Hi Build Limited (formerly Home Builders BOP Ltd) v Forman

Link copied
Case Copied 14 min read

IN THE HIGH COURT OF NEW ZEALAND TAURANGA REGISTRY

I TE KŌTI MATUA O AOTEAROA TAURANGA MOANA ROHE

CIV-2017-470-000183

[2018] NZHC 1320

UNDER The Arbitration Act 1996

IN THE MATTER

of an appeal against an arbitral award

BETWEEN

HI BUILD LIMITED (formerly HOME BUILDERS BOP LTD)

Appellant

AND

NIGEL KELVIN FORMAN and CLARE

LESLEY TURNER as trustees of the NK Forman Family Trust

Respondents

Hearing: 9 April 2018

Appearances:

T Conder for the Appellant

J Delaney for the Respondents

Judgment:

6 June 2018


JUDGMENT OF WOOLFORD J


This judgment was delivered by me on Wednesday, 6 June 2018 at 4:00 pm pursuant to r 11.5 of the High Court Rules.

Registrar/Deputy Registrar

Solicitors:           Holland Beckett Law, Tauranga

Harris Tate, Tauranga

Counsel:            J Delaney, Tauranga

HI BUILD LIMITED (formerly HOME BUILDERS BOP LTD) v FORMAN [2018] NZHC 1320 [6 June 2018]

Introduction

[1]                  The appellant, Hi Build Limited (“HBL”), and the respondents, Nigel Forman and Clare Turner as trustees of the NK Forman Family Trust (“the trustees”), submitted a dispute to arbitration. Essentially, the trustees said they were overcharged by HBL in relation to construction work undertaken by HBL. The arbitrator largely found for the trustees, leaving quantum to be determined between the parties.

[2]                  On 31 October 2017, Brewer J granted HBL leave to appeal the arbitrator’s award on a single question: did the arbitrator err in concluding that claims in relation to payment claims 1 to 9 were brought within time?1 The term “payment claim” is defined in the Construction Act 2002. I use that term and invoice interchangeably. HBL argues on appeal, as it did in the arbitration, that the trustees’ claim in relation to payment claims 1 to 9 was not brought in time.

[3]                  The question on appeal gives rise to four interrelated issues. First, should the trustees’ claim in the arbitration be characterised as being for breach of contract or money had and received? Second, what limitation period applies to the claim? Third, when did time begin to run? Fourth, was the trustees’ claim brought in time? This judgment determines these issues, and accordingly, the appeal.

Facts

[4]                  HBL completed construction work for the trustees between April 2009 and December 2010 pursuant to a written construction contract. The work consisted of renovating trust property, namely a house in Tauranga.

[5]                  The contract provided that payment for the work was to occur on a “charge-up basis”. Specifically, the key contractual terms regarding payment were:

(a)The final contract price would be “as expended” – the total amount of all invoiced claims.


1      Home Builder BOP Ltd v Forman [2017] NZHC 2155.

(b)The hourly charge-out rate for work [interpreted to be work undertaken directly by HBL’s director, Stuart Wood] would be $38.00 per hour excluding GST.

(c)The rate for travel would be $0.60 per kilometre and $38.00 per hour, both excluding GST, for Stuart Wood only.

(d)Materials, builders’ labour and subtrades would be charged at cost plus 9 per cent, including GST. The arbitrator found that the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Hi Build Limited (formerly Home Builders BOP Ltd) v Forman and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2018] NZHC 1320
Decision Date

CaseChat Overview and Summary

In Hi Build Limited (formerly Home Builders BOP Ltd) v Forman, the High Court of New Zealand considered an appeal by Hi Build Limited against an arbitral award that found it had overcharged the respondents, Nigel Forman and Clare Turner as trustees of the NK Forman Family Trust, by approximately $97,609.57. The central issue on appeal was whether the arbitrator had erred in concluding that the respondents' claims in relation to payment claims 1 to 9 were brought within the statutory limitation period. The appeal hinged on four interrelated questions: whether the respondents' claim should be characterised as a breach of contract or money had and received, the applicable limitation period, when time began to run, and whether the claim was brought in time. The court held that the respondents' claim was for breach of contract, not money had and received, because the evidence demonstrated that the parties had agreed to a "wash up" exercise at the end of the contract to resolve any overcharging or invoicing errors, which had not occurred. The court further held that the six-year limitation period under section 4(1)(a) of the Limitation Act 1950 applied to the claim, regardless of its characterisation. The court found that time began to run when the contract was breached, which occurred when the parties failed to conduct the wash up exercise at the end of the contract, rather than when each individual overpayment was made. Since the respondents filed their claim within six years of the breach occurring in December 2010, the claim was brought in time. Consequently, the appeal was dismissed. The court ordered that the parties should determine the quantum of the award in accordance with the arbitrator's interim award. If the parties were unable to agree on the quantum, they should return to the arbitrator. The court also noted that costs should follow the event, and it would make a decision on the costs if the parties could not agree.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established