Marsden Villas Ltd v Wooding Construction Ltd HC Auckland CIV 2006-404-002136

Case

[2006] NZHC 569

25 May 2006

No judgment structure available for this case.

For a Court ready (fee required) version please follow this link

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY

CIV-2006-404-002136

BETWEEN  MARSDEN VILLAS LIMITED Plaintiff

AND  WOODING CONSTRUCTION LIMITED Defendant

Hearing:         11, 12 May 2006

Appearances: B Keene and M Colthart for Plaintiff

DG Hurd and SD Galloway for Defendant

Judgment:      25 May 2006

JUDGMENT OF ASHER J

This judgment was delivered by me on  at                am/pm pursuant to Rule 540(4) of the High Court Rules

…………………………………………… Registrar/Deputy Registrar

……………………………………………..

Date

Solicitors:

Knight Coldicutt, Private Box 106-214 Auckland (M Colthart) Hazelton Law, Solicitors, PO Box 5639, Wellington (SD Galloway)

MARSDEN VILLAS LTD V WOODING CONSTRUCTION LTD HC AK CIV-2006-404-002136  25 May

2006

Table of Contents

Paragraph Number

Introduction  [1] Background  [3] The issues  [8]

Purpose of the Construction Contracts Act 2002  [9]

First  issue  –  Has  Wooding  Construction  served  a  valid payment claim number 29?

[20]

Submission  that  progress  claim  number 29  is  not  a progress payment for the appropriate statutory period

[22]

The default position  [35]

The site meeting agreement  [44]

The inclusion of matters determined by the engineer  [55]

The inclusion of matters in the progress payment claims allegedly determined by the adjudicator

[61]

Conclusion as to progress payment claim  [68]

The second issue – Did Marsden Villas serve its payment schedule on time?

[71]

Was the relevant time for the payment schedule in the

Contract, or is it that provided for in the Act?

[77]

When was the payment claim number 29 received?  [86]

Third  issue  –  Was  Wooding  Construction  entitled  to suspend work?

[98]

Progress payment number 26  [115]

Conclusion  [123]

Introduction

[1]      Marsden  Villas  Limited  (“Marsden  Villas”)  and  Wooding  Construction Limited (“Wooding Construction”) are parties to a Construction Contract for the building of 30 apartments in Paihia (“the Contract”).   The Contract has taken far longer to complete than anticipated and there are disputes between the parties.

[2]      The claims and counterclaims give rise to two questions.  What, if any, valid claims has Wooding Construction against Marsden Villas, and has it lawfully suspended work?  The issues fall to be determined under the Construction Contracts Act 2002 (“the Act”).   That Act sets out a new procedural regime for payments between a principal and a contractor, the consequences of non-payment, and the adjudication of disputes during the course of a Construction Contract.  The Court is not asked to determine any substantive issues between the parties, such as who is responsible for the delays.  This is not the province of the Act.   Rather, the issues before the Court turn on the extent to which the parties have followed and complied with the provisions of the Act, and the consequences of that compliance or non- compliance.

Background

[3]      Marsden   Villas   entered   into   a   Construction   Contract   with   Wooding Construction on 16 October 2003.   The Contract sum was $7,269,631.60 exclusive of GST.   The Project was known as “Samuel Marsden Villas”.   It  involved the construction of 30 apartments of various sizes. The documents that constituted part of the Contract included the New Zealand standard form of contract for 1988, the General Conditions of Contract NZS 3910: 1998. The Construction Contracts Act is included in the list of agreed Contract documents.

[4]      The  engineer  to  the  Contract  was  Mr Vaughan  Brannigan  of  Brannigan Project Management Limited.  As such, he had the usual dual role of engineer under the Contract, and expert adviser to and representative of the principal.

[5]      Wooding Construction, as the Contract has gone over time, has submitted various  extension  of  time  claims  to  Marsden  Villas.    These  claims  have  been disputed by Marsden Villas and have been the subject of an adjudication process, which will  be referred  to  later  in  this  judgment.    This  case  turns  primarily on progress  claim  number 29.    This  claim  was  dated  27 February 2006.    Wooding Construction  claimed  a  payment  of  $2,909,706.59  under  this  claim.     In  the alternative,  given  the  various  challenges  to  the  validity of this  claim,  Wooding Construction claimed  under  an  earlier  progress  claim,  number 26.    The  amount owing under that claim is $1,651,988.80.

[6]      On 30 March 2006 Wooding Construction gave notice to Marsden Villas of its intention to suspend work, relying on the Act.   This was on the basis that the

$2,909,706.59 owing under payment  claim number 29 was overdue.   The notice provided for payment within five working days, failing which work would be suspended.

[7]      On 7 April 2006 Wooding Construction gave notice that it had suspended construction work from that date, and all work has ceased.  Wooding Construction also issued an alternative suspension notice, relying on non-payment of payment claim number 26.   It is in those circumstances that this dispute has come to this Court for urgent determination.

The issues

[8]      The Act sets out certain processes for compliance or non-compliance which give rise to certain consequences.  The issues of how much, if anything, is due, and the validity of the suspension, turn on the extent to which the parties have complied with the procedures set out in the Act.   I consider that the three issues are those generally identified by Mr Hurd for Wooding Construction as follows:

a)       Has Wooding Construction served a valid payment claim in terms of the Act?  Wooding Construction claims it has.  Marsden Villas claims it has not.

b)       If  Wooding  Construction  has  served  a  valid  payment  claim,  has Marsden Villas served its responding payment schedule within time? Marsden Villas claims that it has.  Wooding Construction claims that it has not.

c)      Was Wooding Construction entitled to suspend work?   Wooding Construction contends that it was.   Marsden Villas contends that it was not.

Purpose of the Construction Contracts Act 2002

[9]      All three of the issues raised turn, at least in part, on an interpretation of the relevant provisions of the Act.  Both parties in their submissions rely on the purpose of the legislation.  The purpose of the Act is set out in s 3 which reads:

3         Purpose

The purpose of this Act is to reform the law relating to construction contracts and, in particular,—

(a)       to facilitate regular and timely payments between the parties to a construction contract; and

(b)       to  provide for  the speedy  resolution  of  disputes  arising  under  a construction contract; and

(c)       to   provide   remedies   for   the   recovery   of   payments   under   a construction contract.

[10]   The Law Commission Paper which led to the legislation, Protecting Construction Contractors stated that the Act was “… to have as its purpose the ensuring of prompt cashflow to contractors …” (p 11).

[11]     A little earlier in the report it was put more graphically:

The basic intention is that instead of the cashflow being held up for weeks, months and years, pending a final solution, a decision, described as being “quick and dirty” will be given to resolve the cashflow situation, leaving a final determination of financial rights and obligations to be arrived at later.

[12]     In Gilbert-Ash (Northern) Ltd v Modern Engineering (Bristol) Ltd [1974] AC

689, 716 the House of Lords quoted Lord Denning in the Court below:

[t]here must be ‘cashflow’ in the building trade.  It is the very lifeblood of the enterprise.

This was quoted with approval by the New Zealand Court of Appeal in George

Developments Ltd v Canam Construction Ltd [2006] 1 NZLR 177 at [41].

[13]     In   Gilbert-Ash   the   House   of   Lords   allowed    the    appeal   against Lord Denning’s  decision.  Lord Reid  commented  at  p 699  that  in  a  range  of judgments the English Court of Appeal had come near to laying down a general rule that not only in cases between an employer and contractor, but also in cases between contractor and sub-contractor, sums due under an architect’s certificate must be paid at once without waiting for determination of claims for set-off.  This line of authority was disapproved by the House of Lords, at least as it related to contractor and sub- contractor.

[14]     The  effect  of the  New  Zealand  Construction  Contracts  Act 2002  was  to strongly confirm that such a regime which protected and encouraged cashflows was right for cases between the principal and contractor.  The intention was to improve the head contractor’s ability to obtain payment, by setting up a quick and mandatory payment process.   In enacting such legislation, the Legislature set aside the long- established conservative contractual approach to construction contracts which emphasised freedom of contract.  The history of these cases is described in Hon. R Smellie CNZM QC, Progress Payments and Adjudication, paras  1 – 15.  The Act has “emphatically vindicat[ed] Lord Denning’s approach” (Smellie, para 31.)

[15]     Consistent with the Law Commission Paper, the General Policy Statement which was set out at the beginning of the Explanatory Note accompanying the Bill reads as follows:

This Bill is intended to facilitate prompt and regular payments within the construction industry.

[16]     The Act sets up a procedure whereby requests for payment are to be provided by contractors in a certain form.  They must be responded to by the principal within a certain timeframe and in a certain form, failing which the amount claimed by the contractor will become due for payment and can be enforced in the Courts as a debt.

At that point, if the principal has failed to provide the response within the necessary time frame, the payment claimed must be made.  The substantive issues relating to the payment can still be argued at a later point and adjustments made later if it is shown that there was a set-off or other basis for reducing the contractor’s claim. When there is a failure to pay the Act gives the contractor the right to give notice of intention to suspend work, and then if no payment is made, to suspend work.  There is also a procedure set up for the adjudication of disputes.

[17]     The Act therefore has a focus on a payment procedure, the results that arise from the observance or non-observance of those procedures, and the quick resolution of disputes.    The processes that  it  sets  up  are  designed  to  side-step  immediate engagement on the substantive issues such as set-off for poor workmanship which were in the past so often used as tools for unscrupulous principals and head contractors to delay payments.  As far as the principal is concerned, the regime set up is “sudden death”.  Should the principal not follow the correct procedure, it can be obliged to pay in the interim what is claimed, whatever the merits.  In that way if a principal does not act in accordance with the quick procedures of the Act, that principal, rather than the contractor and sub-contractors, will have to bear the consequences of delay in terms of cashflow.

[18]     In this case Wooding Construction is asserting that exactly this has happened; Marsden Villas has failed to serve its response document, the payment schedule, within the required time and is therefore bound to pay the payment claimed despite the fact that it strongly contests it.   Wooding Construction submits the position is that the claim must be paid and the substantive issues can be argued later.  Marsden Villas strongly contests this.  The determination of the dispute will decide who bears the interim burden, at least in part, of the cost resulting from the delay in completing the job.

[19]     The three broad issues that are to be determined in this case derive from Wooding Construction’s wish to establish that it has served a valid payment claim, that Marsden Villas has failed to respond within the required time and in the required way, and that therefore Marsden Villas is obliged to make the interim payment.  The focus of Marsden Villas is to establish the opposite propositions; that the payment

claim made by Wooding Construction did not invoke the provisions of the Act, that if  it  did  invoke  the  provisions  of  the  Act,  that  Marsden  Villas’  response  was adequate, and that in any event in the circumstances Wooding Construction was not entitled to suspend work.

First  issue  –  Has  Wooding  Construction  served  a  valid  payment  claim,  in serving claim number 29?

[20]     This progress payment claim was dated 27 February 2005.   It was for the amount of $2,909,706.59.  It was sent by Wooding Construction to Mr Brannigan as the  agent  for  Marsden  Villas,  as  had  all  previous  progress  payment  claims. Mr Brannigan  responded  on  15 March 2006  setting  out  his  progress  payment valuation for $162,314.68.  Attached to his letter was a formal payment certificate. The covering letter stated that the payment certificate comprised all or part of a “payment schedule” under the Construction Contracts Act 2002.

[21]     Mr Keene, on behalf of Marsden Villas, has submitted that payment claim number 29 is not a valid claim under the Act, and therefore could not have given rise to an obligation on the principal’s part to pay or respond with a payment schedule, or a right on the contractor’s part to suspend.  He has raised a number of objections to the validity of the claim.

Submission  that  progress  claim  number 29  is  not  a  progress  payment  for  the appropriate statutory period

[22]     Progress claim number 29 is dated 27 February 2006.   It was delivered at

10:22 am on that  day.    27  and  28  February 2006  were both working  days,  and therefore the claim was not for a period of “not less than one month”.   The claim therefore is not a claim for work carried out for a period of over a calendar month. The period is shorter than one month.

[23]     Section 14 of the Act states that the parties are free to agree on progress payment provisions in their construction contact.   This Contract does provide for progress payment claims.  Section 15 provides that the default provisions of the Act

only apply if the parties to a construction contact fail to agree on a mechanism for determining any of the matters that are referred to in s 14.  The first question then is whether the Contract provisions or the provisions of the Act apply to the progress payment claims.  Mr Keene submits that the Act applies.  Mr Hurd submits that the Contract applies.

[24]     Clause 12 of this Contract specifically deals with the contractor’s claims. The clause states the periods for which claims can be made, what the claims will show, and how many progress payments will be made.   The interval between payments is implicitly provided for also in clause 12.1.1, which states that:

Unless otherwise provided in the Contract Documents such claims shall be submitted in respect of work carried out during periods of not less than one Month.

[25]     Clause 12, then, sets out the mechanism for determining progress payments as defined by s 14 of the Act.  The issue is considered in G Bayley and T Kennedy- Grant A Guide to the Construction Contracts Act at pp 57 - 58.  It is stated:

Section 14(b) of the Act provides that the parties to a construction contract are free to agree the date when each of those payments becomes due.  The due  date  for  payment  is  contained  in  many  standard  contracts  in  New Zealand, eg NZS 390: 1988 S12.2.

[26]     In Canam the contract involved was NZS 3915: 2000 which pre-dated the Act and used similar terminology to NZS 3910: 1988 in relation to clause 12.   It appears that the Court in Canam assumed that the times for payment were those set out in the Contract rather than the default provisions in the Act. The approach of the Court of Appeal appears to have been that the specific provisions of the Contract were to be read with the relevant provisions of the Act. The Court of Appeal observed at para [5]:

The combined effect of the specific provisions of the contracts and the Act was that a mechanism existed for periodic claims to be made which had to be responded to in a timely manner.

[27]     I am satisfied that the default provisions in the Act do not apply here. The progress payments provisions that are relevant are those in the Contract itself.  These provisions are part of the standard form of Contract.  That standard form pre-dated

the coming into force of the Act.  Thus, the terminology is different from that in the Act.  However, the Contract was signed by experienced parties six months after the Act came into force.  It must be assumed that the parties were aware of the Act, and would have expected the Contract’s provisions to be read with the Act. There is no attempt in the Contract to provide for the Act rather than the contract provisions to apply.  I therefore approach the issue of how the calculation should be done on the basis that the Contract applies rather than the default provisions.

[28]     Clause 12.1.1 states that the contractor may submit claims for payment under the Contract to the engineer, and that otherwise provided such claims:

… shall be submitted in respect of work carried out during periods of not less than one Month.

[29]     The plain words of clause 12 provide that claims will be submitted for work carried out for periods of not less than one month.  The word “month” is defined in the Contract as a calendar month.  It is not defined in the Act.  However, it could be expected that the month referred to would be a calendar month.

[30]     However, as submitted by Mr Hurd, to interpret the Contract as imposing an invariable  requirement  for  progress  payment  claims  to  be  for  at  least  one  full calendar month does not appear to make business sense.  For example, it could be expected  that  progress  payment  calculations  for  December  would  normally  be carried out  and issued prior to  the  end  of the  calendar  month,  as  the  Contract provides for work to cease from 24 December through to the end of the month.  It would be surprising in those circumstances for a contractor to be expected to wait until the middle of the holiday period, after the conclusion of December, to lodge its payment  claim for that month. It was the uncontradicted evidence  for  Wooding Construction that it was common practice within the industry for payment claims to be made within a day or two of the end of the month, as a matter of administrative convenience.  I note that the practice of sending out progress payment claims before the end of the month has not been complained about or indeed raised by the engineer in respect of earlier claims 1, 25 and 26.   Indeed, it was not raised in relation to payment claim number 29 until after the work was suspended.

