $80,000, and the Trust did not pay for any

Council inspections, the same consideration of efficiency points against finding that the Council owed a duty.

[87]     Secondly, the Council argues that it did not have control of the work, a factor which  was  central  to  the  policy choices  the  Court  made  in  Spencer  on  Bryon. Instead, the Council says that control was delegated to the Trust’s certified engineer because the Council inspector did not have the skill and expertise to ensure that the structural engineer’s design assumptions had been met during construction.   This,

too, points against finding a duty of care in these circumstances.

7      At [32]-[33].

[88]     The  Council  also  placed  some  reliance  on  William Young  J’s  dissenting

judgment in Spencer on Bryon where he observed:

[315]    All  in  all  the  extension  of  the  Hamlin  duty  to  non-residential buildings seems to me to give rise to policy issues of a kind which the courts are not well-placed to assess and quite likely to get wrong …

[316]    … Given that commercial and industrial buildings are owned either by investors or owner/occupiers, any losses associated with defects in their construction are investment or business in nature and thus, are not of a kind that is obviously appropriate for spreading amongst the community, by territorial authority.

By analogy, in the unique factual circumstances, the Council argued this was a case where William Young J’s reasoning should prevail as it was not appropriate for the community to bear the cost of rectifying defects in the Trust’s construction project.

[89]     Finally, the Council placed some reliance on the indemnity clause in the ground lease to the Trust which provided:

The [Trust] shall indemnify and keep indemnified the [Council] from and against all actions, suits, claims, demands, proceedings, losses, damages, compensation, costs, charges and expenses whatsoever which may arise during  construction,  erection  or  operation  of  any  authorised  building  or works or activity ….

[90]     The  Council  says  this  is  broadly  enough  worded  to  cover  liability  for negligence in its regulatory role and emphasises that no duty exists.

Why does the Trust say a duty of care is owed?

[91]     The Trust, in response, relies squarely on the decision in Spencer on Bryon, where the Supreme Court, by a four to one majority, held that a territorial authority’s building regulation duties apply to all premises, not just residential.  There is nothing in the Court’s decision in that case to suggest that any category of building was excluded from this duty.  Rather, it held that “the duty of care is owed regardless of

the nature of the premises”.8

[92]     The Trust says the same point is reached if the question of whether a duty should be recognised is approached afresh, applying the test of whether it is fair, just

8 At [216].

and reasonable to impose the relevant duty on the defendant.   Accepting that proximity is the threshold requirement, and is present in this case, then a duty should be recognised unless that would not be in the public interest.

[93]     In this regard, the Trust points to the relevance of the statutory framework of the 1991 Act which is “to provide the owner with assurance of compliance.   If, through want of care on the part of the Council, that system of assurance fails, then the owner is entitled to look to the Council for his loss”.9   That statutory framework points strongly to a duty in this case where the collapse which occurred is precisely the kind of sudden structural failure which the 1991 Act and the associated building code is intended to prevent.

Is a duty of care owed?

[94]     I approach the question of whether a duty of care is owed on the basis that the Trust  and  the  Council  are  separate  legal  entities  and,  at  the  point  the  damage occurred, the Council did not own the building.  I address the Council’s argument on the ownership issue separately, but conclude that the Trust did own the building when the damage was suffered.

[95]     I also consider the terms of the lease separately.  If the indemnity is to have the effect contended for by the Council, that would govern whether any liability the Council has should be met by the Trust, but not whether the Council owes a duty to the Trust and to subsequent owners or users of the stadium to take reasonable care when issuing a CCC.

[96]     In the present case, the issue is whether there are any factors which put the Trust outside the finding in Spencer on Byron which recognised a duty of care “regardless of the nature of the premises”.  I do not think there are.  The decision in Spencer on Byron was not confined to whether the duty of care owed by building regulators applied  to a discrete category of buildings beyond residential homes. Rather, the question was whether such a duty was owed in respect of all buildings

coming under the 1991 Act’s regulatory regime.

9      Spencer on Byron, above n 3 at [14].

[97]     In concluding that policy reasons supported a general duty of care, the Court made findings which contradict the policy arguments raised by the Council.   In particular:

(a) The existence of the duty was not dependent on the relative level of payment made.  The Supreme Court held that the imposition of the duty was intended to provide compensation for economic loss, without the plaintiff necessarily having to pay for this protection, noting in particular that subsequent purchasers were not distinguished from the first owner even though they had not directly paid for the services of the inspecting

authority.10    In any event, recognising a duty in tort does not cut across

contractual obligations which, say, a supervising architectural engineer, may have to the first owner who employed their services.11

(b) The degree of control that entities such as the Trust exercise over the construction process, for example, by retaining their own architects and engineers, was held to be irrelevant to the imposition of a duty in both Sunset Terraces and in Spencer on Byron.

(c) Equally,  the  relative  lack  of  “vulnerability”  of  commercial  building developers, as compared with residential home owners, was also held to be irrelevant.   First, there was no basis on which to assume that all residential owners are vulnerable, whereas owners of commercial properties are not.  While the Court accepted that, in general, there was less reliance on the local authority with respect to commercial buildings, that was not a strong policy factor and, in any event, a plaintiff did not

have to prove reliance as an element of the tort.12

(d) The argument that policy considerations pointed against transferring the cost to rate payers was answered by the joint judgment in Spencer on

Byron which stated:13

10 At [191].

11 At [193].

12     At [196]-[201].

13 At [203].

The burden has not been shifted to ratepayers but rather to councils, whose financial backing is much greater than virtually all commercial building owners.  Local authorities may, in the event their officers are negligent, meet liabilities from insurance (if available), the income generated by carrying out inspection work, or, in the last resort, rates. Everybody contributes to rates, whether directly or indirectly.   Since everybody uses buildings, everybody gains the benefit if, by imposition of a duty in tort, buildings are rendered safer and healthier.

