IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
CIV-2023-404-001076
[2024] NZHC 272
UNDER THE Judicial Review Procedure Act 2016 IN THE MATTER OF
An Application for Judicial Review
BETWEEN
SAM PEMBERTON CIVIL LIMITED
Applicant
AND
STUART ROBERTSON
First Respondent
GRAEME CHRISTIE
Second RespondentAND
LANDSDALE DEVELOPMENT LIMITED
Third Respondent
Hearing: 15 February 2024 Appearances:
T J Rainey, V Whitfield for the Applicant
J D McBride, N Gillies for the Respondents
Judgment:
23 February 2024
JUDGMENT OF WHATA J
This judgment was delivered by me on 23 February 2024 at 10.00am,
pursuant to Rule 11.5 of the High Court Rules.
Registrar/Deputy Registrar Date: ………………………….
SAM PEMBERTON CIVIL LIMITED v ROBERTSON [2024] NZHC 272 [23 February 2024]
Introduction
[1] Sam Pemberton Civil Limited (SPC) seeks to judicially review two adjudications in respect of a construction contract carried out under the auspices of the Construction Contracts Act 2002 (CCA). SPC was the contractor. Landsdale Development Limited (Landsdale) was the principal. The project was completed on 22 December 2016. In October 2022, SPC commenced an adjudication seeking to review the Engineer’s decision on the sum owing to SPC. Landsdale sought to enlarge this adjudication to include a claim to liquidated damages (LDs), but as SPC refused to consent to this, the adjudicator declined to do so. However, as part of his decision rejecting SPC’s claim, the adjudicator found that Landsdale was entitled to set off in the form of LDs in the sum of $1.09m. Landsdale then commenced, in March 2023, a second adjudication to recoup the LDs. The second adjudicator essentially adopted the findings of the first adjudicator and upheld Landsdale’s claim to LDs. Substantial costs awards were also made against SPC by both adjudicators.
[2] Multiple matters were raised in the pleadings, but the scope of the present review was helpfully narrowed in oral argument to two key issues:
(a)Whether Landsdale’s claim to LDs was time barred as it commenced its claim in March 2023, more than six years after the date of completion of the project.
(b)Whether the adjudicators failed to apply the correct threshold for costs in claims under the CCA.
Background
[3] The immediate background to the claim is helpfully set in the first adjudication determination of Mr Stuart Robertson, which is not disputed, namely as follows:1
Procurement
1 Sam Pemberton Civil Limited v Landsdale Development Limited BDT22-102480, 17 February 2023 (First Adjudicator’s Determination).
9The Project was arranged in 4 stages and for contracting purposes split into two phases. Phase 1 was the earthworks to all Stages 1 to 4, and the civil works to Stage 1 only. Phase 2 was for the balance of the civil works, being to Stages 2 to 4.
10In spring 2014 Landsdale sought tenders from various entities to undertake the Phase 1 earthworks and civil works for the Project. Landsdale highlighted the importance of completing in a timely manner, either within one earthworks season of an alternative proposal from tenderers. SPC submitted its…
Keep reading for free
Create a free CaseChat account to read Sam Pemberton Civil Limited v Robertson and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] NZHC 272
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.