NDM Construction Limited v North Ridge Living no.3 Limited

Link copied
Case Copied 22 min read

IN THE HIGH COURT OF NEW ZEALAND CHRISTCHURCH REGISTRY

I TE KŌTI MATUA O AOTEAROA ŌTAUTAHI ROHE

CIV-2021-409-000530

[2022] NZHC 320

BETWEEN

NDM CONSTRUCTION LIMITED

Applicant

AND

NORTH RIDGE LIVING NO. 3 LIMITED

Respondent

Hearing: 11 February 2022

Appearances:

R G Smedley and K L Vilsbaek for Applicant

M D W King and S R A Hayman for Respondent

Judgment:

1 March 2022


JUDGMENT OF ASSOCIATE JUDGE PAULSEN


This judgment was delivered by me on 1 March 2022 pursuant to Rule 11.5 of the High Court Rules

Registrar/Deputy Registrar Date:

NDM CONSTRUCTION LTD v NORTH RIDGE LIVING NO. 3 LTD [2022] NZHC 320 [1 March 2022]

The application

[1]                 The applicant, NDM Construction Ltd (NDM), applies for an order under s 143 of the Land Transfer Act 2007 that a caveat lodged by it against land owned and being developed by the respondent, North Ridge Living No. 3 Ltd (NRL), not lapse.

[2]                 NDM claims it has a present interest in the land as purchaser under 19 agreements for sale and purchase dated 18 November 2020 between it and NRL.

[3]                 NRL opposes the application and asserts the agreements for sale and purchase were validly cancelled by it following non-fulfilment of a condition that it obtain all necessary consents for the subdivision of the land. Alternatively, NRL argues the Court should exercise its discretion and remove the caveat because, under the agreements for sale and purchase, NDM agreed not to lodge a caveat.

Background

[4]                 NRL is a property development company focusing on small to medium-sized residential developments. In or around late 2020, NRL acquired land at 64A Bayswater Crescent, Christchurch for development into residential sections (the land).

[5]                 At the time of purchase, NRL was aware the development would be challenging because of a unique set of features that included:

(a)a lack of engineering records for fill on the site;

(b)contamination by asbestos;

(c)the property was bounded by a waterway;

(d)the property was within the Christchurch City Council flood plain; and

(e)there is an ephemeral stream on the property.

[6]                 NDM is a Golden Homes franchisee and in the business of selling house and land packages.

[7]                 On 18 November 2020, NDM entered into 19 agreements for sale and purchase with NRL on equivalent terms, pursuant to which it agreed to purchase 19 sections to be created from the subdivision of the land (the agreements). NDM says it has since entered into agreements to on-sell 18 of those sections, along with dwellings it is to build.

[8]                 The agreements recognised that a new title was to issue for each section as a result of a subdivision of the land to be completed by NRL. The agreements were conditional on NRL obtaining all necessary consents for the subdivision of the land within six months of the date of the agreements (i.e. by 18 May 2021).

  1. Clause 26.6 of the agreements relevantly provides:

This Agreement is conditional upon the Vendors obtaining all necessary consents for the subdivision on terms and conditions…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read NDM Construction Limited v North Ridge Living no.3 Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2022] NZHC 320
Decision Date

CaseChat Overview and Summary

NDM Construction Limited sought to sustain a caveat against land owned by North Ridge Living No. 3 Limited (NRL) to prevent its lapse. NDM claimed a present interest in the land as a purchaser under 19 agreements for sale and purchase dated 18 November 2020. NRL opposed the application and argued that the agreements were validly cancelled by it following non-fulfilment of a condition that it obtain all necessary consents for the subdivision of the land within six months of the date of the agreements (i.e. by 18 May 2021). Alternatively, NRL argued that the Court should exercise its discretion and remove the caveat because, under the agreements for sale and purchase, NDM agreed not to lodge a caveat.

The court considered two issues. The first was whether NDM put forward a reasonably arguable case that NRL failed to take all reasonable steps to obtain the subdivision resource consent by 18 May 2021 (in which case the purported cancellations were arguably ineffective). The second was whether the Court should refuse to sustain the caveat in any event when it was lodged in breach of the no caveat clause.

The court held that it was arguable that NRL did not satisfy its obligation to take all reasonable steps to obtain the resource consent by 18 May 2021 for the reasons that follow. NRL's obligation was to take all reasonable steps to obtain the subdivision resource consent "in the circumstances". An important circumstance was the unique nature of the property that created challenges both in its development, and in the preparation and processing of a subdivision resource consent application. Another important circumstance is the subdivision consent was to be obtained within six months. The evidence of Mr Graham would suggest that such a timeframe would be tight. That is the heft of Mr King’s submission that, regardless of any fault on the part of NRL, the resource consent could not have been obtained by 18 May 2021. In those circumstances, NRL can reasonably have been expected to apply for the necessary resource consent without unnecessary delay and the occurrence of such delay would not be reasonable in the circumstances. On the evidence, such delays appear to have occurred. After the agreements were signed on 18 November 2020, there does not appear to have been any significant steps taken to obtain the subdivision resource consent until the appointment of Graham Surveying in early February 2021, apart from the attendance by Hugh Shearer at the meeting with the Christchurch City Council on 17 December 2020. If that is correct, two and a half months of the six month period within which NRL was to obtain the subdivision resource consent were effectively lost. NRL does not provide any satisfactory explanation for the apparent lack of diligence in pursuing the consent during that period. The court held that this issue was one for exploration at a substantive trial once the parties had had an opportunity to complete discovery and give their evidence.

The court also held that the existence of a no caveat clause in an agreement between parties does not preclude the Court from sustaining a caveat in an appropriate case. The existence of a no caveat clause is a relevant consideration to be considered by the Court when considering whether to exercise its residual discretion to remove a caveat, notwithstanding that a reasonably arguable case has been shown for the claimed interest. However, the court held that in this case, the principal purpose of the no caveat clause was a practical one; to prevent NDM from taking steps that impeded the subdivision of the land. That was not the circumstance that had arisen here. The evidence was that NRL had put the development on hold. Further, NDM had lodged the caveat in response to what it considered is a repudiation by NRL of the agreement. On what was before the court, NDM had lodged the caveat as a means to protect its interest in the land which may be defeated should the caveat not be sustained. The court held that weighing all matters in the balance, its discretion should not be exercised to defeat NDM’s statutory right to lodge its caveat and it made an order sustaining it.

The court ordered that pending further order of the Court, the caveat lodged on 6 October 2021 under Instrument No 12261299.1 against Record of Title 291596 shall not lapse. The order was subject to the condition that NDM was, within 21 days of the date of this judgment, to issue proceedings to sustain the interest claimed in the caveat and was to pursue the proceeding diligently to hearing. The court reserved leave to NRL to apply to vary the order in the event that the condition was not complied with. The court also awarded costs to NDM on a 2B basis plus reasonable disbursements as fixed by the Registrar.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established