[98]  The  Council  sought  to  differentiate  the  stadium  from  the residential/commercial building discussion in these judgments.   However, I can discern no rational basis for considering this as a different kind of building in respect of which the Council should not owe a duty of care.  If anything, the fact the Trust was comprised of volunteers, proceeding with construction on the strengths of grants and donations, supports the recognition of a duty.   It meant they were not in a comparable position to commercial building owners who William Young J, in his dissenting judgment, considered should carry any losses associated with defects in their construction as a business risk, rather than spreading it amongst the community via the territorial authority.   Furthermore, the stadium was a community building constructed for the benefit of the public at large, and the case for the territorial authority to ensure its compliance with the building code, and to make good the owner’s losses if it was not, are far stronger.

[99]     In conclusion, there is nothing in the circumstances of the case which takes it outside the framework of obligations established in Spencer on Byron and I accept that the Council did owe the Trust a duty of care when deciding whether to issue a CCC for the remedial work on the stadium roof.

Did the Council own the stadium, and if so, does this negate the imposition of a duty of care?

[100]   Notwithstanding what might be the position if a building such as the stadium was separately owned, the Council says that the contractual relationship between the parties under the lease is relevant to whether or not there is a duty owed by the Council to the Trust in this particular circumstance.

[101]   The Council is the owner of Surrey Park, which is the local purpose reserve on which the stadium is built.  Once it was decided that Surrey Park was the most

suitable location for the stadium, a lease was entered into between the Council and the Trust to permit its erection on part of that reserve land.

[102]   The key terms of the lease between the Council and Trust were as follows:

(a) The lease was for a term of 33 years commencing on the first day of

July 1999.

(b) Clause 4 restricted the use of the land to a community building and recreational facility to ensure compliance with the Reserves Act 1977 which allowed the lease for that purpose only.

(c) Clause 6 prevented any assignment or sale of the land without the consent of the Council.

(d) Clause 8 required the Trust to keep the stadium in good repair, order and condition.

(e) Clause 17 required the Trust to insure all buildings and structures for fire in the name of both the Council and Trust.

(f)  Clause 19 provided that there would be no compensation payable to the Trust on expiry of the lease.  The stadium would revert to the Council and the Trust would not be entitled to compensation for those improvements.

(g) Clause 20 provided that the Trust had no right to acquire the fee simple of the land.

(h) Clause 23 provided that the Trust indemnified the Council against all actions, suits, claims, demands, proceedings, losses, compensation costs, charges and expenses which may arise during construction, erection or operation of the authorised building works.

[103]   Subsequently, Stadium Southland Limited was incorporated for the purposes of managing the stadium.   It was a company that was 100 per cent owned by the

Trust and, on 1 October 2005, the Trust and SSL entered into a sublease for the stadium and this was subsequently recognised in a variation of lease dated 2005.

[104]   The Council argues that, when the stadium was constructed, it was affixed to the land and therefore belongs in law to the Council as the owner of the land.  The subjective intention of the parties could not affect the position.14   Consequently, the Council says the evidence relied on by the Trust to say the building was owned by the Trust, including Council minutes, media statements issued by the mayor, and assets schedules in the Council’s Long Term Council Community Plan, is irrelevant. Because, the stadium is affixed to the land owned by the Council, and therefore, as a matter of law, is the property of the Council, the Council says it could not have owed

a duty to the Trust.

[105]   The Council says the terms of the lease agreement do not contradict that position.  The provisions which confirm that the improvements effected by the lessee revert to the lessor without compensation, implicitly acknowledge the legal position as to ownership and there is no contractual provision in the lease which contradicts it.

[106] The Trust, in response, relies on Lockwood Building Ltd v Trust Bank Canterbury Ltd, which held that, notwithstanding the legal position as it might apply to third parties, in relation to questions which arise between the land owner and the person claiming an interest in the item affixed to the land:15

[T]hose persons may regulate the issue between them as they see fit by contract or otherwise.  In some cases an estoppel may arise preventing one of them from asserting the legal position.

[107]   Here, the Trust says, it was acknowledged by both the Council and the Trust that the stadium needed to be owned by the Trust, a charitable organisation, in order to maximise access to grants and other community funding.  The terms of the lease

agreement confirmed this position in that they reflect that the Trust would continue

14     Elitestone Ltd v Morris [1997] 1 WLR 687 (HL); Melluish (Inspector of Taxes) v BMI (No. 3) Ltd [1996] AC 454(HL).

15     Lockwood Building Ltd v Trust Bank Canterbury Ltd [1995] 1 NZLR 22 (CA) at 29.

to own the stadium while the lease continued, but when the lease terminated, ownership of the stadium would pass to the Council.

[108]   I  accept  that  the  evidence  of  the  contractual  arrangements  between  the Council and the Trust are consistent with the Trust owning the stadium during the term of the lease.   In particular, the lease was of “the said land” only, and the buildings established on the land are referred to separately and have discrete obligations applying to them.  Recognition of the Trust’s ownership is also implicit in its obligations to maintain and insure the stadium, and in the need for an express provision to say that the stadium would revert to the Council without compensation being paid.

[109]   This  is  consistent  with  the  numerous  statements  in  Council’s  official documents which acknowledge the Trust’s ownership of the stadium, including in its agreement of 10 June 2009 regarding the structure of ownership, governance, management and operation of the stadium and the civic theatre, in its LTCCP, and in public   information   leaflets   and   media   statements   by   the   Council.      Even Mr Cambridge, the Council’s solicitor, accepted that the lease provided that the Trust would own the stadium until the lease terminated, and it was at that point that ownership would vest in the Council.

[110]   In those circumstances there is no need to consider whether the Council is estopped from asserting that the Trust owns the stadium, which was the Trust’s fallback position.

[111]   However, even if it was not the case that the Trust owned the stadium, it enjoyed  a  range  of  proprietal  rights  under  the  lease  which,  in  my  view,  were sufficient to support the existence of a duty of care owed by the Council to the Trust. Where that duty was breached it was reasonable to require the Council to meet a claim for damages, being the cost to put the Trust back in the position it was in under the lease where it had a fully functioning stadium available to provide recreational facilities to the public.

[112]   Nothing in these arrangements detracts from the existence of a duty of care I have found was owed by the Council to the Trust, when carrying out its regulatory obligations under the 1991 Act.

Did the Council breach its duty of care to the Trust?

[113]   The  Trust   says   the   Council   was   negligent   in   issuing   the   CCC   on

20 November 2000 because the person who signed and issued it:

(a) did  not  have  reasonable  grounds  to  be  satisfied  that  the  works,  as constructed, complied with the building code;

(b) was not in fact satisfied that the works, as constructed, complied with the building code;

(c) did so without the knowledge, consent or authorisation of Mr Tonkin, the chief building inspector in charge of the building consent team, or any other authorising source; and

(d) did not have compliance with condition 4 or condition 5 of the building consent.

[114]   The Council, in response, says:

(a) Council  officers  did  not  have  the  requisite  skill  level  to  identify the welding defects and it was reasonable therefore to impose a requirement for a producer statement, rather than to inspect the work itself;

(b) it is reasonable for the Council to place reliance on a certificate from an experienced local structural engineer who worked in the same building as the architect on the job and was a member of IPENZ, as was the case here;

(c) while the Council accepts that at the time of issue of the CCC the Council did   not   have   reasonable   grounds   for   issuing   it,   by  the   end   of

November 2001, when it had obtained the PS4 and the datum heights of the trusses, it would have had reasonable grounds to issue the CCC at that stage, and could have issued it non-negligently at that stage so any negligence in issuing it sooner was not causative of the loss; and

(d) in any event, at that stage, Council had still to issue the CCC for the overall stage 4 structural work and could have declined issue of that until it had the information sought under conditions 4 and 5 of the building consent.

The statutory framework for issuing a CCC

[115]   Code  compliance  certificates  are  issued  under  s  43  of  the  1991  Act. Relevantly, it provides:

(3)       Except  where  a  code  compliance  certificate  has  already  been provided pursuant to subsection (2) of the section, the territorial authority shall issue to the applicant in the prescribed form on payment of any charge fixed by the territorial authority, a code compliance certificate, if it is satisfied on reasonable grounds that-

(a)  the building work to which the certificate relates complies with the building code; or

(b) the building work to which the certificate relates complies with the building code to the extent authorised in terms of any previously approved waiver or modification of the building code contained in the building consent which relates to that work.

(8)       Subject to subsection (3) of this section, a territorial authority may, at its discretion, accept a producer statement establishing compliance with all or any of the provisions of the building code.

[116]   Section 2 of the 1991 Act defines producer statements as:

“Producer statement” means any statements supplied by or on behalf of an applicant for a building consent or by or on behalf of a person who has been granted a building consent that certain work will be or has been carried out in accordance with certain technical specifications.

[117]   Section  47  provides  a  list  of  matters  which  territorial  authorities  must consider in relation to the exercise of its powers, including under s 43.  It says:

47Matters for consideration by territorial authorities in relation to exercise of powers

In the exercise of its powers under sections 30 to 46 and 64 to 71 of, and Schedule 3 to, this Act the territorial authority shall have due regard to the following matters:

(a)       The size of the building; and

(b)       The complexity of the building; and

(c)      The location of the building in relation to other buildings, public places, and natural hazards; and

(d)       The intended life of the building; and

(e)       How often people visit the building; and

(f)       How many people spend time in or in the vicinity of the building; and

(g)      The  intended  use  of  the  building,  including  any  special traditional and cultural aspects of the intended use; and

(h)      The   expected   useful   life  of   the   building   and   any prolongation of that life; and

(i)        The reasonable practicality of any work concerned; and

(j)       In the case of an existing building, any special historical or cultural value of that building; and

(k)      Any other matter that the territorial authority considers to be relevant.

Standard of care

[118]   It was not disputed that the Council had an obligation to exercise reasonable care in issuing the CCC.  The required standard is objective, and is based on what would be expected from reasonably competent and experienced persons undertaking that role within a territorial authority.16   However, that is not necessarily the same as what the general practice is in those organisations, as that may not be consistent with

the legal standard of what a reasonable and prudent building inspector would do.

16     McLaren Maycroft & Co v Fletcher Development Co Ltd [1973] 2 NZLR 100 (CA) citing Sulco

Ltd v E S Redit & Co Ltd [1959] NZLR 45 (SC).

