McFarlane v Dickson Marine (Refits) Limited

Case [2013] NZHC 647


IN THE HIGH COURT OF NEW ZEALAND NELSON REGISTRY

CIV-2012-442-375 [2013] NZHC 647

UNDER  District Courts Act 1947

IN THE MATTER OF     an appeal against a decision of the District

Court at Nelson

BETWEEN  ANDREW ANGUS MCFARLANE Appellant

ANDDICKSON MARINE (REFITS) LIMITED Respondent

Hearing:         19 February 2013

Counsel:         P A Cowey for Appellant

J M Fitchett for Respondent

Judgment:      27 March 2013

JUDGMENT OF MILLER J

Introduction

[1]    Dickson  Marine  repaired  a  large  launch,  the  Akarua,  at  the  request  of Mr McFarlane.  This appeal from the District Court concerns a sum of $24,746.29 that Dickson won from Mr McFarlane for the work.1

[2]    The District Court established that this was a time and materials contract with an agreed hourly labour rate.  But Dickson had given estimates, and it had promised to tell Mr McFarlane weekly what stage the work had reached and how much time

had  been  expended.    It  did  not  honour the promise,  and  it  ultimately invoiced

1      Unless otherwise specified, all figures used in this judgment include materials and GST, which was charged at 12.5 per cent until 1 October 2010.

MCFARLANE v DICKSON MARINE (REFITS) LIMITED HC NEL CIV-2012-442-375 [27 March 2013]

Mr McFarlane for about twice the estimates.  The question on appeal is this:  did the District Court err when it denied Mr McFarlane relief for Dickson’s admitted breach of that promise?

[3]    The Dickson estimates that are in dispute - a small portion of the work is not contested  -  totalled  $26,650.38.    After  work  began  in  February  2010  Dickson initially kept Mr McFarlane informed of progress and cost, but it ceased to do so at the end of April.  About mid-May it rendered invoices totalling $29,105.05 for work to  30  April.    Mr  McFarlane  paid  $28,309.67.    In  mid-June  2010  he  went  to Dickson’s yard to collect the vessel, and found invoices for a further $25,751.07, which he had not anticipated and refused to pay.

[4]    It is common ground that the appeal must be allowed in small part, for Dickson conceded in the District Court that it had claimed too much but that concession was not reflected in the judgment.   Mr McFarlane’s case goes much further than that, however: he says that he has paid more than the reasonable cost of the work.  To prove that, he called expert evidence, a challenge to the admissibility of which has been renewed on appeal.

The narrative

[5]    The Akarua is a 20m launch, built in 2002.   Through one of his companies Mr McFarlane bought the vessel in 2005.  Between 2006 and 2008 he had extensive repair and maintenance work done, some of it by men who gave expert evidence at the hearing.  That work cost more than $400,000.

[6]    In 2010 Mr McFarlane decided to prepare the vessel for sale.  He approached Dickson about necessary repair and maintenance work, explaining why he wanted it done.

[7]   Before the vessel was delivered to the yard one of Dickson’s operations managers, Barry Hart, travelled to Queen Charlotte Sound to inspect…

Continue reading McFarlane v Dickson Marine (Refits) Limited

Sign in free to access the full text

Details
AGLC
McFarlane v Dickson Marine (Refits) Limited [2013] NZHC 647
Case
[2013] NZHC 647
Decision Date

CaseChat Overview and Summary

The case of McFarlane v Dickson Marine (Refits) Limited concerns a legal dispute between Mr McFarlane, the appellant, and Dickson Marine (Refits) Limited, the respondent, regarding the repair of a large launch named Akarua. The central issue in the case is whether the District Court erred in denying Mr McFarlane relief for Dickson’s breach of its promise to keep him informed of the progress and costs of the work. The District Court had ruled in favour of Dickson Marine, awarding it $24,746.29 for the work done. The High Court of New Zealand, Nelson Registry, was tasked with reviewing this decision.

The High Court found that the promise made by Dickson Marine to keep Mr McFarlane informed weekly of the progress and cost of the work was a term of the contract. This promise was made before the formation of the contract and induced Mr McFarlane to enter into it. The court also determined that Mr McFarlane's failure to file a counterclaim was not a barrier to him relying on Dickson’s breach of its obligation. The court held that Mr McFarlane had lost the opportunity to control the scope and methodology of the work due to Dickson's failure to keep him informed, which could have led to more efficient work or a narrower scope of work at a fixed price. The court further concluded that the Consumer Guarantees Act 1993 did not add to Mr McFarlane's rights in this case.

The High Court allowed the appeal in part, set aside the District Court judgment, and awarded Dickson Marine $9,093.52. The court ordered that Mr McFarlane would have costs in the High Court on a 2B basis, with counsel to seek agreement on costs. The District Court decision as to costs remained unaffected.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.