ICL Construction (2016) Limited v Ian Roebuck Crane Hire Limited

Link copied
Case Copied 24 min read

IN THE HIGH COURT OF NEW ZEALAND NEW PLYMOUTH REGISTRY

I TE KŌTI MATUA O AOTEAROA NGĀMOTU ROHE

CIV-2022-443-017

[2022] NZHC 2899

UNDER the District Court Act 2016

IN THE MATTER

of an appeal against a decision of the District Court at New Plymouth

BETWEEN

ICL CONSTRUCTION (2016) LIMITED

Appellant

AND

IAN ROEBUCK CRANE HIRE LIMITED

Respondent

Hearing: 19 October 2022

Counsel:

V A Whitfield and M Meier for Appellant I D Matheson for Respondent

Judgment:

4 November 2022


JUDGMENT OF CHURCHMAN J


[1]    This proceeding relates to a contractual dispute between ICL Construction (2016) Limited (ICL), and Ian Roebuck Crane Hire Limited (Roebuck), relating to ICL’s hire of a crane from Roebuck.

[2]    In a judgment of 23 August 2021, Judge Grieg addressed the issue of liability, holding that ICL was in fact liable to Roebuck for unpaid rental on the crane, leaving only the issue of quantum.1 In coming to that conclusion, the Judge considered that the evidence of Mr Cole Wenmoth, ICL’s shareholder and director, was not plausible.2


1      Ian Roebuck Crane Hire Limited v ICL (2016) Limited [2021] NZDC 16806.

2 At [31].

ICL CONSTRUCTION (2016) LIMITED v ROEBUCK CRANE HIRE LIMITED [2022] NZHC 2899 [4

November 2022]

[3]    In a further judgment of 15 February 2022, Judge Grieg struck out three briefs of evidence filed by ICL as to quantum, broadly on the basis that they related to a defence that was not pleaded, and which had never been previously raised in the correspondence between counsel.3 ICL now appeals that decision, on the grounds that the decision was “based on several incorrect legal analyses and has resulted in a gross miscarriage of justice”.

[4]    Roebuck opposes the appeal, saying that the Judge did not err, and that to allow the appeal would constitute a substantial misjustice.

[5]    For the reasons below, I have come to the view that the appeal should be dismissed.

Factual background

[6]    In September 2017, ICL hired a crane from Roebuck. After some time, ICL stopped paying regular invoices for its use, and a dispute arose as to whether there was a binding estimate for the entirety of the services provided. Roebuck instituted proceedings in November 2020, seeking judgment in the sum of $64,098.00, plus interest and costs.

[7]Roebuck alleged that:

It was verbally agreed between the plaintiff (through Ian Roebuck) and the defendant (through Cole Wenmoth) that the plaintiff would supply a 100 tonne crane to the worksite and the defendant would be charged for the time when the crane was actually used based on the rate applicable for the weight of the crane that would normally be used for the work requested.

…

The times during which the crane was used by the defendant were recorded in a crane docket which included information relating to the date of use and the hours to be charged for. Such dockets were signed by representatives of the plaintiff and defendant at the conclusion of each period of use.

A copy of each…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read ICL Construction (2016) Limited v Ian Roebuck Crane Hire Lim... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2022] NZHC 2899
Decision Date

CaseChat Overview and Summary

The case before the High Court is an appeal by ICL Construction (2016) Limited against a decision of the District Court, which found that ICL was liable to pay Roebuck Crane Hire Limited for unpaid crane rental. The appeal concerns the District Court’s decision to strike out evidence filed by ICL in relation to the issue of quantum, to bar ICL from advancing a defence as to quantum, to award an interim payment to Roebuck, and to award interest and costs. The District Court had previously determined that ICL was liable to Roebuck, and that ICL’s evidence in relation to quantum was an unpleaded defence. Roebuck opposed the appeal on the basis that the District Court’s decision was correct, and that to allow the appeal would constitute a substantial miscarriage of justice.

In dismissing the appeal, the High Court held that the District Court was correct to strike out the evidence, as it related to an unpleaded defence. The Court held that the District Court had jurisdiction to apply the relevant rule, and that Roebuck had not failed to particularise its claim. The Court held that it was unconscionable for ICL to pursue an unpleaded defence, and that barring ICL from raising the defence was within the discretion of the District Court. The Court held that the District Court was also correct to award an interim payment to Roebuck, as the Judge had before him sufficient evidence to conclude that an interim payment was appropriate. The Court held that the award of interest and costs was also correct, as the Judge had fixed interest in accordance with the claim, and as Roebuck was successful in their claim as to liability and the interlocutory application, they were entitled to seek costs. The appeal is dismissed, and the sum of $114,104.48 currently held by the Court is to be distributed to Roebuck. ICL is ordered to pay costs in the sum of $16,969.00 plus usual disbursements. Any outstanding interest and/or costs are to be paid by ICL to Roebuck directly. If counsel are unable to resolve the remaining issues as to quantum (if any) and/or costs, then they may file memoranda in the District Court seeking timetable directions for a quantum/costs hearing.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established