[119]   One of the difficulties in the present case was that the Court was required to judge the Council on the standards of a territorial authority in the year 2000, not what  is  expected  of  a  reasonable  and  prudent  council  in  2015,  as  the  relevant standard is what a reasonable person in the defendant’s position would have done at the time.  For example, in Askin v Knox, when dealing with an inspection of diggings which had taken place 20  years earlier, the  Court was conscious of applying a

standard which would have been regarded as reasonable at the time.17   It concluded

that the building inspectors were not negligent, saying that, “acting according to the standards then regarded as reasonable, [they] may have been less conscious of the risk of subsidence that has been underlined by the litigation of more recent decades”.18

[120]   In this case, the Trust relied heavily on the comprehensive 2014  IPENZ guidelines on accepting producer statements, saying these represented the standard a prudent Council should have adopted when accepting a producer statement for the construction review of the remedial works.  However, the Council argued it would be unfair to judge its staff by standards which have been developed with the experience of hindsight, including the lessons learned from Christchurch earthquakes, and from the revision of the Building Act in 2004.

[121]   However, this issue only needs to be looked at in the context of causation, because it is only there that the adequacy of the PS4 which was provided arises.  The PS4 was not provided until 2001, and there was no evidence, as originally suggested, that the Council relied on an “oral” PS4, or on a promise that a PS4 was “on its way”.

Did Council breach its duty of care on 19 November 2000?

[122]   The question of whether there was a breach of Council’s duty of care on

19 November 2000,  when  it  issued  the  CCC,  can  be  disposed  of  easily.    The evidence revealed that there was no considered decision made under s 43(3) of the

1991 Act as to whether the Council could be satisfied on reasonable grounds that the

remedial work on the community trusses complied with the building code.  In fact,

17     Askin v Knox [1989] 1 NZLR 248 (CA).

18     At 252.

the Council’s building inspector, Mr Tonkin, did not consider whether to issue the CCC at all.  It happened without his knowledge or authority.  When that evidence came to light it made more sense of what occurred, as Mr Tonkin struck me as a conscientious and diligent Council building inspector.  I believe he would not have issued a CCC without evidence before him, including a PS4, to satisfy him that it was appropriate to do so.

[123]   The person who signed the CCC was not competent to make the required statutory decision, and it was unknown what grounds she relied on to make the decision.   She did not have a PS4 or any other information on which she could reasonably form the view that the requirements of the building code were met so the statutory  requirements  of  s  43  were  not  met.    This  was  acknowledged  by  the Council’s own expert witnesses, Mr Jordan, to be “surprising” and not acting as he would expect a prudent Council to act.  I agree.

[124]   Faced with the clear evidence of a breach at the time the CCC was issued, the Council was forced to resort to its fallback position based on causation.  It argued that  if  it  had  been  negligent  in  issuing  the  CCC  in  2000,  then,  by the  end  of November 2001 when it had both the PS4 and the datum heights for the trusses, it could have issued the CCC non-negligently, and the loss would have ensued in any event.  This approach shifts the focus on Council’s negligence back to its reliance on the PS4 supplied by Mr Major, and on the provision of measurements relating to the height  of  the  trusses,  but  without  compliance  with  condition  4  of  the  building consent.

Was the negligent issue of the CCC in November 2000 causative of the Trust’s

loss?

[125]   Despite my finding that it was clearly negligent to have issued the CCC in November 2000, the Council answered this saying the negligence was not causative of the loss because it would not have been negligent to issue a CCC in reliance on the information it had by 28 November 2001.  That meant the collapse would have happened anyway, in the absence of negligence.

[126]   To succeed, the Council must affirmatively show that the loss would still have happened without any negligence on its part.   The Trust’s submission emphasised that it was insufficient for the Council to show that the plaintiff’s loss might still have occurred, but that it must positively show that despite its negligent act or omission, the loss would still have occurred.19

Would Council have breached its duty of care if it issued a CCC for the remedial works on 28 November 2001?

[127]   By 28 November 2001, which was just over a year after the CCC was issued, the Council had the following information:

(a) a PS4 from Mr Major, along with an accompanying letter; and

(b) a plan showing the height of each truss in the community courts at its midpoint, above floor level.

[128]   The PS4 had been provided in January 2001, and the covering letter dated

16 January  2001  provided  a  description  of  how  the  construction  works  for  the remedial work at community court trusses was carried out.  The letter said in relation to that work:

and the Trust chose the latter option.

37     See J and B Caldwell Ltd v Logan House Retirement Home Ltd [1999] 2 NZLR 99 (HC) at 106;

Gunton v Aviation Classics Ltd [2004] 3 NZLR 836 (HC).

[193]   Finally, the Council says that the fact that, under the lease, the building is to vest  in  the  Council  at  the  end  of  the  lease  should  not  tell  against  making  an allowance for betterment.   That is because the lease obliges the Trust to keep the improvements in good repair, order and condition during the term of the lease and it is the saving on this obligation which justifies a deduction for betterment.

The Trust’s position

[194]   The Trust’s primary position is that the Council should not be entitled to a

deduction in respect of any new-for-old betterment because:

(i) the  Trust  is  being  forced  to  incur  capital  expenditure  to  replace building elements that it would not otherwise have had to incur during the term of the lease; and

(ii) the  Council  will  be  the  ultimate  beneficiary  of  this  expenditure because, at the end of the lease, the Council will acquire a newer stadium from the Trust than it would have had received otherwise, without having to pay the Trust any compensation.

[195]   If it is determined that a deduction should apply, then the Trust says it should not be based on the “crude percentage discount” approach adopted by the Council but:

(a) must be limited to the betterment that the Council can show as increasing the Trust’s  revenue  and/or  reducing  its  expenses, as  the  newer items provide no corresponding pecuniary advantage to the Trust, such as an increase in value ultimately realisable on sale;

(b) must balance any such pecuniary advantage against the detriment to the Trust  of  an  unexpected  and  unwanted  capital  payment  that  the Trust would never otherwise have had to make or, at least, would not have had to make until a much later date;

(c) must reflect the fact that the Council has not shown that the Trust will obtain any real pecuniary advantage from the new-for-old items, and nor has it made any allowance for the carrying cost incurred as a result of the advanced capital expenditure; and

(d) should be based on the depreciation rates that the Council applies to its own buildings and its asset management plan, and not the Trust stadium project list which was prepared in 2008 for a different purpose, and which does not bear a reliable relationship to what has actually been required in terms of maintenance or replacement.

[196]   Applying these principles, a more realistic assessment of the deduction for betterment, if one is to be applied at all, is the figure of $828,373.32 calculated by the Trust’s expert witness, Mr Burrows.

Legal principles applying to betterment

[197]   There is no doubt that the Trust is entitled to be put back into the same position, so far as the money can do so, that it would have been in were it not for the Council’s negligence.  However, where, as here, there is no second-hand equivalent readily available, the plaintiff is forced by the defendant’s negligence to substitute what was lost with something new.

[198]   The Courts have regularly had to grapple with the dilemma that, where the plaintiff  receives  new-for-old,  it  may  be  overcompensated  and  have  acquired  a benefit at the defendant’s expense.  However, to give the plaintiff no more than the depreciated value of the original item which was lost may under-compensate the plaintiff by ignoring the economic burden of having to obtain an immediate and more expensive replacement.  Thus, any deduction for betterment may need to be reduced to take account of any economic cost to the plaintiff of investing in new-for- old at a point in time when it would not otherwise have done so.

[199]   Resolving  these  tensions  is  highly dependent  on  the  particular  facts  and circumstances of each case.38   Where the plaintiff had “no reasonable choice but to replace” a damaged building, that may be a factor counting against any significant deduction for betterment.39   It is then for the defendant to prove the value and extent of any betterment.40

[200]   The  relevant  principles  to  consider  when  deciding  whether  to  allow  a deduction  for  betterment  were  articulated  in  Voaden  v  Champion  (The  Baltic Surveyor and the Timbuktu) where Rix LJ said:41

I suspect … that the true principle is that in the relevant cases the betterment has  conferred  no  corresponding  advantage  on  the  claimant.    Take  the ordinary case of the repair of some part of a machine.  Where only a new part  can  be  fitted  or  is  available,  the  betterment  is  likely  to  be  purely nominal:  for unless it can be posited that the machine will outlast the life left in the damaged part just before it was damaged, the betterment gives the claimant no advantage; and in most cases any such benefit is likely to be entirely speculative.  So in the case of replacement buildings:  the building may be new, but buildings are such potentially long-lived objects that the mere newest of a building may be entirely by the way … Even where the replacement is of a moderately bigger size … in the absence of any reason for thinking that the bigger size is of direct benefit to the claimant, he has merely mitigated as best he can.  If, however, it were to be shown that the bigger size (or some other aspect of betterment) were of real pecuniary advantage to the claimant, as where, for instance, he was able to sublet the

20 per cent extra floor space he had obtained in his replacement building, I

do not see why that should not have to be taken into account.  It is after all a basic principle that where mitigation has brought measureable benefits to a

claimant, he must give credit for them.  …

How should the principles apply in this case?

[201]   There is no dispute that the only practicable option for the Trust was to rebuild the stadium and so it received a new building in place of a 10 year old building.  The real issue is whether it can be said to have received any real pecuniary advantage or benefit from having to incur the cost of replacing the stadium, when under its  lease arrangement  with  the Council, it  is precluded from  gaining any commercial  benefit  from  the  newer  building,  either  through  sale,  or  through  a

compensatory payment on termination of the lease.

38     Hyder Consulting (Australia) Pty Ltd v Wilh Wilhelmsen Agency Pty Ltd [2001] NSWCA 313 at

[107].

39     Hyder Consulting (Australia) Pty Ltd, above n 38 at [49].

40     J and B Caldwell Ltd v Logan House Retirement Home Ltd, above n 37 at 109.

41     Voaden v Champion (The Baltic Surveyor and the Timbuktu) [2002] EWCA Civ 89.

[202]   I am satisfied that, because of the terms of the lease between the Trust and the Council, the Trust receives no benefit simply because it has a newer, and therefore more valuable, building.   The only value of the building to the Trust was that it enabled the Trust to provide a certain level of facilities and amenities to the public of Southland, for a finite period of time.  A new building gives no practical benefit to the  Trust  in  the  delivery  of  that  outcome,  over  and  above  a  well  maintained

10 year old building, and of course, no pecuniary advantage to the Trust, because it cannot sell it.

[203]   Equally though, I reject the idea that any benefit to the Trust in terms of having a new building should be cancelled out by the benefit to the Council in that, when the building vests in Council, it, too, will receive the benefit of a 10 year younger building.  When the building vests it will either be a 23 year old building as opposed to a 33 year old building, or a 56 year old building as opposed to a 66 year old building.  Not only do I have no evidence by which I can quantify the difference in value of what Council will receive, but it, too, presumably, will hold the building for community recreation purposes, rather than for sale as an asset and will receive no pecuniary benefit from having a newer building vest in it.

[204]   However, there is merit in the submission that by replacing the 10 year old stadium with a new stadium, the Trust will benefit from some reduction in the cost of meeting its obligation to replace or refurbish components of the stadium in order to keep it in good repair.  However, quantifying that saving is more difficult.

