IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
CIV-2018-404-2815
[2019] NZHC 866
UNDER The Companies Act 1993, section 290 IN THE MATTER OF
an application to set aside a statutory demand
BETWEEN
MEGA PROJECT HOLDING LIMITED
Applicant
AND
OREWA DEVELOPMENTS LIMITED
Respondent
Hearing: 1 April 2019 Appearances:
R O Parmenter for the Applicant W A Endean for the Respondent
Judgment:
18 April 2019
JUDGMENT OF ASSOCIATE JUDGE R M BELL
This judgment was delivered by me on 18 April 2019 at 11:00am
pursuant to Rule 11.5 of the High Court Rules.
…………………………………
Deputy Registrar
Solicitors:
Winston Wang & Associates, Auckland, for the Applicant
Dawsons Lawyers (W A Endean), Howick, Auckland, for the RespondentCopy for:
Ray Parmenter, Barrister, Auckland, for the Applicant
MEGA PROJECT HOLDING LIMITED v OREWA DEVELOPMENTS LIMITED [2019] NZHC 866 [18 April 2019]
[1] The applicant and the respondent, both property developers, were each carrying out residential subdivisions at Orewa on adjoining properties. Their subdivision consents required them to upgrade West Hoe Heights Road, which runs between their properties. In December 2016, they made an agreement to share the costs. Orewa Developments Ltd would carry out the roading work and Mega Project Holding Ltd would pay Orewa Developments Ltd half the costs. Orewa Developments Ltd says that it has carried out the roading work and has asked Mega to pay its share, but Mega has paid nothing. Orewa Developments Ltd has served a demand under s 289 of the Companies Act on Mega requiring payment of
$1,452,803.62 “for roading construction costs adjoining the land belonging to you at West Hoe Heights Orewa, pursuant to a written agreement made on or about 5 December 2016 between you and the creditor”. Mega has applied to set aside the statutory demand as it says that there is a substantial dispute as to the alleged debt. It says that Orewa Developments Ltd has not met the conditions for payment. Mega had to be given certain information and it had to give certain approvals before work started, but Orewa Developments Ltd did the work without giving the information or obtaining Mega’s approval.
[2] Orewa Developments Ltd’s director was the late Liangren Li, who died in 2018. For its development, it had a project engineer, Property and Project Consulting Ltd. Mr Marsh, a director of that company has sworn an affidavit for Orewa Developments Ltd. Orewa Developments Ltd used CKL Surveys Ltd as its engineer. Mr Jackman, that company’s engineering manager, swore a late affidavit that was admitted without objection. The contractor who carried out the roading work was Dempsey Wood Civil Ltd. Mega’s director is Mr Jerry Zhu. Its engineering consultant was Mr Greg Richardson of Crang Civil Ltd.
Principles on setting aside applications
[3] There is no dispute as to the principles on applications under s 290 of the Companies Act to set aside statutory demands. Statutory demands under s 289 are used to create a presumption of insolvency under…
Continue reading Mega Project Holding Limited v Orewa Developments Limited
Sign in free to access the full text
- AGLC
- Mega Project Holding Limited v Orewa Developments Limited [2019] NZHC 866
- Case
- [2019] NZHC 866
- Decision Date
CaseChat Overview and Summary
The court first addressed the principles governing applications under s 290 to set aside statutory demands, emphasizing that the overall purpose of s 290 is to prevent injustice arising from the presumption of insolvency. The court found that Mega Project Holding Limited had shown a genuine and substantial dispute as to contractual liability, as the conditions for payment had not been met. Specifically, Mega Project Holding Limited had not been given the opportunity to approve the costs before work started, as required by the contract. The court also determined that there was a non-contractual debt owed by Mega Project Holding Limited to Orewa Developments Limited under the principle of free acceptance, as Mega Project Holding Limited had acquiesced in the work being carried out on a shared costs basis.
However, the court ruled that Orewa Developments Limited could use a statutory demand to enforce the non-contractual debt, as it was a liquidated demand. The court set aside the statutory demand to the extent that it exceeded $1,284,122.94, which was the total of Orewa Developments Limited's payment claims. The court ordered Mega Project Holding Limited to pay Orewa Developments Limited $1,284,122.94 by 17 May 2019, and if not paid in full, Orewa Developments Limited could begin a liquidation proceeding against Mega Project Holding Limited. Orewa Developments Limited was awarded costs on the application under category 2, with a deduction of 25 per cent.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.