Origin Energy Resources (Kupe) Limited v Tenex Alliance New Zealand Limited and Green HC Ak CIV 2010-404-00106

Case

[2010] NZHC 32

19 January 2010

No judgment structure available for this case.

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY

CIV 2010-404-00106

UNDER  the Judicature Amendment Act 1972

AND UNDER                 the Declaratory Judgments Act 1908

BETWEEN  ORIGIN ENERGY RESOURCES (KUPE) LIMITED

Plaintiff

ANDTENIX ALLIANCE NEW ZEALAND LIMITED

First Defendant

ANDJOHN GREEN Second Defendant

Hearing:         19 January 2010

Counsel:         M D O'Brien and T M Horder for the plaintiff

B Keene QC and C J Booth for first defendant

Judgment:      19 January 2010

(ORAL) JUDGMENT OF POTTER J

Solicitors:            Bell Gully, P O Box 1291, Wellington 6140

Kensington Swan, Private Bag 92101, Auckland 1140

Copy to:             B Keene QC, P O Box  879, Auckland 1140

ORIGIN ENERGY RESOURCES (KUPE) LIMITED V TENIX ALLIANCE NEW ZEALAND LIMITED AND

ANOR HC AK CIV 2010-404-00106  19 January 2010

Introduction

[1]      By an interlocutory application  dated  18  January  2010  the  plaintiff  Origin

Energy Resources (Kupe) Limited (“Origin”) seeks an order from the Court:

Pending further order of   the   Court,   prohibiting   the   defendants   from proceeding with any adjudication under the Construction Contracts Act 2002

in respect of any disputes under or in connection with the first defendant’s subcontract with the plaintiff (as disclosed agents for the Kupe Joint Venture

Parties) and Technip Singapore Pte Limited and dated 4 March 2008.

[2]      The  application  is  opposed  by  the  first  defendant,  Tenix  Alliance  New Zealand Limited (“Tenix”) in a notice of opposition dated 19 January 2010 filed in Court today.

[3]      In  submissions  this  morning  Mr  O’Brien  for  Origin  raised  a  further  issue, namely that Origin claims a conflict of interest by Kensington Swan, solicitors for Tenix,  in  respect  of  which  Mr  O’Brien  advised  that  proceedings  will  be  filed forthwith. Mr  Keene  QC,  representing  Tenix,  had  no  details  of  that  proposed proceeding.   It is an issue I cannot advance today.   Mr O’Brien, in fairness to him, raised  the  issue  simply  to  explain  to  the  Court  this  additional  complexity  in  the background to the application.

The issue

[4]      As  I  have  discussed  with  counsel  this  morning,  the  issue  for  the  Court  is whether to grant the order sought on an interim and short term basis to enable the jurisdictional dispute that gives rise to the application to be heard and determined in this Court at some date in February 2010, or whether the Court should decline the application so the processes under the Construction Contracts Act 2002 (“the Act”) which have already been commenced and are in train, can proceed to determination by the adjudicator who has been appointed and is the second defendant named in the interlocutory application.

Background

[5]      I  shall  briefly summarise  the  background  that  gives  rise  to  the  matter  now before the Court.

[6]      The dispute between the parties arises in relation to the Kupe Gas Project for development of the Kupe field located offshore from Taranaki.

[7]      Origin operates a Petroleum Mining Licence 38146 issued by the Crown in respect of the Kupe field and is the agent for the eight joint venture parties (including Origin) involved in the Kupe Gas Project.

[8]      Origin as agent for the Kupe joint venture parties has entered into a Project

Alliance Agreement dated 7 September 2008 (“the Alliance Agreement”) with:

a)        Technip Singapore Limited of Singapore as contractor;

b)        Technip Geoproduction of Malaysia as guarantor; and

c)        Technip Oceania Pty Ltd of Australia as nominated subcontractor.

[9]      The     Alliance    Agreement    relates    to    the    design,    engineering     and commissioning of the facilities to produce the Kupe field.

[10]     Origin, Technip Singapore and Tenix  are  parties  to  a  subcontract  dated  4

March   2008   (“the   subcontract”)   pursuant   to   which   Tenix   agreed   to   install mechanical piping for gas and related products for the Kupe Gas Project.

[11]     Disputes have arisen between the parties under the subcontract.

[12]     The statement of claim alleges that Tenix purported to submit on or about 28

October and 3 December 2009 the last two Monthly Financial Status Reports (“MFSR’s”) respectively claiming payment of some  $33m  and $61m.  Validity of those MFSR’s and the underlying sums claimed are disputed by the Alliance (Origin and  Technip  Singapore). It is alleged in the statement of claim that  amounts  in

excess of period payment claims which total roughly $4m, cannot properly form part

of  a  payment  claim  under  the  Act  and  are  not  in  the  nature  of  a  progress  claim contemplated by the Act.  Nevertheless Mr O’Brien accepted in submissions that this is an adjudication issue.

[13]     Article 7.2 of the Particular Terms and Conditions of the subcontract sets out the process for resolving disputes, differences or questions.   Article 7.2(b) provides

for a 60 day process for the attempted resolution of disputes.  Article 7.2(c) provides

for any dispute not resolved by that process to be settled by an arbitration under the Arbitration Act 1996 and the Rules of Arbitration of the  International  Chamber of Commerce.

[14]     Section 25(1) of the Act provides that any party to a construction contract has the right to refer a dispute to adjudication, which is the process invoked by Tenix in this case.   Sections 25(3) and (4) of the Act provide an exception to the right of a party to a construction contract to refer disputes to adjudication without the consent of the other party, if the parties have agreed to refer disputes to arbitration and the arbitration is an international arbitration as defined in article 1(3) of Schedule 1 of the Arbitration Act 1996.

[15]     Origin contends that the dispute in this case is governed in accordance with the  agreement  between  the  parties  in  the  subcontract,  by the  Arbitration  Act  1996 because this is an international arbitration as defined in Schedule 1 of the Arbitration Act 1996.  Accordingly in the two causes of action pleaded in the statement of claim, Origin  alleges  illegality  and  error  of  law  in  Tenix  initiating  and  the  adjudicator entering into and exercising, adjudication jurisdiction under the Act.

[16]     It is unnecessary for me to detail the precise bases upon which the allegations are  made.           However,  they  include  an  allegation  that  there  is  no  “construction contract”  between Origin and Tenix  as Origin is acting only as  agent  for the joint venture parties to whom the notices of adjudication are not addressed and who have not been served.

Submissions

[17]     Mr O’Brien in oral submission, submitted that the adjudication process that has been invoked and has led to the appointment of an adjudicator, Mr Green, the second defendant, provides pressure which is unhelpful to the proper determination

of the present issues before the Court.  He notes there is no express power under the Act  for  the  adjudicator  to  determine  his  jurisdiction,  which  is  in  contrast  to  the position of an arbitrator under the Arbitration Act who is vested expressly with that power.  He submitted that it is a waste of time and cost for this matter to proceed via the adjudicator; the adjudicator will have to interpret the construction contract; that will  raise  the  question:  Is  there  an  arbitration  agreement?;  the  answer,  he  said,  is clearly yes, and the issue becomes one of interpretation of the relevant provisions of the Arbitration Act.

[18]     He referred to the judgment in Patel v Pearson Group Limited HC WN CIV

2008-485-2571, as did Mr Keene, a judgment to which I shall refer further shortly.

[19]     Mr  O’Brien  submitted  that  the  issue  of  jurisdiction  is  expressly  within  the ambit  of  the  Judicature  Amendment  Act  1972  under  which  the  application  for interim relief is brought, and that such an application can be made at any time.   He submitted it is logical that this issue comes first to the High Court for determination rather than being left in the first instance for adjudication by the adjudicator whose determination  could  only  be  provisional.   He  submitted  that  Origin  should  not  be subjected to that process which is not suited to the nature of this dispute, and that ultimately determination by the High Court of the jurisdictional issue will save both parties time and cost.

[20]     Mr Keene submitted that the order sought by Origin will interfere with the adjudication process expressly provided by the Act. He submitted that Origin, following the adjudicator’s determination on jurisdiction, can exercise its  rights  in respect of that determination, including  the  right  to  judicially  review  it. He submitted that the two matters raised by Origin, namely the jurisdiction issue and the conflict of interest issue are likely to significantly delay progress, and are unlikely to be resolved by a February hearing. Thus, the aim of the Act, which is a swift and

inexpensive process leading to prompt determination, will be denied Tenix and the purpose of the Act will be frustrated.  He submitted that the adjudicator should first address the jurisdictional issues, leaving Origin with appropriate rights to review if it is dissatisfied with the adjudicator’s determination.