[205]   The first problem in quantifying the saving is that the time period over which the saving is made is uncertain because there is a right of renewal in the lease, but it is unknown whether that will be taken up.  I consider, therefore, that I should only have regard to savings which are achieved in the first 33 year term of the lease, as that is the only period where there is reasonable certainty of tenure.

[206]   The  second  problem  is  there  is  no  certainty  over  how  to  quantify what pecuniary advantage the Trust receives based on the potential to avoid one replacement or refurbishment cycle for some stadium components.

[207]   The Council’s quantity surveyor, Mr Green, endeavoured to quantify this on a component by component basis by calculating the difference in value of having a new component over a partly depreciated component.   To do this, his evidence relied, at least in part, on a document described as a stadium project list.   This document was prepared in 2008 to help analyse the capital replacement, maintenance and operational costs required for the running of the stadium, in order to provide an indication of its future funding requirements.   The list categorised the various components of the stadium structure and then estimated how often that item would need to be replaced or refurbished, and at what cost.  For example, the floor of event court one was predicted to require replacement each 10 years at a cost, in 2010, of

$93,591.  It would also need resurfacing every two years, in between replacement, at a cost of $18,718.  The exterior roof needed repainting every 20 years at a cost of

$218,380, but replacement in 2040, when it was 40 years old, at a cost of $960,871.

[208]   Mr Green’s assessment took the estimated life for each component, at which stage it would have depreciated 100 per cent, and determined what “benefit” the Trust had received by receiving a new component, rather than a partly depreciated component.  For example, the exterior steel cladding was assumed to have a 35 year lifespan.  Thus, at 10 years old, when 28 per cent of its lifespan had been spent, it was assumed to have depreciated 28 per cent.  He then calculated what 28 per cent was of the new price of the cladding to calculate the financial benefit of the “betterment” that the Trust had received by having the 10 year old cladding replaced with new cladding.

[209]   I consider, though, that Mr Green’s approach fails to take account of the unusual context of this case.  His approach can be applied to a normal commercial building, where either the existing owner gains the benefit of the extended life of the component, or where it can be reflected in the value of the building, if sold.  Here, though, the finite period of the Trust’s ownership skews such benefits.  For example, if a component does not need replacing in the term of the lease, because its expected

lifespan is more than 33 years,42 then the Trust has had to incur the cost of replacing

a component  which  it  would  not  otherwise have had  to  replace.    However,  by replacing other components, it may have deferred a maintenance obligation, such as

42     Such as the exterior cladding.

repainting the roof.   Depending on the timing of the maintenance cycle, that may have saved the Trust one occurrence of such expenditure during the term of the lease.

[210]   Determining whether a maintenance cycle, or replacement cycle, has been avoided by the Trust through rebuilding the stadium, would be possible to calculate, if there was an agreed maintenance schedule.  However, the reliability of the stadium project list, which attempted to provide such a maintenance schedule, was hotly disputed by the Trust.   The stadium manager, Nigel Skelt, pointed out that in the period 2008-2010, the schedule predicted expenditure of $1,700,000 but the accounts showed that only a fraction of that expenditure had been incurred.  The Trust argued that that put in question the reliability of the stadium project list as a maintenance schedule, particularly when  Mr Skelt’s  evidence  was  that  the building  was  well maintained, and the shortfall in expenditure was not as a consequence of deferring necessary maintenance or letting the stadium fall into a state of poor repair.

[211]   Thus, as Mr Green acknowledged in cross-examination, and I accept, the stadium project list could not be relied on to determine when items would need to be refurbished or replaced.

[212]   Equally, Mr Burrows’ evidence does not provide a practical assessment of the maintenance savings achieved by the Trust as a consequence of having to rebuild the stadium.   He, too, approaches the assessment of betterment in a similar way to Mr Green, but using the different (and generally lower) depreciation rates which are used by the Council itself, to calculate his betterment figure of $828,373.32.

[213]   In  the absence of an  agreed  maintenance and  replacement  schedule, and given my view that the approach taken by the quantity surveyors does not accurately reflect the Trust’s loss, I am compelled to take a more impressionistic approach to the quantification of betterment.

[214]   This is not unusual.  In the Caldwell case, Fisher J emphasised “the need for a broad and robust judgment on such evidence as was available”43  and, in Gunton,

43     J and B Caldwell Ltd, above n 37 at 113.

Chambers J observed that “flexibility must be maintained to accommodate the facts

of each particular case”.44

[215]   Here, I am satisfied that the defendant has established there will be a level of pecuniary benefit to the plaintiff, through avoiding one cycle of refurbishment or replacement on some components of the building.  I do not, however, accept that it has received a benefit simply through the comparative “newness” of the components, as  has  been  calculated  in  different  ways  through  Mr Green’s  and  Mr  Burrows’ evidence.   However, some of their evidence does, in effect, take account of that, particularly where an item at or near the end of its life, is replaced through the rebuilding process.

[216]   I also do not accept that an allowance should be made for any carrying cost the Trust has incurred. Again the facts of this case differ from those which involve a normal commercial entity.   I have been given no evidence that the Trust itself has had to borrow funds or forgo interest as a result of the early expenditure.  Instead the evidence has been that it relies on external grants and funding to meet its expenses as they arise.

