Rangitahi Limited v Pemberton Civil (Hamilton) Limited

Link copied
Case Copied 18 min read

IN THE HIGH COURT OF NEW ZEALAND HAMILTON REGISTRY

I TE KŌTI MATUA O AOTEAROA KIRIKIRIROA ROHE

CIV-2021-419-000177

[2021] NZHC 3471

BETWEEN

RANGITAHI LIMITED

Applicant

AND

PEMBERTON CIVIL (HAMILTON) LIMITED

Respondent

Hearing: 27 October 2021

Appearances:

J A MacGillivray for Applicant V A Whitfield for Respondent

Judgment:

16 December 2021


JUDGMENT OF ASSOCIATE JUDGE P J ANDREW


This judgment was delivered by Associate Judge Andrew on 16 December 2021 at 3.00 pm

pursuant to r 11.5 of the High Court Rules Registrar / Deputy Registrar

Date ………………………..

RANGITAHI LTD v PEMBERTON CIVIL (HAMILTON) LTD [2021] NZHC 3471 [15 December 2021]

Introduction

[1]Rangitahi Ltd1 applies to set aside a statutory demand issued by the respondent,

Pemberton Civil (Hamilton) Ltd,2 in the sum of $973,079.47.3

[2]                 The statutory demand was based on a progress payment claim (number 41) under a construction contract. That construction contract is subject to the Construction Contracts Act 2002.4 The progress payment claim was issued after the engineer had issued the final completion certificate.5 Rangitahi did not issue a progress payment schedule in response to the progress payment claim. On that basis, Pemberton’s position is that Rangitahi cannot deny the debt is due and owing. Pemberton relies on ss 22 and 23 of the CCA and the statutory philosophy of “pay now, argue later”.6

[3]                 The issue before me is whether Pemberton issued a valid progress payment claim; specifically, whether it is reasonably arguable that the issuing of the FCC meant that Pemberton could only make one final “wash-up” payment claim encompassing all of its outstanding claims.

Factual background

[4]                 Rangitahi is undertaking the development of a subdivision in Raglan comprising over 550 sections. In 2018, the parties entered into a written construction contract to complete the construction of earthworks and civil works necessary to deliver sections in “precinct A” of the subdivision. The construction contract is a NZS3910:2013 contract.7 It provided for retentions that were to be released in accordance with cl 12.3.2, below, and the special conditions of the contract.

[5]Clause 12.2 of the contract is entitled “Progress Payment Schedules”. Clause

12.2.1 provides that the engineer shall provide a Progress Payment Schedule in


1      Rangitahi.

2      Pemberton.

3      Companies Act 1993, s 290.

4      CCA.

5      FCC.

6      Gill Construction Ltd v Butler [2010] 2 NZLR 229 at [9].

7      For ease, I refer to this as the Precinct A contract.

response to each payment claim not later than 12 working days after the date of service of the payment claim.

[6]Clause 12.3.2 provides for “Retention monies”:

The monies retained, less any deductions which the Principal is entitled to make, shall be paid to the Contractor as follows:

(a)By payment, as part of the first progress payment after the issue of the Practical Completion Certificate for the whole of the Contract Works or for the Separable Portion, of any amount in excess of the defects liability retention specified in the Special Conditions;

(b)By payment, as part of the first and any subsequent progress payment after the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Rangitahi Limited v Pemberton Civil (Hamilton) Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2021] NZHC 3471
Decision Date

CaseChat Overview and Summary

Rangitahi Limited applied to set aside a statutory demand issued by Pemberton Civil (Hamilton) Limited, claiming $973,079.47. The statutory demand was based on a progress payment claim under a construction contract, which is subject to the Construction Contracts Act 2002. The issue before the court was whether Pemberton had issued a valid progress payment claim, specifically if it was reasonably arguable that the issuing of the Final Completion Certificate meant that Pemberton could only make one final "wash-up" payment claim encompassing all of its outstanding claims. The court found that it was reasonably arguable that after the Final Completion Certificate was issued, Pemberton could only make one final "wash-up" claim encompassing all of its outstanding claims. It followed that the payment claim 41 was arguably invalid and Rangitahi's failure to issue a progress schedule in response cannot be relied upon by Pemberton to establish that the debt is due and owing. The court granted Rangitahi's application to set aside the statutory demand. As to costs, Rangitahi was entitled to costs on a 2B basis plus disbursements. If costs could not be agreed, then memoranda were to be filed by 28 January 2022.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established