IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
CIV-2017-404-1693 [2017] NZHC 2905
BETWEEN MARUTI INVESTMENTS LIMITED
Applicant
AND
RITELINE ROOFING LIMITED Respondent
Hearing: 22 November 2017 Appearances:
Mr Phillip Rice for Applicant
Mr Andrew Swan for RespondentJudgment:
24 November 2017
JUDGMENT OF ASSOCIATE JUDGE J P DOOGUE
This judgment was delivered by me on
24.11.17 at 3.30 pm, pursuant to
Rule 11.5 of the High Court Rules.
Registrar/Deputy Registrar
Date……………
MARUTI INVESTMENTS LIMITED v RITELINE ROOFING LIMITED [2017] NZHC 2905 [24 November
2017]
[1] The background to this case is that the parties entered into a contract in November 2016 pursuant to which the applicant which was intending to construct a house at Blockhouse Bay, Auckland sought and obtained from the respondent, a roofing company, a price to provide the roof on the subject property. The price being acceptable, the parties entered into a contract on 29 November 2016. The respondent as the roofer undertook in terms of the contract to supply and install the roof. The price was to be $22,106.53 for the cost of the roof together with a variation by adding an upgrade in the colour of the roof at a cost of $1,877.26.
[2] I shall refer to other aspects of the parties’ contract further on in this
judgment.
[3] The roof was duly constructed. Thereafter a dispute developed between the parties. Mr Happy a director and shareholder of the respondent says that in early December 2016 prior to carrying out the installation he undertook two site measures of the property at which time he says it was discovered that the actual roof size was greater than provided for on the plans by approximately 73 metres. He said he advised the applicant through its project manager, Mr A Kumar, of the size cost difference and said that there would be an extra cost for the “addition services based on the standard square metre rate”. Mr Happy said:
The applicant, through Mr Kumar, accepted that the actual roof size was greater than on the plans and authorized the respondent to proceed with the installation and agreed that the applicant would sort out the difference but needed roof on asap.
[4] Subsequently Mr Happy says that the respondent invoiced the applicant in the sum of $3,981.02 for the claimed additional costs and when those were not paid also charged interest under the contract. Further he deposed that the respondent had incurred “collection costs”.
[5] Mr Happy was of the belief that could be no dispute over the debt. He said the roof area was greater than provided for on the plans and the applicant agreed to pay the additional costs.
[6] Mr Tailor who was a director of the applicant also gave an affidavit. He produced a copy of the contract that his company had entered into with the respondent. He says that a full set of plans was provided to the respondent prior to the…
Keep reading for free
Create a free CaseChat account to read Maruti Investments Limited v Riteline Roofing Limited and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] NZHC 2905
- Decision Date
CaseChat Overview and Summary
The court had to decide whether there was a substantial dispute about the extra charges based on the increased size of the roof, which the respondent claimed as justification. The court examined the contract, which stated that the price was based on the plans provided, and that there was no provision for the respondent to vary its charges upwards to reflect a subsequent measuring up of the work actually carried out. The court also considered whether there was an oral agreement before the work was started that the job was bigger than the respondent had expected when providing its price for the job. The court found that there was at least an arguable case that there was a substantial dispute about the enforceability of the claim which the respondent had brought by way of a statutory demand.
The court set aside the statutory demand and ordered Riteline Roofing Limited to pay 2B costs to Maruti Investments Limited, subject to a reduction of 50% to reflect the Court’s disapproval of the non-compliance with the timetable directions in this case. The applicant was also entitled to disbursements to be approved by the Registrar.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi