Sam Pemberton Civil Limited v Robertson

Link copied
Case Copied 39 min read

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY

I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE

CIV-2023-404-001076

[2024] NZHC 272

UNDER THE Judicial Review Procedure Act 2016

IN THE MATTER OF

An Application for Judicial Review

BETWEEN

SAM PEMBERTON CIVIL LIMITED

Applicant

AND

STUART ROBERTSON

First Respondent

GRAEME CHRISTIE
Second Respondent

AND

LANDSDALE DEVELOPMENT LIMITED

Third Respondent

Hearing: 15 February 2024

Appearances:

T J Rainey, V Whitfield for the Applicant

J D McBride, N Gillies for the Respondents

Judgment:

23 February 2024


JUDGMENT OF WHATA J


This judgment was delivered by me on 23 February 2024 at 10.00am,

pursuant to Rule 11.5 of the High Court Rules.

Registrar/Deputy Registrar Date: ………………………….

SAM PEMBERTON CIVIL LIMITED v ROBERTSON [2024] NZHC 272 [23 February 2024]

Introduction

[1]                  Sam Pemberton Civil Limited (SPC) seeks to judicially review two adjudications in respect of a construction contract carried out under the auspices of the Construction Contracts Act 2002 (CCA). SPC was the contractor. Landsdale Development Limited (Landsdale) was the principal. The project was completed on 22 December 2016. In October 2022, SPC commenced an adjudication seeking to review the Engineer’s decision on the sum owing to SPC. Landsdale sought to enlarge this adjudication to include a claim to liquidated damages (LDs), but as SPC refused to consent to this, the adjudicator declined to do so. However, as part of his decision rejecting SPC’s claim, the adjudicator found that Landsdale was entitled to set off in the form of LDs in the sum of $1.09m. Landsdale then commenced, in March 2023, a second adjudication to recoup the LDs. The second adjudicator essentially adopted the findings of the first adjudicator and upheld Landsdale’s claim to LDs. Substantial costs awards were also made against SPC by both adjudicators.

[2]                  Multiple matters were raised in the pleadings, but the scope of the present review was helpfully narrowed in oral argument to two key issues:

(a)Whether Landsdale’s claim to LDs was time barred as it commenced its claim in March 2023, more than six years after the date of completion of the project.

(b)Whether the adjudicators failed to apply the correct threshold for costs in claims under the CCA.

Background

[3]                  The immediate background to the claim is helpfully set in the first adjudication determination of Mr Stuart Robertson, which is not disputed, namely as follows:1

Procurement


1      Sam Pemberton Civil Limited v Landsdale Development Limited BDT22-102480, 17 February 2023 (First Adjudicator’s Determination).

9The Project was arranged in 4 stages and for contracting purposes split into two phases. Phase 1 was the earthworks to all Stages 1 to 4, and the civil works to Stage 1 only. Phase 2 was for the balance of the civil works, being to Stages 2 to 4.

10In spring 2014 Landsdale sought tenders from various entities to undertake the Phase 1 earthworks and civil works for the Project. Landsdale highlighted the importance of completing in a timely manner, either within one earthworks season of an alternative proposal from tenderers. SPC submitted its…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Sam Pemberton Civil Limited v Robertson and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2024] NZHC 272
Decision Date

CaseChat Overview and Summary

Sam Pemberton Civil Limited (SPC) sought judicial review of two adjudication determinations concerning a construction contract with Landsdale Development Limited (Landsdale) for work completed in 2016. The primary issues were whether Landsdale’s claim for liquidated damages (LDs) was time-barred and if the adjudicators correctly applied the cost threshold for claims under the Construction Contracts Act 2002 (CCA). SPC argued that Landsdale’s claim for LDs was time-barred as it was initiated over six years after the project’s completion date. The court found that the adjudicators were correct in determining that the “act or omission” for the limitation period began with the adjudicator's determination, not the date of completion. This approach aligned with the contract provisions and provided the necessary certainty, as the exact “Due Date” and extent of LDs could only be determined after the adjudication processes were completed. Regarding the costs, SPC challenged the adjudicators' decisions to award costs based on their claims being without substantial merit. However, the court found that the adjudicators provided detailed and legally sound reasons for their cost awards, and SPC had not demonstrated any legal error in these determinations. Consequently, the court declined the application for judicial review on both grounds, finding that the limitation and cost issues were more appropriately resolved in the pending arbitration.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.