IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY

CIV2010-404-006549 [2012] NZHC 241

BETWEEN  BRIAN MARTEL, RHIANNON MARY MARTEL AND SHERYL ELIZABETH LANE

Plaintiffs

ANDAUCKLAND CITY First Defendant

ANDJOHN CHENG XIE Second Defendant

Hearing:         29 February 2012

Appearances: D Cowan for the Second and Third Defendants

K Fulton for the Fourth Third Party

Judgment:      2 March 2012

JUDGMENT OF ASSOCIATE JUDGE CHRISTIANSEN

This judgment was delivered by me on

02.03.12 at 2:30pm, pursuant to

Rule 11.5 of the High Court Rules.

Registrar/Deputy Registrar

Date……………

Solicitors/Counsel:
D Cowan, Rainey Law, Auckland – doug.cowan@raineylaw.co.nz

K Fulton, Barrister, Auckland – kerryfulton@xtra.co.nz

BRIAN MARTEL, RHIANNON MARY MARTEL AND SHERYL ELIZABETH LANE V AUCKLAND CITY HC AK CIV 2010-404-006549 [2 March 2012]

ANDJOHNSCO LIMITED Third Defendant

ANDMAU SENG LING First Third Party

ANDIGOR ARAKELIAN Second Third Party

ANDDVK ROOFING & WATERPROOFING CO LIMITED

Third Third Party

ANDAUCKLAND FRAME & TRUSS SUPPLIES LIMITED (TRADING AS PLACEMAKERS)

Fourth Third Party

Background

[1]      In December 2005 the plaintiffs purchased the Bucklands Beach property of the second defendant.   The plaintiffs allege their dwelling upon the property is a leaky building and that as a result of defects in design and construction of the dwelling, moisture has been able to enter the structure causing rot and decay to the framing timber.  The plaintiffs have undertaken repairs and have sued to recover a cost of $633,517.22 plus consequential losses and general damages.

[2]      The plaintiffs allege Mr Xie was the developer/project manager when the dwelling was built over the period December 2002 to November 2003.

[3]    The plaintiffs allege the third defendant (Johnsco) was the head contractor/builder for the construction of the dwelling.  Mr Xie is the sole director of Johnsco.

[4]      Mr Xie and Johnsco deny they acted in the development in the capacities the plaintiffs allege.  They say that if however they are found liable to the plaintiffs then they are entitled to indemnity and/or contribution from the fourth third party (AFT) in connection with the supply of external and internal timber wall framing for the dwelling.

[5]      AFT were at all material times the suppliers of pre-nailed framing timber to the various Placemakers stores in the Auckland area.

[6]      In or about November 2003 Steve Marshall Building Limited (SMB) trading as Placemakers were contracted by Johnsco to supply:

(a)       Kiln dried and gauged radiata pine machine stressed graded H3 LOSP

treated timber frames for the external walls of the dwelling; and

(b)      Kiln dried and gauged radiata pine machine stressed graded H1 LOSP

treated timber frames for the internal walls of the dwelling.

[7]      SMB  contracted  AFT  to  manufacture  and  supply  the  pre-nailed  frames directly to Mr Xie and Johnsco and this they duly did in December 2002 for use in the construction of the dwelling.

[8]      On 10 November 2003 AFT issued a written Producer Statement to Johnsco confirming it had supplied timber frames for use during the construction of the dwelling. The Producer Statement stated that:

(a)      The external timber frames that were supplied were kiln…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Martel v Auckland City and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2012] NZHC 241
Decision Date

CaseChat Overview and Summary

The case involved a dispute between the plaintiffs, Brian Martel, Rhiannon Mary Martel, and Sheryl Elizabeth Lane, and the defendant, Auckland City. The plaintiffs claimed that their dwelling was a leaky building due to defects in design and construction, resulting in moisture entering the structure and causing rot and decay to the framing timber. The plaintiffs sought to recover costs of $633,517.22 plus consequential losses and general damages. The defendant, Auckland City, denied the claims and sought summary judgment or, alternatively, a strike-out of the claims.

The court considered the legal issues involved in the case, including whether there was sufficient evidence to prove that the timber used in the construction of the dwelling was untreated or treated to an adequate standard, whether there was an arguable claim for misleading and deceptive conduct in breach of the Fair Trading Act, whether the claims were time-barred, whether contractual limitations in the contract of supply precluded a claim, and whether there was an arguable claim of negligence.

The court found that there was not sufficient evidence to prove that the timber used in the construction of the dwelling was untreated or treated to an adequate standard. The court also found that the claims against Auckland City must fail, and summary judgment was granted in their favour. The court further found that except for the critical finding regarding the treatment of timber used in the dwelling construction, it would not have struck out the claims brought by Auckland City or the claim for contributory negligence brought by the plaintiffs. The court ordered that costs be paid to Auckland City on a 2B basis.