| IN THE COURT OF APPEAL OF NEW ZEALAND I TE KŌTI PĪRA O AOTEAROA |
| CA659/2020 [2022] NZCA 208 |
| BETWEEN | IAG NEW ZEALAND LIMITED |
| AND | QBE INSURANCE (AUSTRALIA) LIMITED |
| CA156/2021 | ||
| BETWEEN | IAG NEW ZEALAND LIMITED | |
| AND | JOAN MARGARET FRASER SLEIGHT AND ALAN LEITHFIELD SLEIGHT | |
| Hearing: | 14 and 15 September 2021 |
Court: | Kós P, French and Collins JJ |
Counsel: | N S Gedye QC, O V Collette-Moxon and M K Booth for Appellant in CA659/2020 and CA156/2021 |
Judgment: | 25 May 2022 at 11.30 am |
JUDGMENT OF THE COURT
AThe appeal in CA659/2020 is allowed.
BThe respondent’s cross-appeal in CA659/2020 is allowed.
CLeave is reserved to the parties in CA659/2020 to seek further orders in respect of quantum and the form of final judgment orders in light of this judgment in the event the parties are unable to agree on quantum.
DLeave is reserved to the parties in CA659/2020 to seek orders as to costs in the event costs are unable to be agreed.
EThe appeal in CA156/2021 is allowed and the decision of the High Court awarding interest to the first respondents is quashed.
FThere is no award of costs in CA156/2021.
____________________________________________________________________
REASONS OF THE COURT
(Given by French J)
Introduction
This case concerns defective repairs to an earthquake damaged home. The homeowners sued their insurance company IAG New Zealand Ltd (IAG), the repairer, the project manager monitoring the repairs and the project manager’s insurance company.
In the High Court, Gendall J upheld most of the homeowners’ claims against each of the four defendants and awarded damages representing the cost of the necessary further remedial work. He also upheld but only in part a cross-claim made by IAG against the project manager under an indemnity clause in the contract between those parties.[1]
[1]Sleight v Beckia Holdings Ltd [2020] NZHC 2851 [Substantive judgment].
IAG now brings two appeals. The first CA659/2020 relates to the Judge’s refusal to allow all of its indemnity claim against the project manager. The second appeal CA156/2021 relates to the Judge’s decision to award the homeowners interest dating back to 2015 on the damages.[2]
[2]Sleight v Beckia Holdings Ltd [2021] NZHC 456 [Costs and interest judgment].
For its part, the project manager cross-appeals one aspect of the Judge’s findings regarding the extent of its liability to indemnify IAG.
Background
Mr and Mrs Sleight owned a house in Christchurch. It was damaged in the Christchurch earthquakes of 2010 and 2011. They made a claim on their insurance policy with IAG and elected to repair the house. IAG accepted the claim.
It had become apparent to IAG that its usual administrative resources were insufficient to manage the large volume of claims it received as a result of the Christchurch earthquakes. It took a number of…
Keep reading for free
Create a free CaseChat account to read IAG New Zealand Ltd v QBE Insurance (Australia) Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2022] NZCA 208
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi