IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2013-404-2158 [2013] NZHC 2284
BETWEEN M VAN DER WAL BUILDERS & CONTRACTORS LIMITED Appellant
ANDGEOFFREY HANHAM AND ELIZABETH HANHAM Respondents
Hearing: 29 August 2013
Appearances: S E McCabe for Appellant
C F Foote for Respondents
Judgment: 3 September 2013
JUDGMENT OF COOPER J
This judgment was delivered by Justice Cooper on
3 September 2013 at 3.00 p.m., pursuant to r 11.5 of the High Court Rules
Registrar/Deputy Registrar
Date:
Solicitors:
Martelli McKegg Wells & Cormack, Auckland
Kendall Sturm & Foote, Auckland
VAN DER WAL BUILDERS & CONTRACTORS LIMITED v HANHAM [2013] NZHC 2284 [3 September
2013]
Introduction
[1] The appellant, M Van Der Wal Builders & Contractors Ltd, appeals against a decision of Judge Gittos, given in the North Shore District Court on 28 March 2013.
[2] In the judgment the Judge held that the respondents, Mr and Mrs Hanham, who were the defendants in the District Court, were not liable to the appellant on a claim for damages in the sum of $188,297 for alleged breach of contract.
[3] The appellant is a builder and contracted with the respondents to carry out building work on their house at Kingfisher Grove, Greenhithe. The works consisted of renovations and improvements.
[4] Once the works were commenced, the Council required various works to be carried out on the basis that they were necessary to bring the existing house structure into compliance with the Building Code as altered following enactment of the Building Act 2004. The parties had not been aware that those requirements would be made, or the extent of them, when entering into the building contract. The result of the Council’s requirements was a very significant increase in the amount of work needing to be done, and its cost. Eventually, the respondents decided that they could not afford to continue with the works and purported to give the appellant notice terminating the contract on expiry of a two week period after the notice was given.
[5] The appellant’s claim in the District Court asserted that the purported cancellation was in breach of contract. Damages were sought on the basis of a calculation of the profit that would have been derived from completing the balance of the works outstanding as at the date of the wrongful cancellation.
[6] By agreement there were to be separate trials of liability and quantum. In the event, Judge Gittos held that the purported cancellation was valid. That meant that a trial on quantum would be unnecessary. The decision that the respondents were entitled to terminate the contract was based on a finding that the contract had an implied term entitling the respondents to terminate the contract in the circumstances that had arisen. The appellant says that that finding is incorrect.
[7] Before addressing the principal issues, it is appropriate to set out the relevant provisions of the contract and to summarise the reasons that the Judge gave for the decision he reached.
The contract
[8] The contract…
Keep reading for free
Create a free CaseChat account to read M Van Der Wal Builders & Contractors Limited v Hanham and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2013] NZHC 2284
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.