IN THE HIGH COURT OF NEW ZEALAND DUNEDIN REGISTRY
I TE KŌTI MATUA O AOTEAROA ŌTEPOTI ROHE
CIV-2020-412-082
[2023] NZHC 468
BETWEEN KATHRYN RAE McKINLAY and ALAN WAYNE REID
Plaintiffs
AND
ROSS NEIL WHITBURN and VALERIE ELIZABETH WHITBURN
Defendants
Hearing: 22 February 2023 Appearances:
J W Cowan for Plaintiffs (by VMR)
T J Shiels KC for Defendants (by VMR)
Judgment:
10 March 2023
JUDGMENT OF ASSOCIATE JUDGE LESTER
McKINLAY v WHITBURN [2023] NZHC 468 [10 March 2023]
[1] On 28 May 2015, the defendants, Ross and Valerie Whitburn (the Whitburns), purchased 438 Portobello Road, Dunedin (the property) from Kathryn McKinlay and Alan Reid (the vendors), settlement to take place only eight days after, on 5 June 2015. The contract was on the Ninth Edition of the ADLS Agreement for Sale and Purchase of Real Estate (the 2015 contract).
[2] As at least part of the building on the land had been built by the vendors, cl 6.2(5) of the 2015 contract created a warranty that building work had received an appropriate permit, resource consent or building consent and that to the vendors knowledge, the work had been completed in compliance with those permits or consents and that where appropriate a Code Compliance Certificate was issued for the works.
[3]Further term of sale, cl 18 of the 2015 contract provided:
18.0 This Agreement is subject to and conditional upon the Vendor obtaining a Code Compliance Certificate for the improvements and an Electrical Certificate of Compliance for all improvements and providing copies of same to the Purchaser as a condition of settlement.
[4] Given the short time between the date of the 2015 contract and settlement, the vendors must have been confident they could satisfy cl 6.2(5) of the 2015 contract. As I will describe below that confidence proved to be badly misplaced.
Settlement does not occur
[5] The Code Compliance Certificate and the Electrical Certificate of Compliance required by cl 18 of the 2015 contract were not available at settlement. A flood event at the property in June 2015 brought to the Whitburns’ attention that there were a number of potential issues with building work at the property that would bring cl 6.2(5) into play. In circumstances that are disputed, the Whitburns took possession of the property but did not settle.
[6] The parties attended mediation and entered into a settlement agreement dated 19 December 2016 (the settlement agreement).
[7]The key provisions of the settlement agreement are as follows:
1.Subject to the provisions which follow, the Parties confirm the Agreement for Sale and purchase dated 27 May 2015.
2.The Vendors will obtain a Code Compliance Certificate for all improvements to the property other than the crib wall and the barbecue wall.
3.In relation to the crib wall the Vendors will obtain a Building Consent for repair work to the wall at the point where it changes direction and will also obtain a Code Compliance Certificate for this work.
4.The Vendor will…
Keep reading for free
Create a free CaseChat account to read McKinlay v Whitburn and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2023] NZHC 468
- Decision Date
CaseChat Overview and Summary
The court held that special condition 18 of the original contract was superseded by the terms of the settlement agreement. The vendors' obligation to obtain the compliance documents was unqualified and they had to do so within a reasonable time. While the vendors argued that obtaining the compliance documents would be difficult, the court found that a reasonable time had elapsed and the vendors were in breach of the settlement agreement. The court also rejected the argument that the contract had been frustrated. Finally, the court held that the purchasers' request for specific performance with compensation for the full purchase price was not an appropriate use of the specific performance jurisdiction. The purchasers had not demonstrated that the vendors did not have a defence based on hardship.
The court found the purchasers were entitled to judgment for liability against the vendors for the vendors' failure to settle. However, the form of relief for the finding of liability, including whether there will be an order for specific performance with compensation, is a matter for trial.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi