Ridgecrest NZ Limited v IAG New Zealand Limited

Link copied
Case Copied 36 min read

IN THE HIGH COURT OF NEW ZEALAND CHRISTCHURCH REGISTRY

CIV-2012-409-000295 [2012] NZHC 2954

BETWEEN  RIDGECREST NZ LIMITED Plaintiff

ANDIAG NEW ZEALAND LIMITED Defendant

Hearing:         26 September 2012 (Heard at Wellington)

Counsel:         C R Carruthers QC and P A Cowey for plaintiff

B D Gray QC and P M Smith for defendant

Judgment:      8 November 2012

RESERVED JUDGMENT OF DOBSON J

Contents

Background, and the preliminary question ..................................................................................... [1] The policy ............................................................................................................................................ [6] Competing contractual interpretations .......................................................................................... [16] Interpreting the terms of the contract ............................................................................................ [25] Merger............................................................................................................................................... [37] Frustration ........................................................................................................................................ [54] Conclusion......................................................................................................................................... [77]

Background, and the preliminary question

[1]      These  proceedings  involve  a  dispute  between  an  insurer  and  insured  in relation to the extent of the insurer’s liability for damage to a commercial building in Gloucester Street, central Christchurch.  The building was damaged on a number of

occasions by some of the more severe of the earthquakes suffered by Christchurch in

RIDGECREST NZ LIMITED v IAG NEW ZEALAND LIMITED HC CHCH CIV-2012-409-000295 [8

November 2012]

the relevant period.   Eventually, the building suffered irreparable damage and has subsequently been demolished.

[2]      In those circumstances, the defendant (the insurer) has paid the plaintiff (the insured) the amount that represents the limit on liability under the policy for any one happening of $1.984 million.  The insurer had earlier incurred some $125,000 as the partial cost of repairs needed on account of damage caused in earlier earthquakes. The insurer treats these payments as fully discharging its liabilities under the policy.

[3]      In contrast, the insured claims that it is entitled to additional sums comprising the estimated costs of all repairs that would have been necessary to restore the building to its pre-earthquake condition, after each of the earlier earthquakes.  The extent of such repairs had been assessed by quantity surveyors on each occasion.

[4]      For  the  purposes  of  determining  the  preliminary  question  to  which  this judgment relates, the parties agreed on a statement of facts which included the

following:

At material times, there was a policy of insurance between the parties whereby the insurer provided replacement cover for the insured’s commercial  building  situated  at  215  Gloucester  Street  for  events including  earthquake  damage,  with  a  limit  of  $1.984m  for  each

happening.

The building sustained damage in an earthquake on 4 September 2010.

The cost  of repairing that  damage was  assessed  and  estimated  to  be between $110,115.09 (inclusive of GST) and $196,352 (plus GST).  Such repairs had been commenced but were not completed by the time the

second relevant earthquake occurred.

In  a  second  relevant  earthquake  on  26 December  2010,  the  building suffered  further,  distinct  damage.   The  cost  of  repairing the  building following  that  earthquake  was  assessed  and  estimated  to  be  between

$200,000 (inclusive of GST) and $337,056 (plus GST).  Such repairs had

been commenced but had not been completed by the time of the third

relevant earthquake.

The  building  sustained  further  distinct  damage  as  a  result  of  a  third earthquake on 22 February 2011.  The insured contended that the cost to repair  the  damage  caused  by…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Ridgecrest NZ Limited v IAG New Zealand Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2012] NZHC 2954
Decision Date

CaseChat Overview and Summary

Ridgecrest NZ Limited (the plaintiff) sued IAG New Zealand Limited (the defendant) in relation to the extent of the defendant’s liability for damage to the plaintiff’s commercial building in Gloucester Street, central Christchurch. The building was damaged by several earthquakes during the relevant insurance period. The plaintiff claimed additional sums for the estimated costs of repairs that would have been necessary to restore the building to its pre-earthquake condition, after each of the earlier earthquakes. The defendant paid the plaintiff the amount that represents the limit on liability under the policy for any one happening, and considered its liabilities fully discharged. The court was required to determine whether the insured was entitled to be paid for the damage resulting from each happening up to the limit of the sum insured in each case. The court held that the contractual terms would entitle the insured to be paid the further amounts claimed. The doctrine of merger should not apply generally to material damage contracts of insurance. However, in the circumstances of this contract and its part performance, the obligation of the insurer to meet the full extent of liability provided for in the contract had been frustrated. The preliminary question was answered “no”.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established