IN THE HIGH COURT OF NEW ZEALAND CHRISTCHURCH REGISTRY
I TE KŌTI MATUA O AOTEAROA ŌTAUTAHI ROHE
CIV-2017-409-000100
[2021] NZHC 2708
BETWEEN PI-HUI BEATRICE TSAI HSU
First Plaintiff
AND
KENNETH TSAI
Second Plaintiff
AND
MARGARET ANN MAHONEY and GRAHAM PAUL MCQUEEN
First Defendants (Discontinued)
AND
BUSHNELL INVESTMENTS LIMITED
(formerly named BUSHNELL BUILDERS LIMITED)
Second DefendantAND
CHRISTCHURCH CITY COUNCIL
Third Defendant (Discontinued)
AND
LANCE PHILIP AUSTIN
Fourth Defendant
AND
BUSHNELL BUILDERS LIMITED
Fifth Defendant
Hearing: 6 October 2021 Appearances:
R G Smedley for Plaintiffs
Judgment:
11 October 2021
JUDGMENT OF JUSTICE DOOGUE
(Quantum)
HSU v MAHONEY [2021] NZHC 2708 [11 October 2021]
This judgment was delivered by me on 11 October 2021 at 2.30 pm pursuant to Rule 11.5 of the High Court Rules
Registrar/Deputy Registrar Date:
Introduction
[1] On 1 July 2021, I delivered a judgment in which I found Bushnell Investments Ltd (BIL) liable in contract and negligence for the failure to construct a tanking system to the standard of compliance with the Building Code for the plaintiffs’ home situated at 2 Clearview Lane, Mt Pleasant, Christchurch.
[2] I found BIL and Mr Austin, a director of BIL, to be concurrently liable for general damages of $25,000 to each of Ms Hsu and Mr Tsai.
[3] I reserved leave to the parties to revert to the Court for determination of the quantum for the remediation of the tanking system.
Background
[4] At the hearing in April, the expert quantity surveyor for the plaintiffs, Mr Webber, calculated the cost of remediating the retaining wall at $133,955.00 (excluding GST) broken down as follows:
1
Construction
98,297 Subtotal
98,297
2
Preliminary & General
8
%
7,864
3
Margin
10
%
10,616
Subtotal
116,777
4
Professional Fees
5,000
Subtotal
121,777
5
Contingency
10
%
12,178
Total
133,955
[5] The expert quantity surveyor for BIL and Mr Austin, Mr Eggleton, estimated the remediation cost as $66,654.65. His breakdown was as follows:
Total
46,465.10
Preliminary and General
8%
3,717.21
50,182.31 Contractors margin – 10%
10%
5,018.23
55,200.54 Contingency
5%
2,760.03
Total
excluding GST
$57,960.57
GST
8,694.08
Total including
GST
$66,654.65
[6] In the liability decision I observed that I had reservations about each of the experts’ evidence. I suggested they confer in light of the comments I had made to see if they were able to reach agreement on the cost of remediating the tanking system.
[7] I also invited both experts to consider what efficiencies could be made in the general costings to reflect that remediation of the tanking system on the south retaining wall will need to take place at the same time as the remediation of the tanking system on the east and west elevations of the house.
[8] The experts did not reach an agreed position for consideration by the Court. The plaintiffs therefore now apply for determination of quantum. They filed revised and updated evidence from Mr Webber who gave further evidence at the hearing. The defendants did not file any further evidence nor appear at the hearing. The…
Continue reading Hsu v Mahoney
Sign in free to access the full text
- AGLC
- Hsu v Mahoney [2021] NZHC 2708
- Case
- [2021] NZHC 2708
- Decision Date
CaseChat Overview and Summary
The main legal issues the court had to decide were the construction cost items that were disputed between the experts, such as the excavation of the south elevation, the cost of moving and reinstating a lamppost, and the supply and installation of Swelltite tanking, among others. The court also had to decide on the appropriate preliminary and general costs allowance, contingency allowance, and whether professional fees were required.
Justice Doogue found that the expert evidence presented by the plaintiffs was more reliable and accurate than that presented by the defendant. The court accepted the expert evidence provided by Mr Webber, who had revised some of his earlier costings and provided a comprehensive explanation for the costs involved. The court found that the costs for remediation should be calculated based on Mr Webber's revised estimate, taking into account the various factors discussed in the judgment.
As a result of the findings, Bushnell Investments Limited was ordered to pay the plaintiffs $140,724.42 plus interest. The issue of legal and associated costs was to be dealt with by way of written submissions. The plaintiffs were to file their submissions within 21 working days, and the defendants had 21 working days thereafter to file their submissions in reply.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.