Discussion

[21]     Both parties, as I have said, referred to the judgment of Miller J in Patel v Pearson.      That  case  concerned  whether  there  was  a  construction  contract  made between the parties claimed.  At [37] Miller J addressed the issue: can an adjudicator determine his or her jurisdiction?  He noted at [38] that the legislation (the Act), does not   prove   explicitly   that   the   adjudicator   may   determine   jurisdiction,   which distinguishes  it  from  the  Arbitration  Act 1996  which,  under  article  16  of  the  First Schedule,   provides   that   authority. He   noted   the   Act   contemplates   that   the adjudicator  will  interpret  the  construction  contract  and  deal  with  ancillary matters. At [42] he referred to a number of English decisions.

[22]     Mr  O’Brien  referred  specifically  to  this  paragraph  and  also  to  the  extract from Keating on Construction Contracts 8th ed (Sweet & Maxwell, London, 2006) to which Miller J referred at [42]. Keating states at 17-019:

As a matter of practice where the adjudicator’s jurisdiction is contested it is submitted that the appropriate approach is for the adjudicator to enquire into his  jurisdiction  and  if  he  is  satisfied  that  he  has  jurisdiction  he  should continue the adjudication unless and until the court orders otherwise.

Deviating slightly from consideration of the judgment in Patel v Pearson, I note that Mr O’Brien’s emphasis was on the words “unless and until”.  He submitted that it is appropriate  for the High  Court to intervene at any stage of the process which will arrest  the  process  to  adjudication  under  the  Act  if  the  determination  of  the  High Court is that the adjudicator lacks jurisdiction.

[23]     At [44] Miller J noted that the approach to jurisdiction taken by the English Courts is consistent with the decisions in Stellar Projects Limited  v  Nick  Gaja Pluming Limited HC AK CIV 2005-404-6984 10 April 2006 and LSB Limited v Loader  DC  HAM  CIV  2008-019-1041 26 September  2008. He said it  recognises

that  an  adjudicator’s  powers  under  the  legislation  depend  on  the  existence  of  a construction  contract  and  a  dispute  under  that  contract  that  has  been  referred  to adjudication.    If  those  prerequisites  have  not  been  met,  there  can  be  no  lawful adjudication.  That is recognised in ss 73 and 74 of the Act.

[24]     At [45] he said:

...  the  legislature  contemplated  that  adjudicators  will  determine  matters going to jurisdiction, and that the District Court will become involved only after the adjudication has been completed.  The entire point of the legislation

is prompt and inexpensive dispute resolution.

For those reasons, he said:

I  accept  that  an  adjudication  and  resulting  determination  are  provisionally binding until this Court on judicial review, or the District Court under s 74, determines otherwise.

[25]     While I accept Mr O’Brien’s submission that there is no reason why the High

Court should not intervene at any stage of the process on an application to determine

an issue of jurisdiction under a contract which is subject to the Act, the Act provides

a  process  for  adjudication  and  does,  inferentially,  accept  that  the  adjudication  will determine issues of jurisdiction in the first instance.

[26]     In this case the matter has been progressed to the point where an adjudicator has been appointed, the parties being unable to agree upon one, and Mr Green has indicated  that  he  will  determine  the  issue  of  jurisdiction.   He  has  made  timetable orders  to  place  the  matter  before  him  for  adjudication  within  the  tight  timeframe contemplated by the Act.

[27]     I   consider   the   appropriate   procedure   is   for   the   matter   to   proceed   to adjudication   before   the   appointed   adjudicator,   for   the   parties   to   make   their submissions to the adjudicator and for him to determine the issue of jurisdiction as he thinks fit.   Depending on the outcome of that determination the matter may well come  back  to  the  High  Court  on  an  application  for  judicial  review  by  Origin  or possibly by Tenix.  The High Court will then be asked to review the determination of the adjudicator and will have the benefit of his adjudication and the reasons for it.

[28]     I  accept  that  in  the  long  run  this  process  may prove  more  time  consuming than the one Origin seeks to implement by means of the order it has sought from the Court  in  its  interlocutory  application,  but  I  consider  it  is  the  appropriate  process given the purpose and intent of the Act.

Result

[29]     Accordingly the application by Origin is declined.

[30]     Having  reached  that  decision,  I  commend  to  the  parties  a  co-operative response to agreeing amendments to the timetable orders made by the adjudicator to ensure that both parties have reasonable opportunity to place their submissions and the factual aspects of this matter, which are important, fully and properly before the adjudicator.  Otherwise his determination will not have the value I consider it should.

[31]     Costs are reserved.  Costs should follow the event.  If the parties cannot agree costs, memoranda may be filed for my consideration and determination.

Actions
Download as PDF Download as Word Document


Cases Citing This Decision

0

Cases Cited

0

Statutory Material Cited

0