IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY

CIV-2013-404-2416 [2014] NZHC 1934

BETWEEN

SAMSON CORPORATION LIMITED

Plaintiff

AND

MACRENNIE COMMERCIAL CONSTRUCTION LIMITED Defendant

AND

JAWA STRUCTURES LIMITED First Third Party

AND

VERTRANS ASSOCIATES (NZ) LIMITED

Second Third Party

AND

SHANDONG TADA AUTO-PARKING COMPANY LIMITED

Third Third Party

AND

SUSAN NANETTE HERBERT AND HG INDEPENDENT TRUSTEES LIMITED Fourth Third Party

OnThePapers: 14 August 2014

Judgment:

15 August 2014

JUDGMENT (NO. 2) OF ASSOCIATE JUDGE SMITH - COSTS

[1]      In a reserved decision delivered on 30 May 2014, I upheld the fourth third parties’ (the Herbert Trustees’) application for summary judgment  on the claims made  against  them  by  the  defendant  (Macrennie).     I  invited  counsel  to  file memoranda if costs could not be agreed.

[2]      The parties could not agree on costs, and memoranda have now been filed.  I

now give judgment on the Herbert Trustees’ costs application.

SAMSON CORPORATION LIMITED v MACRENNIE COMMERCIAL CONSTRUCTION LIMITED [2014] NZHC 1934 [15 August 2014]

The costs regime in the High Court Rules

[3]      Rule  14.1  of  the  High  Court  Rules,  confers  on  the  Court  an  overriding discretion as to the appropriate costs order.  Subject to that discretion, r 14.2 sets out a number of general principles to be applied in the determination of costs.   The following principles are relevant to the court’s consideration of costs in this case:

(i)The party who fails in the proceeding should pay the costs of the party who succeeds.1

(ii)The   award   of   costs   should   reflect   the   complexity  and significance of the proceeding.2

(iii)Costs should be assessed by applying the appropriate daily recovery rate to the time considered reasonable for each step reasonably required in the relation to the proceeding.3

(iv)What is a reasonable time for a particular step in a proceeding should not depend on the skill or experience of the solicitor or counsel involved or on the time actually spent by the solicitor or counsel involved or on the costs actually incurred by the

party claiming costs.4

[4]      Appropriate daily recovery rates are set out in Schedule 2 to the High Court Rules.    The  recovery  rates  are  divided  into  three  categories,  which  reflect  the differing levels of complexity or significance a case or a step in a case, may have.  A higher level or complexity or significance may place a case in category 3, in which case the successful party is likely to recover costs based on the higher category 3 daily recovery rate.   A very simple case may be treated for costs purposes as a category 1 case, in which the lower daily recovery rate set out in Schedule 2 will

apply.  Most cases are in the middle category, category 2.

1      High Court Rules, r 14.2(a).

2      High Court Rules, r 14.2(b).

3      High Court Rules, r 14.2(c).

4      High Court Rules, r 14.2(e).

[5]      That is the position in this case.  At a case management conference on 23

October  2013, Associate  Judge  Doogue  directed  that  the  proceeding  should  be treated as “category 2 for costs…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Samson Corporation Limited v Macrennie Commercial Constructi... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2014] NZHC 1934
Decision Date

CaseChat Overview and Summary

Samson Corporation Limited sought damages from Macrennie Commercial Construction Limited for alleged breaches of contract. The matter proceeded to a summary judgment application by the fourth third party, Susan Nanette Herbert and HG Independent Trustees Limited (the Herbert Trustees). The court reserved its decision on the summary judgment application, and later upheld the application on the claims made against the Herbert Trustees by Macrennie. The court now considers the Herbert Trustees' application for costs. The primary issue is whether the Herbert Trustees are entitled to costs on the basis of band C, as opposed to band B, for certain steps taken in the proceeding. A further issue is whether the Herbert Trustees are entitled to increased costs, on the basis that Macrennie unnecessarily contributed to the time or expense of the proceeding by taking or pursuing a step or an argument that lacked merit.

The court considers that there is no basis for an increased costs order. The Herbert Trustees did not succeed on all of their arguments for summary judgment, and the court was satisfied that Macrennie did not act unreasonably in opposing the estoppel claims. The court also considers that the Herbert Trustees are entitled to costs for certain steps taken in the proceeding, even though those steps were not specifically provided for in Schedule 3 to the High Court Rules. The court rejects Macrennie's submissions that the Herbert Trustees should not be awarded costs for filing an amended statement of defence and counterclaim, and for providing discovery and inspecting documents. The court finds that a band B time allocation is appropriate for all of the steps taken by the Herbert Trustees in the proceeding. There was no basis for Macrennie to argue that a normal amount of time was insufficient for the steps in question. The court accepts that some of the steps, including the filing of the summary judgment application and preparation for the hearing, were time-consuming, but not to the extent that a band C time allocation was justified.

The court awards the Herbert Trustees costs against Macrennie in the total sum of $25,870, made up as follows: $3,980 for the statement of defence, $3,184 for preparation for the case management conference, $796 for filing a memorandum for the case management conference, $796 for filing a memorandum for the second case management conference, $597 for appearance at the case management conference, $4,975 for preparing a list of documents on discovery, $2,985 for inspecting documents, $1,194 for filing the interlocutory application for summary judgment, $2,985 for preparation of written submissions, $1,194 for preparation of the bundle of documents for the hearing, $1,990 for appearance at the hearing, and $398 for sealing the judgment. The court also awards the Herbert Trustees disbursements in the sum of $3,076.56. The total amount of costs and disbursements awarded to the Herbert Trustees is $28,946.56.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established