[31]     The most likely interpretation of clause 12.1.1 is that claims should be issued on a calendar monthly basis, rather than on some shorter basis such as weekly or spasmodically without reference to  any particular period.   I do not interpret the clause as imposing any mandatory requirement that claims can issue only after the end of a calendar month.

[32]     Even if clause 12.1.1 does require claims to be for a period of at least one- month, I do not consider that a claim for a shorter period is an invalid claim under the Act.  The purpose of Subpart 2 of the Act is to allow the parties to reach their own agreement, and failing such agreement to set up a default provision for the making of claims (and provision for the due date of payment at s 18, which will be dealt with later in this judgment).  Its purpose is not to set up any form of mandatory procedure.   It is to  set  up the  mechanism for calculating progress claims.    The mandatory procedure comes in the next Subpart of the Act, relating to the procedure for making and responding to payment claims.   A failure to calculate a month’s instalment over a whole calendar  month period does not invalidate the payment claim itself.  The payment claims may contain all sorts of errors. The structure of the Act is to give the principal the opportunity to respond to those errors by providing a payment schedule within the mandatory time.

[33]     Although the judgment in Canam did not deal with this issue specifically, the Court in that case did consider other alleged faults in a payment claim.   Canam stated, following Windeyer J in Hawkins Construction (Australia) Pty Ltd v Mac’s Industrial Pipework Pty Ltd (2001) 163 FLR 18, at [43]:

… technical quibbles should not be allowed to vitiate a payment claim that substantively complies with the requirements of the Act …

The  Court  of  Appeal  confirmed  that  such  an  approach  is  “critical”  to  the interpretation of the Act.

[34]     There  is  no  obvious  reason  why  the  Legislature  should  have  made  it mandatory that progress payment claims be for certain specified periods, or indeed that  they  must  comply with  whatever  periods  are  specified  in  the  Construction Contract.  Such a requirement would be technical and oppressive, and is contrary to

the purpose of the Act of ensuring prompt cashflows.  This particular complaint is in the nature of a “quibble”.   There is no  suggestion that  there is any substantive problem caused for a principal as a consequence of the period of the claim being for less than that stipulated in the Contract.  There is nothing in the Act to indicate that a failure to observe the Contract in calculating a progress payment is fatal to a claim. For these reasons I do not consider that this objection is valid.   I will be referring later  in this  judgment  to the  severe and  immediate  consequences  suffered  by a principal who fails to serve a payment schedule in time.  The question arises whether what is good for the goose is good for the gander.   The answer is that the Act’s purpose is to facilitate prompt and regular payments, and that while a very strict position is taken as to payment time limits, such a strict and literal approach is not required in respect of matters of form.

The default position

[35]     If the Contract does not govern the period to which a payment claim relates, and the default  provision in s 17 does indeed apply, Mr Keene  submits that  the payment claim does not comply with s 17.   I have found that the Contract does apply, but will now consider the consequences if the Act applies.

[36]     Sections 15 – 18 set out  default  provisions for progress payments in the absence of express terms.  Section 17 reads as follows:

17       Amount of progress payment

(1)       The amount of a progress payment must be calculated by reference to—

(a)       the relevant period for that payment; and

(b)       the value of the construction work carried out, or to be carried out, during that period; and

(c)       any  relevant  provisions  in  the  construction  contract  (including, without limitation, provisions relating to the retention of money or liquidated damages).

(2)       For  the  purposes  of  subsection  (1)(a),  the  relevant  period  for  a progress payment under a construction contract is—

(a)       the  period  commencing  on  the  day  of  the  month  on  which construction work was first carried out under the contract and ending on the last day of that month (the first period); and

(b)       each month after the first period.

(3)       For the purposes of subsection (1)(b), the value of construction work must be calculated with regard to—

(a)       the contract price for the work; and

(b)       any other rates or prices set out in the contract; and

(c)       any variation to the construction work authorised under the contract;

and

(d)       if any work is defective, the estimated cost of rectifying the defect.

(4)       If the contract does not expressly provide for the matters referred to in  subsection  (3)(a)  and  (b),  the  value  of  construction  work  must  be calculated with regard to—

(a)       the reasonable value of the work; and

(b)       the  reasonable  value  of  any  variation  to  the  construction  work authorised under the contract; and

(c)       if any work is defective, the estimated cost of rectifying the defect.

[37]     Mr Keene, in arguing that s 17 applies and creates a mandatory requirement which has not been met, relies on s 17(2) of the Act.  This provides that a progress payment “must be calculated” by reference to the work carried out or to be carried out during the relevant period, which must be a calendar month.

[38]     However, s 17 does not appear to set out a mandatory requirement that the period be exactly one calendar month for each progress payment, or no less than one calendar month.  Rather, it appears to envisage that a claim may properly be made before the end of the calendar month period, in that at s 17(1)(b) it is provided that it may relate to work “to be carried out”.   The definition of ‘period’ appears to be broader and less specific in the Act than that  in the Contract  itself.   While the progress payment must be calculated by reference to the relevant  period for the payment, and while that should be monthly after the first period, there appears to be enough leeway in the words to allow a progress payment to be given before the end of a calendar month, and for a period that does not extend for duration of a calendar month.  I do not consider the progress claim to offend against s 17.

[39]     Claims must be calculated with reference to calendar monthly periods, which was done in this case.  They do not have to rigidly apply to every working day in a one-month period.

[40]     In any event, for the reasons that I have already given, the progress payment provisions in the Act do not set up a technical and mandatory pre-requisite to valid payment claims, requiring that they effectively be for progress payment periods of a calendar month.   That is not the purpose of this Part of the Act.   The purpose is rather to establish a basis upon which progress payments are to be calculated, so that there is a clear and exact amount for an exact period, for a clear and relevant value and with reference to any relevant provisions set out in a payment claim.  There will then be a claim, and the principal will then be in a position to properly respond.  If a principal does not agree with the way in which a progress payment is calculated in a progress claim, it may protest to this in a responding payment schedule.  That is the appropriate remedy.  There is no reason for the Court to interpret s 17 as setting up a gateway through which a valid claim must pass.   I bear in mind the substantive compliance approach, referred to earlier in this judgment.

[41]     The word “must” is used in s 17(3).   However, it is clear that calculation errors do not invalidate the progress payment at all; rather, such errors are responded to by the principal in the payment schedule, who can then protest at flaws in the claim, and set out its position as to the correct amount owing.   If that is done, the principal avoids the interim obligation to pay.

[42]     Further, under s 20 there are certain requirements that claims must meet to be payment claims under the Act.   Section 20(1) states that a payee “may” serve a payment claim on the payer for each progress payment, either at the end of the relevant period that is specified in or determined by the contract or, if the Contract does not so provide, at the end of the monthly period specified in s 17(2).  It is to be noted that the word used is “may” rather than the word “must” used in s 20(2).  This is a further indication that the period of the claim is not mandatory.

[43]     For these reasons I am satisfied that payment claim number 29 is not invalid because of any error in respect of the period being less than one month.   While I

consider that clause 12.0 of the Contract governs the matter, the same conclusion is reached if the Act applies.

The site meeting agreement

[44]     In the second argument for invalidity of the progress claim, it is submitted for Marsden Villas that the Contract was varied, so that extension of time claims would not be made until after the completion of works.   Marsden Villas argues that as a consequence all the extension of time claims which make up the current  claims which are in dispute are invalid and must be deferred.

[45]     The submission is based on the evidence of Mr Brannigan.  He asserted that in a site meeting, which took place in May 2004 before the commencement of the Contract, the point was formally agreed.  It is asserted that Mr Halton for Wooding Construction specifically accepted that he would not seek payments for extension of time claims until the end of the Contract, the consideration being that Mr Brannigan would not seek to deduct any money on behalf of Marsden Villas for liquidated damages until that time.  Mr Brannigan and Mr Wooding were not called for cross- examination.

[46]     The site meeting Minutes for 13 May 2004 recorded:

KH and VB agreed that Extension of Time payment or deduction would be made at the completion of the contract.

[47]     Mr Halton in his affidavit in reply did not deny receiving the site Minute, but asserted that the arrangement was casual and did not involve the “giving away” of any rights to obtain payment for extensions of time if the progress of the Project was significantly delayed.  Such a change would have seriously prejudiced his company in the event of serious delays.

[48]     Clause 2.7.3 of the Contract provides:

2.7.3    The General Conditions shall not be varied or modified except by the Special Conditions,  or  by  express  provision  in  any correspondence which has been identified as a contract document.

[49]     The alleged variation does not meet the requirements of clause 2.7.3.  It is not expressed to create a special condition, and the site Minutes for 13 May 2004 are not identified as a Contract document.   Even the words of the Minute itself do  not purport to record a variation of Contract.  The words indicate a “one-off” agreement, presumably relating to the single progress claim that is the subject of the preceding record in the Minutes.   The clause refers to “extension of time payment” in the singular rather than in the plural.  These words do not indicate a significant variation of the Contract.

[50]     In deciding whether the parties were agreeing to vary the Contract, the Court is able to consider their conduct after the alleged variation.  The question is not one of  interpretation,  but  the  resolution  of  the  matter  of  fact:  McLaren  v  Waikato Regional Council [1993] 1 NZLR 710, 731, National Bank v Murland [1991] 3

NZLR 86 at 93, Mears v Safecar Security Ltd [1983] QB 54, 77 per Stephenson LJ. Commonsense would indicate that if there was a variation on this important issue it could be expected to be reflected in the actions of the parties.

[51]     There was nothing in the parties’ conduct to indicate that they regarded the Contract as varied on this point.  Extension of time claims were included in progress payment claims through to March 2006, and were dealt with without the alleged variation being raised.  Indeed, the point was not raised in the adjudication that took place  early  this  year.    Mr Brannigan’s  correspondence  through  to  March 2006 indicated an acceptance that extension of time claims could be included in progress payment claims.

[52]     Mr Brannigan in his reply affidavit suggested that he processed the extension of time claims because the variation related to actual payments or deductions, rather than to whether extensions were to be granted.  However, the distinction appears to be a fine one, and lacking in commercial reality.  It would have been expected that there  would  have  been  some  qualification  expressed  by  Mr Brannigan  in  his correspondence about the extension of time claims if this was his intention.

[53]     I do not consider that the variation can be seen as part of a more general agreement   involving  the  deduction  of  liquidated   damages,   as   submitted   by

Mr Keene.    There  is  no  satisfactory  evidence  of  such  a  mutual  arrangement. Moreover, liquidated damages would not arise until after the due date for completion of the Contract (as properly extended).  Extension of time claims would obviously be made far earlier than that and, from the point of view of the contractor’s cashflow, would need to be dealt with as they arose.   There is no logic to this alleged “consideration”.   I can see no reason why the Contractor would have agreed to postpone extension of time claims to the end of the Contract.

[54]     For these reasons I do not consider that there was a variation of the Contract, whereby extension of time claims would be left  to  the actual completion of the Contract.  Wooding Construction was in a position to make extension of time claims as they arose.

The inclusion of matters determined by the engineer

[55]     The progress payment claim number 29 included sums which had been in Mr Brannigan’s earlier certificates and which he had rejected.  As a third ground for submitting that the claims were invalid, Mr Keene submitted that once the engineer had given a ruling, any challenge to it under the Contract had to be by a notice under that Contract.  That would have to be determined then in accordance with the dispute resolution provisions of the Contract. It could not be “regurgitated” in later claims.

[56]     This was a similar argument to that run in Canam. The Court of Appeal ruled at para [44]:

We do not accept the appellant’s contention that a contractor could never re- present a previously declined or ignored claim even if it wished to resubmit the claim or support it with further information. As noted by the Associate Judge … there is nothing in the Act that restricted payment claims in this way.

Mr Keene submitted that this statement by the Court of Appeal was obiter dicta and invited me not to apply it.  I do not accept that submission.  This statement was, in my view, part of the basic and essential reasoning of the Court of Appeal.

[57]     Certainly it would not be commercially sensible for a contractor making a monthly  claim  to  be  precluded  from  including  previous  outstanding  claims.

Providing the claimed amounts for different periods are properly itemised according to when those amounts were incurred, a cumulative claim presents no difficulty to the recipient of the claim, as the Court of Appeal pointed out in Canam at para [45]. Further, a contractor who does not understand a claim is able to seek clarification by using the framework contained in the Act (Canam: para [46]). The Court of Appeal observed that the inclusion of claims for work in prior periods appears to be common practice in the building industry (para [47]). Indeed, the Court of Appeal went on to state specifically, at para [53]:

We are persuaded that the provisions of the Act and the contract did not prevent the use of a cumulative-style claim.

[58]     As  the  Court  of  Appeal  pointed  out  at  para [54],  s 19  defines  “claimed amount” as “an amount of progress payment specified in a payment claim that the payee claims to be due for construction work carried out.”  Such a definition does not limit the claimed amount to work solely carried out in the period stated on the claim.   In this case, of course, the Contract applies.   Clause 12.1.1 provides that claims shall be submitted in respect of work carried out during periods of not less than one month.   These words do not limit the amount of any claim to the work carried out in most recent month.  Nor do the words of clause 12.1.2, which set out what the contractor’s claims shall show.

[59]     The Court of Appeal in Canam concluded at para [56]:

We reject the suggestion that the Act and its protective processes are to be interpreted in a restrictive and confining manner.

[60]     The  approach  urged  by  Marsden  Villas  is  a  confining  and  restrictive approach.  It is not supported by the words of the Contract or the words of the Act. There does not appear to be any policy reason that can be called into play to support it.  It is contrary to the ratio and reasoning of Canam.  I do not consider that the fact that the claim included earlier amounts claimed by Wooding Construction and rejected by the engineer invalidated the claim as a progress claim under the Act.

The inclusion of matters in the progress payment claims allegedly determined by the adjudicator

[61]     Mr Keene developed his submission concerning the contents of the progress payment claims further.  He submitted that the claims were flawed not only because they included earlier claims already rejected by the engineer but, further, because they included claims that had been considered and rejected by the adjudicator at an earlier adjudication.  Mr David Carden had been appointed an adjudicator under the Act on 8 November 2005.  The claim that he was required to consider related to a balance of progress claim number 22, an extension of time claim of 175 working days with costs, and a further extension of time claim for 127 working days with costs.  The substantial content of the adjudication claim related to the extension of time claims up to that time.

[62]     The Act creates a specific adjudication process in Part 3.  There is a right to refer disputes to arbitration.   The adjudication process is said not to prevent the parties from submitting the dispute to another dispute resolution process, which can even be concurrent (s 26(1)) and nothing in the adjudication process can effect any civil proceedings under a Construction Contract: s 27(1).  The adjudicator under s 48 must determine whether or not any of the parties to the adjudication are liable to make a payment under the Contract, and any questions in dispute about the rights and obligations of the parties under the Contract.   It is stated at s 58(2) that  an adjudicator’s determination about the parties’ rights and obligations under the construction  contract  is   not  enforceable.      A  determination  under   s 48(1)(a) concerning liability to make a payment is, however, enforceable.   Decisions of the adjudicator are reviewable under the Act.  The purpose of this part of the Act appears to set up a quick fire arbitration process, which will avoid delay and present a quick result, without precluding the parties from later or even contemporaneously adjudicating the issues in a more leisurely way.

[63]     Mr Keene submitted that the effect of these sections was to “give force” to the adjudicator’s determination on the extension of time claims.  He submitted that large portions of the progress claim  number 29 that  are  before this  Court  were effectively determined by the adjudicator.  He submitted that those old claims were

now re-submitted in progress claim number 29 as though the entire adjudication process had never happened.

[64]     It is necessary first to consider whether the adjudicator did in fact determine the extension of time claims that are the subject of much of the contested material in the progress claims.  It is clear that the adjudicator did not determine the extension of time claims that constitute the outstanding claims that are repeated in progress claim number 29.  His summary records that there is insufficient evidence before him for him to determine the extension of time claim to 29 August 2005.   He states “That claim will require processing and other dispute resolution process”.  In relation to the further extension of time claim for the further 127 days, he declined that claim for the same reasons, save for an agreed extension of time of 62 working days.

[65]     The position is, therefore, that none of the claims that are the subject of the ongoing progress claims have in fact been declined by the adjudicator.   Rather, he has declined to determine them.  The adjudicator’s decisions therefore do not change the  position  in  any  way.    The  extension  of  time  claims  were  declined  by  the engineer, and have not been dealt with by the adjudicator.

[66]     It is also the case that even if the adjudicator had determined in a declaratory way a right to an extension of time claim, that would be a determination about the parties’ rights and obligations under the Construction Contract rather than a determination of whether or not a party is liable to make the payment under the Contract.    Only  determinations  that  a  party  is  liable  to  make  a  payment  are enforceable under s 58(2).  There are certainly no determinations by the adjudicator in relation to the extension of time claims that fall into the enforceable category.

[67]     I do not consider that the submission of the extension of time claims at an earlier time to the adjudicator has resulted in any determination of those issues. Further, even if there had been some determination of the issues by the adjudicator, that determination does not preclude the party from pursuing its claims in a Court or by way of arbitration.  Given the acceptance of cumulative claims by the Court of Appeal in Canam, it is difficult to see why a progress claim should be invalidated because a claim is included that has already been adjudicated.  Res judicata would

not apply.  Such a claim could be rejected by the engineer in the principal’s response by way of payment schedule.  That is the appropriate response.  There is no reason why including such earlier claims would make the progress claim void.

Conclusion as to progress payment claim

[68]     I am not able to uphold the submissions that progress claim number 29 was invalid, or for some reason not a payment claim under the Act.  I do not consider that the inclusion of previously rejected claims has affected its effectiveness as a claim.

[69]     The obligatory requirements for payment claims are at s 20(2).  The payment claim must be:

20    Payment claims

(2)      A payment claim must— (a)     be in writing; and

(b)      contain  sufficient  details  to  identify  the  construction  contract  to which the progress payment relates; and

(c)      identify the construction work and the relevant period to which the progress payment relates; and

(d)      indicate a claimed amount and the due date for payment; and

(e)      indicate  the  manner  in  which  the  payee  calculated  the  claimed amount; and

(f)       state that it is made under this Act.

[70]     These s 20 requirements do not relate to the substantive content of claims, which has been the focus of some of the submissions of Marsden Villas on the point, but rather on clarity of form, so the principal knows what the claim is and can respond to it.   Those s 20 requirements were all met  by Wooding Construction. Issues such as the period for which a claim is made and the cumulative nature of the claim do not involve any breach of s 20(2).  There is no variation of the Contract in

relation to the extension of time claims.  For these reasons I hold that the payment claim number 29 was valid and effected under the Act.

The second issue – Did Marsden Villas serve its payment schedule on time?

[71]     The core obligation imposed by the Act in relation to this dispute was that contained in Part 2, Subpart 3 of the Act.   A principal must respond to a payment claim within the time prescribed by s 22 by providing a “payment schedule” to the contractor in terms of s 21.    The  severe  consequences  of not  providing  such  a payment schedule, or failing to pay the claimed amount within the times prescribed, are set out in s 23(2):

23       Consequences of not paying claimed amount where no payment schedule provided

(2)      The consequences are that the payee

(a)      may recover from the  payer, as a debt due to the  payee,  in any court,—

(i)       the unpaid portion of the claimed amount; and

(ii)      the actual  and  reasonable costs  of  recovery  awarded  against  the payer by that  court; and

(b)      may serve notice on the  payer of the payee's intention to suspend the carrying out of  construction work under the construction contract.

[72]     It was the failure of the principal to provide such a payment schedule in time which led to the appellant’s dilemma in Canam.  It is that same alleged failure which has led to these proceedings.  As a consequence of the alleged failure by Marsden Villas to provide a payment schedule on time to Wooding Construction, Wooding Construction contends that there is now due to it the amount claimed in payment claim number 29, and further, that it  was entitled to  give notice of intention to suspend, and ultimately to suspend all work.

[73]     Marsden Villas submits that its payment schedule was provided within time. There is agreement between the parties as to the relevant sequence of events.   In particular it is agreed that:

a)       Payment claim number 29 claiming $2,909,706.56 was received by facsimile  by  Mr Brannigan  as  the  agent  for  Marsden  Villas  on

27 February 2006.

b)       On  1 March 2006   Mr Brannigan  received   the   original   copy  of progress claim number 29.

c)       In  response,  payment  schedule  number 29  (dated  14 March 2006) stating an amount owing of $162,314.68 was sent by Mr Brannigan to Wooding Construction on 15 March 2006.

d)On 30 March 2006 Marsden Villas paid to Wooding Construction by bank credit the sum of $162,314.68.

[74]     The critical question is whether the payment schedule response of Marsden Villas was within the prescribed period.   That payment schedule certified that the amount owing was not $2,909,706.56, but rather the sum of $162,314.68.  That latter sum was paid on 30 March 2006, within time.   The $2,909,706.56 was not  paid within the prescribed timeframe.  Marsden Villas claims that it was not required to pay that amount, because it had served its payment schedule within time.  It raises various arguments to support that position.

[75]     Section 22(b) provides that the principal becomes liable to pay the claimed amount on the due date for the progress payment to which the payment claim relates, if the principal does not provide a payment schedule to the payee within:

(i)       the time required by the relevant construction contracts; or

(ii)       if the contract does not provide for the matter, 20 working days after the payment claim is served.

[76]     It is common ground between the parties that the payment schedule provided in response to payment claim number 29 was provided within 20 working days after the payment claim was served.   Thus,  if the default  period of 20 working days applies, then Wooding Construction is not in a position to claim the $2,909,707.56 and must concede the invalidity of its suspension.

Was the relevant time for the payment schedule the ten days in the Contract, or was it the twenty days provided for in the Act?

[77]     It must first be determined whether the Contract provided for the provision of the payment schedule.   It is common ground between the parties that NZS 3910:

1998 was drafted before the Act came into force.  It is also to be noted that in 1998, the Law Commission Report which led to its enactment had not been drafted or released.  However, at the time of execution of the Contract on 16 October 2003 the Act had been in force for over six months.  Clause 12.2.1 of the Contract provided:

12.2.1  Within 10 Working Days after the receipt of the Contractor’s claim the Engineer shall issue a progress payment certificate for a sum comprising  the   value   of   the  Contractor’s   claim  amended   as necessary under 12.3, less previous payments certified, and less any other deductions which are required by the terms of the contract or by law.   The certificate shall show details of any amendments and deductions.

[78]     The timeframe for the response was therefore 10 days under the Contract. Unsurprisingly the  phrase  “payment  schedule”  is not  used  in  the  1998  form of contract.  Mr Keene points out that the draughtsman of the original NZS 3910: 1998 did not even know or contemplate the various protections and provisions of the Act which came into force four years later.   There are different phrases used, such as “progress payment  certificate”  instead of “payment  schedule”.    He submits  that given the draconian consequences of the failure to meet the precise time deadlines under the Act, the Court should be slow to hold that the effect of clause 12.2.1 was to abridge the statutory response time from 20 working days to 10 days.

