IN THE HIGH COURT OF NEW ZEALAND CHRISTCHURCH REGISTRY
I TE KŌTI MATUA O AOTEAROA ŌTAUTAHI ROHE
CIV-2015-409-000111
[2018] NZHC 2005
BETWEEN NICON LIMITED
Plaintiff
AND
TOWER INSURANCE LIMITED
First Defendant
STREAM GROUP NZ PTY LIMITED
Second Defendant
Hearing: 16-19 April 2018
Further written submissions:
Plaintiff – 8 May 2018
First and Second Defendants – 21 May 2018Appearances:
P B McMenamin for Plaintiff
J P Forsey and S E Henderson for First and Second Defendants
Judgment:
8 August 2018
JUDGMENT OF GENDALL J
NICON LTD v TOWER INSURANCE LTD [2018] NZHC 2005 [8 August 2018]
INTRODUCTION [1]
BACKGROUND FACTS [6]
Nicon’s first association with Stream[11]
The Heads of Agreement (HOA) [14]
Charges for assessments [22]
Stream/Tower stop giving work to Nicon[28] NICON’S OVERALL CLAIMS [31]
THE PRELIMINARY QUESTION PROCESS [36]
THE FOUR PRELIMINARY QUESTIONS [41]
(A) Is the HOA binding? [42]
The authorities [44]
Intention to be bound? [54]
Uncertainty? [59]
Conclusion on Question (A) [62]
(B) Was Tower/Stream obliged to offer Nicon all the relevant demolition work?[64]
The authorities [65]
Demolition work? [70]
“Offer the opportunity to undertake the demolition work…as a preferred
contractor”? [71]
Stream/Tower’s ability to engage other contractors? [75]
Extrinsic evidence [79]
Conclusion on Question (B) [81]
(C) Was Stonewood an agent of Tower and Stream? [85]
Discussion [86]
Conclusion on Question (C) [88]
(D) Is Nicon entitled to fees for its quotes after 21 July 2011? [90]
Discussion [91]
Conclusion on Question (D) [99]
RESULT [102]
COSTS [103]
INTRODUCTION
[1] This proceeding has sprung out of events which followed the Canterbury earthquake sequence in 2010 and 2011. The plaintiff (Nicon) is a demolition contractor. Nicon arranged with the first defendant (Tower) to provide demolition quotes both for Tower’s reserving purposes and to inform claims, and then to carry out some demolition and site clearance work relating to earthquake damaged properties in Christchurch. At the time, the second defendant (Stream) provided Tower with cost estimates for damage and acted as its project manager on damaged properties for which Tower carried insurance. Tower then carried out insurer-managed repairs or rebuilds on insured properties and organised demolition and site clearance as required.
[2] The present proceeding is before the Court for determination of certain preliminary issues which underlie Nicon’s claim against Tower and Stream. That claim is based essentially on two contracts alleged to have been formed between the parties.
[3] Tower and Stream deny the existence of these contracts and, in the alternative, contend that if they do arise they do not have the effect and meaning which Nicon alleges.
[4] These proceedings were issued some time ago, having been commenced by Nicon’s first statement of claim filed on 4 March 2015. Following a 20 June 2017 minute issued by Fogarty J in this Court, on 9 August 2017 the parties requested the Court to hear issues which comprise the fundamental aspects of this dispute as preliminary questions.
[5]Those agreed preliminary questions are:
(a)Whether or not a Heads of Agreement signed on 28 February…
Keep reading for free
Create a free CaseChat account to read Nicon Limited v Tower Insurance Limited and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2018] NZHC 2005
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.