[217]   In the end, I consider a deduction for betterment of five per cent of the rebuild cost reflects a reasonable estimate of the cost savings in maintenance that the Trust will achieve through the term of the lease by having a rebuilt stadium.  That translates to a figure of just over $750,000, and which I consider should be rounded to that figure.  If I take the average of Mr Green’s and Mr Burrows’ calculations for betterment for “newness” of the components, which is $1,185,188, then $750,000 reflects approximately two-thirds of that figure.  I am satisfied that figure reasonably reflects the proportion of the betterment factor calculated by the quantity surveyors that can be attributed to reduced maintenance costs as opposed to simply the “newness”  of  the  items.    Accordingly,  I  make  a  deduction  for  betterment  of

$750,000.

44     Gunton, above n 37 at [175].

Is GST payable on the damages award?

[218]   The final issue is whether or not the Trust is entitled to GST on the rebuild cost and, if so, whether GST is payable on the damages including or excluding interest.

[219]   The issues arise because this is a subrogated claim brought by the Trust, as plaintiff, at the request of its insurer, IAG, under the terms of the policy.  Thus any judgment sum will be payable in the first instance by the Council to the Trust. However, any recovery by the Trust will ultimately be paid over to IAG, which must

account for GST on that sum.45     There is therefore an obvious interest in IAG

arguing that the Trust, too, should have GST added to its claim.

Why the Trust says GST should be added to the damages award

[220]   The Trust says that it will have to account for GST on the judgment sum once it received payment from the Council, as a consequence of s 5(13) of the Goods and Services Tax Act 1985 (the GST Act).  In order to be fully compensated by the award of damages, the Trust must therefore recover the judgment sum, plus GST, from the Council.

[221]   Section  5(13)  of  the  GST Act  provides  that  where  “a  registered  person receives a payment under a contract of insurance … the payment is … deemed to be consideration received for a supply of services performed by the registered person”, and it must account for GST on that payment.  The Trust argues that in this context, the words “under a contract of insurance” have a broad meaning, and do no more than require some causative relationship between the contract and the payment.  It says this does not have to be a direct relationship.  For example, the plaintiff may have to account for GST despite the fact that it was not a party to any relevant insurance contract, such as a plaintiff who receives a payment from its tortfeasor’s liability insurer by virtue of its charge on the insurance monies under the Law

Reform Act 1936, s 9(1).46

45     Goods and Services Tax Act 1985, s 5(13B).

46     Pegasus Group Ltd v QBE Insurance (International) Ltd HC Auckland CIV-2006-404-6941, 24

September 2010 at [12].

[222]   The Trust argues that the claim was brought by the Trust as a consequence of its obligations to IAG under the express terms of the policy which, at clause GC10, provides:

The Insured shall at the request of and at the expense of the Insurer take such action as may be necessary or reasonably required by the Insurer for the purpose of enforcing any right and remedies, or of obtaining relief or cover from other parties to which the Insurer shall be or would become entitled or subrogated upon paying for or making good any loss under this policy whether before or after being paid by the insurer.

[223]   As a consequence, the Trust argues that any judgment sum the Council is required to pay the Trust as a consequence of such proceedings is captured as a payment which is “under a contract of insurance”, albeit indirectly, and GST is payable by virtue of s 5(13).

[224]   The Trust then also says that, because the amount the insurer receives from the Trust as a result of exercising its rights of subrogation under the contract of insurance is a taxable supply under s 5(13B) of the GST Act, it makes sense that the Council’s payment to the Trust should also have GST applied to it.   It says that would achieve consistently between the provisions of s 5(13) and s 5(13B), allowing the one payment to flow through to the other.

Why the Council says GST should be excluded from the damages award

[225]   The Council, on the other hand, argues that the position of the insurer is irrelevant to whether GST is payable as between the Trust and the Council.   That question must be determined using the standard enquiry as to whether the payment of damages represents a taxable supply by the Trust to the Council which attracts GST  under  the  GST Act.    The  Council  says  it  does  not,  as  it  is  a  claim  for compensation, which is not a taxable supply.  Furthermore, as in Gunton v Aviation

Classics Ltd,47 any GST the Trust expended in repairing the stadium was able to be

claimed back by the Trust and so GST should be excluded from the calculation of damages, to avoid overcompensating the Trust.

47     Gunton v Aviation Classics Ltd, above n 37.

Should GST be added to the award of damages?

[226]   I first consider whether GST would be payable on any damages I award to the

Council, leaving aside the question of the insurer’s obligation to pay GST under s

5(13B) and the question of whether s 5(13) changes the position.

[227]   In  the  present  circumstances,  I  am  satisfied  that  the  GST  position  is analogous to that in Gunton, where Chambers J held that, because the plaintiff was able to deduct the GST charged on the repairs as input tax, if GST was then to be included as part of the damages, the plaintiff would be overcompensated.  To fully compensate the plaintiff, it only required an award which equalled the net cost of the repairs.

[228]   The same approach has been adopted in a decision of the New South Wales, Court of Appeal in relation to the application of GST to an award of damages.  In Gagner Pty Ltd (t/as Indochine Café) v Canturi Corporation Pty Ltd, Campbell JA said: 48

[151]    In summary, as the GST legislation currently stands, if the plaintiff in an action for tort is registered for GST purposes, and stands to receive an input credit for any GST payments incurred in making good its damage, and there is no impediment to the plaintiff receiving the full benefit of the input credit, that GST amount should be excluded from the quantum of damages recoverable.

[229]   Like the plaintiffs in Gunton and Gagner, the Trust is GST registered and its loss is therefore the cost of repairs, and of its lost rent, net of GST.

[230]   I also accept the Council’s argument that the damages award here does not constitute a taxable supply for GST purposes because there is no reciprocal supply by the other party.  Instead the payment is compensatory in nature and is intended to put right the loss caused by the defendant’s negligence.