[79]     However, the Act was in force when the Contract was entered into.  It was referred to in correspondence between the parties when negotiating the Contract, and must be seen as part of its factual matrix.   While different  terminology is used

between the Contract and the Act, the structure of there being a contractor’s claim on a monthly basis and a substantive response within a set time limit is common to both the Contract and the Act.  As Mr Hurd points out, the technical requirements for a payment schedule as defined in s 5 and as referred to in s 21 of identifying the payment claim to which it relates, and of indicating an amount  accepted by the engineer,  are  similar  to  those  set  out  in  the  Contract  for  a  progress  payment certificate.

[80]     In Canam a similar contractual situation applied, with the Contract being a document drafted prior to the Act but entered into after the Act had come into force. In the High Court Associate, Judge Christiansen used the contractual provisions to calculate the time period for the payment schedule: see para [47]. The Court of Appeal proceeded on the basis that the combined effect of the specific provisions of the Contract and the Act was that a mechanism existed for periodic claims to be made which had to be responded to in a timely manner: see para [5].

[81]     If the provisions of clause 12 and the time limits in the Contract did not apply for the purposes of the Act then it would have been necessary for there to have been two responses to each payment claim, one for the Contract and one for the Act. There is no reference to two such processes in the Contract or the preceding correspondence.   It is to be noted as part of the background to the Contract that the parties knew that the Act applied.   Therefore, if they had intended there to be the provision of a separate payment schedule to the periodic claims, they would have provided for this in the Contract.  They did not do so.  I infer that they intended a single process, governed by clause 12.2.1.  I interpret that clause in the Contract as providing for the time within which the principal must provide a payment schedule, despite the absence of a direct statement to that effect.  I am further supported in that view by the conduct of the parties.

[82]     As a matter of practice the parties proceeded on the basis that the engineer’s response under clause 12.2.1 was the payment schedule response.  I consider that this conduct, which appears to have applied to all progress payment certificates, is admissible as an aid to interpretation of the meaning of clause 12.2: New Zealand Diving Equipment Ltd v Canterbury Pipe Lines Ltd [1967] NZLR 961 (CA), 978,

980, 985, 986, Attorney-General v Dreux Holdings Ltd (1996) 7 TCLR 617 (CA),

627-628, Valentines Properties Ltd v Huntco Corporation Ltd [2000] 3 NZLR 16 (CA), at [19] (reversed on appeal but not on this point).  It may not always be the case  that  the  conduct  of  the  parties  after  the  Contract  is  a  legitimate  aid  to construction and the issue has yet to be fully examined by the appellate courts. However, in this case where there are experienced commercial parties, their conduct immediately following the Contract and then throughout its implementation, in treating the response under clause 12.2.1 as also the  payment  schedule response under the Act, is as matter of logic a guide to the intended meaning of the Contract.

[83]     When  a  progress  payment  certificate  was  presented  to  Marsden  Villas, Wooding Construction in its covering letter stated:

In  accordance  with  the  terms  and  conditions  of  our  contract  and  the provisions of the Construction Contracts Act 2002 we anticipate the issue of your corresponding payment schedule within 10 working days or receipt of this payment claim.   Payment becomes due within 7 working days of the date of the payment schedule.

In the payment certificates Mr Brannigan specifically stated in the covering letter that they comprised “all or part of the payment schedule under the Construction Contracts Act 2002”.

[84]     The response on 14 March 2006 was not only expressed to be a payment schedule, but also expressed to be a “payment certificate” in the covering letter, and a “progress certificate” in the attachment  to the  letter.   The layout  is that  of a progress payment certificate in terms of the Contract.  There was never any attempt to send a separate document as a payment schedule.  It is illogical for Marsden Villas to assert that their only response, which was to issue progress payment certificates under paragraph 12.2 of the Contract and to refer to the certificates also as being payment schedules, was not an acceptance that the provisions and timetable set out in  clause 12  applied.    As  Mr Hurd  submitted,  Marsden  Villas  can  not  operate according to clause 12 for some purposes and not for others.

[85]     The parties, by this unequivocal adoption of the provisions of clause 12 as governing  the  sending  and  response  to  the  payment  claim,  have  confirmed  an

interpretation that the Contract term applies and not the default term in the Act.  That period was 10 working days and not the default period of 20 days.

When was the payment claim number 29 received?

[86]     It  is  common  ground  that  progress  claim  number 29  was  received  by

Mr Brannigan  by facsimile  at  10:22 am on  27 February 2006.    It  is  agreed  that

10 working days from the date of receipt of the facsimile copy was 13 March 2006. It is common ground that the date of the service of the progress payment certificate number 29, which I find was the responding payment schedule in terms of s 22 of the Act, was 15 March 2006.

[87]     I have found that the relevant time required by the Construction Contract for the service of the payment schedule was 10 days.  This means that if progress claim number 29  was  received  by  Mr Brannigan  for  the  purposes  of  the  Act   on

27 February 2006, the payment schedule served on 15 March 2006 was two days out of time.  If that is correct the amount claimable is the $2,909,706.56 now claimed by Wooding  Construction,   and   not  the  $162,314.68  set  out  in  Mr Brannigan’s responding payment  schedule.    However  Mr Keene contends that  the receipt  by facsimile on 27 February 2006 was not adequate service of the payment claim on Mr Brannigan, and that the 10 working days must run from the receipt of the original progress  claim  number 29  on  1 March 2006.    If  that  is  so,  then  the  progress certificate   and   payment    schedule   response    from   Mr Brannigan,    sent    on

15 March 2006, was in time.

[88]     The Contract does not contain any provision as to how documents are to be served.  In any event, while the Contract may provide for the computation of time for service because this is expressly stated to be so in s 22(b), the way in which service of notices is to be carried out is expressly provided for in s 80 of the Act.  Section 12 of the Act prohibits contracting out of the Act, so s 80 would have effect despite any provision to the contrary in any agreement or Contract.  The payment schedule is a document required to be served under the Act, and must be served in accordance with the provisions of the Act.

[89]     Section 80 contains provisions common to Acts of this type to the effect that it  is sufficient  service is the document  is delivered to the person, or left  at  the person’s usual or last known place of residence or business, or is posted in a letter addressed to that person.  It also provides at s 80(d) that is it sufficient service if:

(d)      the notice or document is sent in the prescribed manner (if any).

[90]     The Construction Contracts Regulations 2003 provide in r 9 as follows:

9         Additional modes of service

(1)       In addition to the modes of service specified in section 80 of the  Act, any notice or any other document required to be served on, or given to, any person under the Act or these regulations is sufficiently served if—

(a)       it is sent by fax; or

(b)       it is sent by email or other means of electronic communication and the requirements of  regulation 10 are met.

(2)       A notice or document sent by fax under subclause (1)(a) is, in the absence  of  proof  to  the  contrary,  served  or  given  if  the  fax  machine generated a record of the transmission of the notice or document to the fax machine of the recipient, and the date of the record is taken to be the date of receipt of that notice or document.

(3)       A notice or document sent by email or other means of electronic communication under subclause (1)(b) is, in the absence of proof to the contrary, regarded as having been served or given,—

(a)       in  the  case  of  an  addressee  who  has  designated  an  information system for the purpose of receiving emails or other electronic communications, at the time the email or communication enters that information system; or

(b)       in any other case, at the time the email or communication comes to the attention of the addressee.

(4)       For  the  purposes  of  subclause  (3),  information  system  means  a system for producing, sending, receiving, storing, displaying, or otherwise processing emails or other electronic communications.

[91]     Service by facsimile  is adequate service under  r 9(2).   It  being  common ground that a faxed document was sent on 27 February 2006, the question is whether there is “proof to the contrary” in terms of r 9(2) that it was served or given in compliance with the Regulation.

[92]     Mr Keene  submitted  that  the  facsimile  received  by  Mr Brannigan  was illegible, at least in part.  He submitted that if a document is not legibly transmitted in a way that it could be practically worked upon and responded to, and that is adequately proven, then in terms of r 9(2) the document has not been served or given as required.

[93]     In West City Construction Ltd v Edney (High Court Auckland, CIV 2005-

404-001066, 1 July 2005, Venning J) it was held that the service provisions of s 80 of the Act are not mandatory or exclusionary.  If a document is served on a party in a different way and the evidence satisfies the Court that the document has come to the attention of the party, then that is sufficient proof of service (para [35]).  The same practical approach must apply to r 9.

[94]     The  facsimile  copy  received  by  Mr Brannigan  on  27 February 2006  was produced to the Court.  I note that although Mr Brannigan had previously expressed problems in receiving legible facsimile transmissions, this particular facsimile was received without complaint.   Although Mr Brannigan’s facsimile machine may not have been of the best quality, the document received was legible on the print out that has been produced.   Despite the fact  that there is a slight  blurring  and  lack of definition in the letters and figures, it can be easily read.  For this reason I find that in terms of r 9 there was service by facsimile transmission on 27 February 2006, and that Marsden Villas has not proven to the contrary.

[95]     Mr Hurd further submitted that  even  if the document  were  illegible,  that illegibility was due to a failure of the engineer to install and maintain a facsimile machine that produced legible copies.   He submitted that party to a Construction Contract  could  not  frustrate  service  by  operating  a  defective  machine,  or  not supplying sufficient toner.

[96]     Regulation 9(2) states that any document can be served by facsimile if the facsimile machine generated a record of the transmission of the notice or document to the facsimile machine of the recipient.  If the document was sent by facsimile, and the recipient received a notice stating that it had been received, then the recipient would be aware that the document had been sent, even if that recipient was unable to

read it.  In such circumstances it would be expected that the recipient would take the initiative to obtain a legible copy.  Thus, even if Mr Brannigan was not able to read all of the facsimile transmission he had received, he was nevertheless on notice that the document had been sent and he should have taken steps to obtain a good copy. In the circumstances, even if Mr Brannigan had received a facsimile that was not fully legible, the receipt of it and the generation of a record of its transmission on his facsimile machine, would have been sufficient to constitute service for the purposes of the Act.   Any other conclusion would enable a recipient  of a notice to  take advantage of its own poor equipment or unwillingness to follow up messages.   It would be a result contrary to the purpose of the Act, which is to remove technical or artificial barriers to the payment process.

[97]     I am satisfied that Marsden Villas was served with the payment claim on

27 February 2006.  This means that pursuant to s 22 of the Act Marsden Villas was required to provide a payment schedule to Wooding Construction by 13 March 2006. It did not do so.  In terms of the Act, the consequences are severe.

Third issue – Was Wooding Construction entitled to suspend work?

[98]     I have found that payment claim number 29 was valid, and that no payment schedule response was served in time.   Marsden Villas has paid Wooding Construction on the basis of the payment schedule served out of time.  That sum was

$162,314.68.  It has not paid the amount required of $2,909,706.59.  In terms of s 23 of the Act, the consequence is that Marsden Villas became liable to pay that amount to Wooding Construction.  The net amount owing is $2,747,391.91 including GST, taking  into  account  the  $162,314.68  received.     In  terms  of  s 23(2)  Wooding Construction may recover the sum from Marsden Villas as a debt due together with costs.

[99]     Marsden Villas did not appear to dispute its liability for the sum if it failed on its arguments as to the validity of the payment claim and the time of the payment schedule referred to earlier in this judgment.  It did, however, submit that even if it were unsuccessful in its submissions on these points, the suspension notice issued by Wooding Construction was nevertheless invalid.  Mr Keene submitted that a late but

bona  fide  payment  schedule  provided  during  the  five  day  notice  of  suspension period, but before the actual suspension of work, would be sufficient to terminate the right to suspend.

[100]   It is necessary to consider the provisions relating to suspension.  Section 23 which sets out the consequences of not paying the claimed amount when no payment schedule has been provided.  Section  23(2) states:

23       Consequences of not paying claimed amount where no payment schedule provided

(2)      The consequences are that the payee

(a)      may recover from the  payer, as a debt due to the  payee,  in any court,—

(i)       the unpaid portion of the claimed amount; and

(ii)      the actual  and  reasonable costs  of  recovery  awarded  against  the payer by that  court; and

(b)       may serve notice on the  payer of the payee's intention to suspend the carrying out of  construction work under the construction contract.

[101]   Section 72(1) provides:

72       Suspension of construction work

(1)      A  party  who  carries  out   construction  work  under  a   construction contract (party A) has the right to suspend  work under that contract if—

(a)       any of the following circumstances applies:

(i)        a  claimed amount is not paid in full by the due date for its payment and no payment schedule has been provided by the party who it is claimed is liable for the payment (party B):

(ii)       a  scheduled amount is not paid in full by the due date for its payment even though a  payment schedule given by party B indicates a scheduled amount that party B proposes to pay to party A:

(iii)      party B has not complied with an adjudicator's determination that party B must pay an amount to party A by a particular date; and

(b)       party A has served on party B a notice under  section 23(2)(b) or section 24(2)(b) or  section 59(2)(b), as the case may be; and

(c)       the amount mentioned in subsection (1)(a)(i) or subsection (1)(a)(ii) is not paid, or the determination mentioned in subsection (1)(a)(iii) is not complied with, within 5  working da ys after the date of that notice.

[102]   Mr Keene focused on the words in s 72(1)(a)(i) and submitted that before there is a right to suspend work it is necessary for both the claimed amount to not be paid, and for there to be no payment schedule provided.  He submitted that it is not necessary for the purposes of this sub-section for the payment schedule to be delivered  within  the  statutory  minimum  period.    He  submitted  in  effect  that  a principal has a second chance to provide a payment schedule which, while it will not necessarily avoid the obligation to pay the amount in the payment claim, will bring an end to  the right  to  suspend.    He emphasised,  as he did  in relation to other submissions, the very severe and potentially financially disastrous consequences that may flow from an inadvertent error to provide a payment schedule on time.

[103]   The  words  of  s 72(1)  and  the  scheme  of  the  Act  do  not  support  this submission.  Section 72(1) requires as a pre-condition to suspension:

a)        a  default  in  the  paying  the  claimed  amount  or  in  providing  the payment schedule processes set out earlier in the Act;

b)       the service of a notice of intention to suspend;

c)        non-payment of the amount owed within five working days of the date of the notice.

[104]   While s 72(1)(a)(i) in requiring the claimed amount not to be paid and that “no payment schedule has been provided” does not refer to the time stated in s 22(b) within which the payment schedule should have been provided, it must be assumed that the reference to “has been provided” is a reference back to ss 22 and 23.  The word “provided” is used in s 22(b), in the heading of s 23 and in s 23(1)(a), all with reference to the time allowed in s 22(b).  The use of the same word is an indication that it incorporates a reference back to those sections.

[105]   The structure of s 72 does not make sense if the provision of a payment schedule partway through the five-day period can terminate the right to suspend.  If

that were so, s 72(1)(c) could be expected to specifically refer to the provision of a payment schedule, as an event cancelling the right to suspend work.  It does not do so.  It only refers to the amounts owed being paid as an event which will terminate the right to suspend.

[106]   Mr Keene  submitted  that  the  clause  “no  payment  schedule  has  been provided” could have no sensible meaning, unless it was intended to provide an opportunity to provide a payment schedule and avoid suspension.   However, the clause has meaning in that it refers back to s 22.  It will not be a basis for interim suspension if a claimed amount has not been paid in full and by the due date, but if a payment schedule has in fact been provided within the due payment schedule date. For the purposes of clarity the clause reiterates the fact that a payment schedule provided within the period will preclude suspension.

[107]   The New Zealand legislation is based upon the Housing Grants, Construction and Regeneration Act 1996.   Section 112 of that Act, which relates to the right to suspend  performance  for  non-payment,  is  more  specific.     It  states  that  the prerequisites are non-payment in full before the final of the claim demand and “… no effective notice to withhold payment has been given.”   The word “effective” relates back to the giving of a notice within the prescribed timeframe.   It can be expected that the New Zealand section was intended to do the same.

[108]   It  is  also  to  be  noted  that  the  past  tense  is  used  in  s 72(1)(a)(i).    The requirement is that no payment schedule “has” been provided.   That  indicates a reference back to the timeframe provided for in s 22.  It does not appear to be setting up a new five-day timeframe in which a payment schedule can be provided after the earlier time has expired.   It is more likely that the present tense would have been used if that was the intention.

[109]   If s 72(1) was interpreted as allowing a principal to avoid interim suspension by providing a payment schedule, it would lead to the anomalous position that the principal would be liable for the full amount of the debt owed in terms of s 23, but that debt would not be treated as owed for the purposes of suspension.   It would mean that  for the purposes of suspension there was  no  need to  file  a  payment

schedule within the timeframe set out in s 22, but rather there would be extra time provided, running from the date of any interim suspension notice.

[110]   Such a conclusion would run contrary to the overall scheme of the Act, and its stated purpose.  The Act was set up to protect contractors and to create a regime whereby principals can no longer delay and confuse the payment process.

[111]   The non-provision of the payment schedule is one of the crucial hinges of the Act.   The structure appears to be that there will be absolute and irreversible consequences resulting from the non-provision of such a payment schedule.   This appears to be consistent with the purpose of the Act to facilitate regular and timely payments, and the approach of the Court of Appeal in Canam. In Canam the focus was on the provision of the progress payment claim, rather than the provision of payment schedules.  However, it appears to have been the assumption that the severe consequences of the non-provision of a payment schedule in time were absolute.

[112]   Thus, I interpret the statement in s 72(1)(a)(i) that there is a right to suspend work where “no payment schedule has been provided” as meaning that the right arises when “no payment schedule has been provided in accordance with s 22”.

[113]   The only way in which suspension can be avoided if an interim suspension notice has been properly served is by the payment of the claimed amount, or if a valid payment schedule has issued, payment of the validly scheduled amount, or if there has been an adjudication determination that an amount be paid, payment of that amount.

[114]   There having been no payment of the claimed amount, or valid payment schedule issued, or payment of a validly scheduled amount, Wooding Construction was  entitled  to  suspend  works  and  did  so  in  accordance  with  the  Act  on

30 March 2006.

Progress payment number 26

[115]   This  is  the  alternative  fall  back  position  of  Wooding  Construction.    If payment claim number 29 is found to be invalid, then it relies on the earlier progress payment  claim  number 26.    Progress  claim  number 26  was  served  prior  to  the adjudication (although the extension of time claims were considered later by the adjudicator).

[116]   Progress payment  claim number 26 related to the work for the period to

31 December 2005.   It was served by facsimile  on 22 December 2005  seeking  a payment of $1,651,988.80.  The original was received on 24 December 2005.  The payment   certificate  and  payment   schedule  was   transmitted   by  facsimile   by Mr Brannigan  to  Wooding  Construction  on  17 January 2006,  certifying  for  the payment of $184,210.86.

[117]   The definition section in the Contract at clause 1.2 excludes from “working days”  any  days  falling  within  the  period  from  Thursday 25 December 2003  to Friday 2 January 2004 inclusive.   That definition does not apply, as the Court is dealing with the period two years later.  It is necessary to go to the definition section of the General Conditions of Contract at clause 1.2.  This states:

Working Day means a calendar day other than any Saturday, Sunday, public holiday or any day falling within the period from 24 December to 5 January both inclusive irrespective of the days on which work is actually carried out.

[118]   There is a similar provision in the Act.  For the reasons that I have already given, I do not consider the fact that the notice was sent  before the end of the calendar month was fatal to its validity as a payment claim under the Act.   The extension of time claims were not deferred by the variation of contract until the end of the Contract for reasons that I have already given.  The claim did include amounts previously rejected by Mr Brannigan, but for the reasons I have already given, the progress payment  claim is  valid,  even  if  it  did  reiterate the  previously  rejected claims.  The claim was served before the adjudication, so that even if there were any determination of the extension of time claims in that adjudication, that cannot affect it.

[119]   If there was a valid payment claim served on 22 December 2005, the latest date for issuing a payment certificate an payment schedule is in contention.   Mr Keene has raised an argument specific to progress claim number 26, which does not apply  to   progress  claim  number 29.     This  submission  revolves  around   the computation of the 10-day period over Christmas.   Mr Keene submitted that the calculation of Wooding Construction as to the last day for receipt of the schedule being  16 January 2006  was  wrong  by  one  day  and  that  the  correct  day  was

17 January 2006.  The payment schedule was sent on 17 January 2006.

[120]   Under s 22(b)(i) computation of time must be calculated under the relevant Construction Contract if it applies.   I have already found that the Contract in this case does apply.  On this basis 10 clear working days (which would include Friday

23 December 2005  and  then  10 days  from  and  including  6 January 2006)  would conclude on Wednesday 18 January 2006 (which I note is one day longer than the time  submitted  by  Mr Keene,  who  proposed  17 January 2006  as  the  date  for delivery).   The payment schedule was sent on 17 January 2006 and was therefore sent in time.   I find therefore that the payment  schedule in relation to  progress payment number 26 was forwarded within the required 10 working days.

[121]   It follows from this finding that if Wooding Construction had not been able to rely on progress payment number 29, its claim in respect of progress payment number 26 would fail, as it is based on the non-receipt of the payment schedule in time.  I find that payment schedule number 26 was served in time.

[122]   The  payment  schedule  in  payment  certificate  number 26  certified  for  a payment of $184,210.86.   That sum was paid within time by Marsden Villas to Wooding Construction on 1 February 2006.   There are therefore no moneys owed under progress payment claim number 26.  There was also no basis upon which to suspend work on the basis of the non-provision of a payment schedule in relation to progress claim number 26, or non-payment.

Conclusion

[123]   The result of this case reflects the drastic consequences of a failure on the part of a principal to serve a timely payment schedule.  The principal was in time in relation to  progress payment  number 26 and as a  consequence  is up  to  date on payments due on that claim and not at risk of suspension.  It was, however, late in delivering its payment schedule in relation to progress payment claim number 29. That failure means it is liable to pay the full amount claimed by Wooding Construction,   less  the  schedule  amount  that   has  been  paid.     That  sum  is

$2,747,391.91.  It also means that the suspension of work which is based upon the non-payment and the lack of provision of a payment schedule is valid and work will remain suspended until payment.

[124]   I make the following orders:

a)        I decline to order the declarations sought by Marsden Villas.

b)       Judgment  is  entered  for  Wooding  Construction  for  the  sum  of

$2,747,391.91 including  GST.    The  alternative  claim  by  Wooding

Construction for $1,467,777.94 including GST is dismissed.

c)        I  declare  that  the  current  suspension  of  the  Contract  works  by

Wooding Construction is lawful.

[125]   There are matters of interest and costs still to be determined, and I reserve leave to the parties to make submissions on these and any other ancillary matters arising out of these orders. The defendant, as the party that is primarily successful, is to file submissions within 14 days.  The plaintiff has 14 days in which to respond. The  defendant  then  will  have  7 days  in  which  to  reply.    The  parties  may  by memoranda seek alternative timetabling orders if required.

…………………………………

Asher J

Actions
Download as PDF Download as Word Document


Cases Citing This Decision

0

Cases Cited

0

Statutory Material Cited

1