JUDGMENT OF THE COURT
A The application to adduce new evidence is declined.
B The appeal is dismissed.
CThe appellants must pay the respondent costs for a standard appeal on a band A basis and usual disbursements.
____________________________________________________________________
REASONS OF THE COURT
(Given by Venning J)
Sonsram Trustee Ltd (Sonsram Trustee) and Arjun Sami appeal the decision of Associate Judge Christiansen in which he entered summary judgment for Harrison Grierson Consultants Ltd (Harrison Grierson) as defendant.[1]
Background
[1]Harrison Grierson Consultants Ltd v Sonsram Trustee Ltd [2016] NZHC 581 [HC judgment].
Between 2005 and 2008 Redhill Development (NZ) Ltd (Redhill) carried out a major subdivision development at Papakura. Harrison Grierson acted as engineering consultant to Redhill. Vinod Chand of Harrison Grierson was appointed as engineer to the construction contract between Redhill and HEB Contractors Ltd (HEB).
A Certificate of Practical Completion (CPC) was issued by Harrison Grierson on 8 May 2008. The CPC was issued to Redhill and HEB and certified that in accordance with the construction contract the works had been completed and qualified for the certificate on 28 March 2008; and that the obligations under the contract to remedy any omissions or defects commenced on that date and continued until 28 June 2008. In issuing the CPC Harrison Grierson were discharging their contractual obligation to certify for practical completion where execution of the contract works had reached the stage where the consultants were able to certify them as complete. It is unclear when Harrison Grierson issued a final completion certificate but both Redhill and HEB had by 3 July 2008 reached a position where the only issues between them related to liability for payment of the amounts finally owing under the contract.
Redhill failed to pay the balance of $2,191,816 claimed by HEB under the construction contract. HEB took adjudication proceedings under the Construction Contracts Act 2002 against Redhill, Sonsram Development Holdings Ltd (Sonsram Development) and Mr Sami. The adjudicator found that Redhill had failed to provide a valid payment schedule in response to HEB’s payment claim issued on 23 May 2008. In doing so the adjudicator rejected Mr Chand’s evidence that the period for responding to the payment claim had been extended by agreement. On 8 June 2009 the adjudicator made an award holding Redhill liable for $2,039,307 together with costs of $45,000. He held Sonsram Development and Mr Sami jointly and severally liable with Redhill as owners of the site works on the basis Redhill was an “associate” of theirs on the basis of their relationship.[2] Sonsram Development and Mr Sami were related to Redhill. Sonsram Development was the sole shareholder of Redhill. Sonsram…
Keep reading for free
Create a free CaseChat account to read Sonsram Trustee Limited v Harrison Grierson Consultants Limi... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] NZCA 264
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi