IN THE COURT OF APPEAL OF NEW ZEALAND

I TE KŌTI PĪRA O AOTEAROA

 CA659/2020  
 [2022] NZCA 208

BETWEEN

IAG NEW ZEALAND LIMITED
Appellant

AND

QBE INSURANCE (AUSTRALIA) LIMITED
Respondent

CA156/2021

BETWEEN

IAG NEW ZEALAND LIMITED
Appellant

AND

JOAN MARGARET FRASER SLEIGHT AND ALAN LEITHFIELD SLEIGHT
First Respondents

QBE INSURANCE (AUSTRALIA) LIMITED
Second Respondent

Hearing:

14 and 15 September 2021

Court:

Kós P, French and Collins JJ

Counsel:

N S Gedye QC, O V Collette-Moxon and M K Booth for Appellant in CA659/2020 and CA156/2021
D H McLellan QC, S D Galloway and B K McLay for Respondent in CA659/2020 and Second Respondent in CA156/2021
D J Cooper and M J Borcoski for First Respondents in CA156/2021

Judgment:

25 May 2022 at 11.30 am

JUDGMENT OF THE COURT

AThe appeal in CA659/2020 is allowed.

BThe respondent’s cross-appeal in CA659/2020 is allowed.

CLeave is reserved to the parties in CA659/2020 to seek further orders in respect of quantum and the form of final judgment orders in light of this judgment in the event the parties are unable to agree on quantum.

DLeave is reserved to the parties in CA659/2020 to seek orders as to costs in the event costs are unable to be agreed.

EThe appeal in CA156/2021 is allowed and the decision of the High Court awarding interest to the first respondents is quashed.

FThere is no award of costs in CA156/2021.

____________________________________________________________________

REASONS OF THE COURT

(Given by French J)

Introduction

  1. This case concerns defective repairs to an earthquake damaged home.  The homeowners sued their insurance company IAG New Zealand Ltd (IAG), the repairer, the project manager monitoring the repairs and the project manager’s insurance company.

  2. In the High Court, Gendall J upheld most of the homeowners’ claims against each of the four defendants and awarded damages representing the cost of the necessary further remedial work.  He also upheld but only in part a cross-claim made by IAG against the project manager under an indemnity clause in the contract between those parties.[1]

  3. IAG now brings two appeals.  The first CA659/2020 relates to the Judge’s refusal to allow all of its indemnity claim against the project manager.  The second appeal CA156/2021 relates to the Judge’s decision to award the homeowners interest dating back to 2015 on the damages.[2]

    [2]Sleight v Beckia Holdings Ltd [2021] NZHC 456 [Costs and interest judgment].

  4. For its part, the project manager cross-appeals one aspect of the Judge’s findings regarding the extent of its liability to indemnify IAG.

Background

  1. Mr and Mrs Sleight owned a house in Christchurch.  It was damaged in the Christchurch earthquakes of 2010 and 2011.  They made a claim on their insurance policy with IAG and elected to repair the house.  IAG accepted the claim.

  2. It had become apparent to IAG that its usual administrative resources were insufficient to manage the large volume of claims it received as a result of the Christchurch earthquakes.  It took a number of…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read IAG New Zealand Ltd v QBE Insurance (Australia) Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2022] NZCA 208
Decision Date

CaseChat Overview and Summary

The Court of Appeal of New Zealand was required to decide two main issues in this case. The first issue concerned the extent of the liability of Hawkins Management Ltd (Hawkins), the project manager, to indemnify IAG New Zealand Ltd (IAG), the insurance company, for any breach of obligations under the Rebuild Solution Master Agreement (RSMA). The second issue was whether interest should have been awarded to the homeowners for the delay in receiving damages. The court had to interpret the RSMA to determine the scope of Hawkins' obligations, particularly in relation to the quality of the repair work. The court also had to decide whether the award of interest under section 87 of the Judicature Act 1908 was appropriate given that the damages were calculated based on current repair costs rather than the rates prevailing in 2015. The Court of Appeal concluded that Hawkins was only to have a very limited quality assessment function under the RSMA, primarily an administrative and coordination role. The court found that the High Court had erred in its interpretation of the RSMA and in the application of the naked eye test. The court allowed both the appeal and cross-appeal, quashed the relevant findings of the High Court, and reserved leave to the parties to seek further orders in respect of quantum and the form of final judgment orders. As for the second issue, the Court of Appeal held that the award of interest was improper because the damages were calculated on the basis of present day costs of repairs, not the rates prevailing in 2015. The court allowed the appeal, quashed the decision of the High Court awarding interest, and made no award of costs.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established