[231]   The Trust’s next argument is that, whatever the position might normally be, s 5(13) alters it because, at least in an indirect way, any payment received from the

Council and paid to the Trust is a “payment under the insurance contract” for the

48     Gagner Pty Ltd (t/as Indochine Café) v Canturi Corporation Pty Ltd [2009] NSWCA 413, (2009) 262 ALR 691.

purposes of that section, because it results from the insurer exercising its rights of subrogation under the policy.

[232]   The Council’s argument turns on a question of statutory interpretation and whether it is correct to categorise a damages award payable to the Trust in these proceedings as payment under the insurance contract.

[233]   I consider that the only logical reading of s 5(13) is that it only captures payments made by the insurer to a person entitled to the benefit of the payment, whether or not the recipient is a party to the insurance contract.  While the section specifies (as Winkelmann J noted in Pegasus Group Ltd),49  that the recipient of the payment need not be the insured, that does not justify broadening the scope of the clause to encompass payments which are not made by the insurer and which the insured would be entitled to receive independently of the insurance contract.   Put another way, the Trust would be entitled to sue the Council regardless of whether it

was insured.  Thus the payment it receives from the Council is not “under a contract of insurance”.   The fact that the Trust has contractually bound itself to seek such payment, and then pass it back to its insurer, does not alter the position that the payment by the Council relates to a separate set of obligations and not obligations under the policy of insurance.  Section 5(13) should be read as encompassing only a payment which an insurer is obliged to make under a contract of insurance, whether or not the recipient is the insured party.

[234]   I therefore am satisfied that s 5(13) does not apply to the damages payment the Council is to make to the Trust and my conclusion that GST is not payable on the damages awarded does not alter.

Should GST be added to the interest inclusive, or interest exclusive, judgment sum?

[235]   Because of my conclusion that GST is not payable on the damages, I am satisfied that this issue does not arise for consideration.

49     Above n 46.

[236]   However, I do not ignore that the Trust (or perhaps, more accurately, the Trust’s insurer) argues that, because the insurer is obliged to account for GST on payments received when it exercises rights acquired by subrogation under a contract of insurance, there should be a commensurate application of GST to the entirety of the judgment sum, including interest.

[237]   I do not accept that reasoning.   First, as I have found above, there is no requirement for GST to be added to the compensatory damages awarded in favour of the Trust.   Second, the payment that will be made to IAG, the Trust’s insurer, is received in a different context.  IAG is in the business of providing insurance cover. It  receives  insurance  premiums  and  it  pays  out  on  claims.    Sometimes  it  also recovers money through its rights of subrogation.   The latter is deemed a taxable supply by virtue of s 5(13B) and it must account for GST on the amount received. Because the payment is not compensatory in the hands of the insurer, but simply an additional source of revenue from its business activity, there is no reason to marry up the GST position as between the Council and the Trust, and as between the Trust and its insurer.  Section 5(13B) operates independently to oblige the insurer to account for GST, and does not affect the position as to whether GST should be a component of the damages awarded as between the Council and the Trust.

Summary of quantum award

[238]   The calculation of the damages claim based on my findings above is as follows:

(a) notional cost in 2010 of reinstating stadium to

2000 specifications

$15,126,665.35

(b) less allowance for betterment

$750,000.00

(c) plus agreed loss of rental income

$85,826.00

(d) plus interest at 5 per cent per annum from

1 February 2013 to 20 August 2015

$2,035,764.31

(e) total of damages plus interest

$17,998,225.66

(f)  less  settlement  sum  received  from  second defendant

$1,000,000.00

(g) judgment sum    $16,998,225.66           

Indemnity as between the First and Second Defendant

[239]   The Council has a cross claim against Mr Major which he has not defended. While such a claim may be of little practical benefit to the Council given the size of the claim, it is understandable that the Council  seeks a finding of how liability should be apportioned between it and Mr Major.

[240]   The findings of the Department of Building and Housing investigation, and of the IPENZ investigation, are clear.  Mr Major had the primary responsibility to monitor construction of the remedial  work and  to provide written confirmation, through a PS4, that the work had been carried out in accordance with the plans and specifications and in compliance with the building code.  He did not undertake that monitoring negligently.  He simply did not undertake it at all.  Instead he relied on the steelwork fabricator’s word that the work was done correctly.  That was a serious abdication of his professional responsibilities, particularly when he knew the Council was relying on his PS4 to be satisfied that the work was code-compliant.   The provision of the PS4 was the primary reason the defective welding work was not identified and a CCC was issued.  Furthermore, not only did he provide a misleading PS4,  he  did  not  provide  the  other  information  the  Council  required  from  him pursuant to the conditions of the building consent  and that, too, was negligent. However, the Council’s failure to insist on provision of that information remained an operative cause of the failure as well.

[241]   I therefore apportion liability 90 per cent to Mr Major and 10 per cent to the

Council in terms of the cross claim between these two defendants.

Costs

[242]   Costs, as requested by the parties are reserved.  If costs cannot be agreed:

(a) the Trust is, within 20 working days of receipt of this judgment to file any memorandum on costs;

(b) the Council is to file any memorandum on costs within 30 working days of the date of this judgment;

(c) the Trust may file any memorandum in reply within 35 working days of the date of this judgment.

[243]   Costs  will  be determined  on  the papers  unless  I require  assistance  from counsel.

Solicitors:

Young Hunter, Christchurch
Heaney & Partners, Christchurch

Eagles Eagles & Redpath, Invercargill

McElroys, Auckland