Harbourcity Developments Limited v Owen HC Auckland CIV-2006-404-1400
[2007] NZHC 1708
•30 March 2007
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2006-404-1400
BETWEEN HARBOURCITY DEVELOPMENTS LIMITED
First Appellant
AND VIPOND PROPERTIES LIMITED Second Appellant
AND ELIZABETH JOYCE OWEN Respondent
Hearing: 22 June 2006
Appearances: S O McAnally for the Appellants
J Cox for the Respondent
Judgment: 30 March 2007 at 4.30 pm
JUDGMENT OF FRATER J
This judgment was delivered by Justice Frater on 30 March 2007 at 4.30 pm, pursuant to
r 540(4) of the High Court Rules
Registrar/Deputy Registrar
Date:
Solicitors: Keegan Alexander P O Box 999 Auckland for the Appellants
Rennie Cox P O Box 6647 Auckland for the Respondent
HARBOURCITY DEVELOPMENTS LTD AND ANOR V OWEN HC AK CIV-2006-404-1400 30 March
2007
[1] This is an appeal against the judgment delivered in the District Court at North Shore by His Honour Judge Hole on 17 February 2006 in which he declined to strike out claims against the appellants in negligence and nuisance.
Background
[2] The respondent, Ms Owen, is, and at all material times was, the registered proprietor of a property at 139 Vipond Road, Stanmore Bay, Whangaparoa. The appellants, Harbourcity Developments Ltd (“Harbourcity”) and Vipond Properties Ltd (“Vipond”) are each property developers.
[3] On or about 21 October 1996 the Rodney District Council (“the Council”) granted Vipond consent, on an un-notified basis, to subdivide a 2.26 ha block of land, part of which adjoined the respondent’s property, into 32 lots. Terms and conditions of the consent included the requirement that Lot 29, which gave access to the subdivision from Vipond Road, should vest in the Council as a public road and that a new residential lot (Lot 8), be situated between the respondent’s property and Lot 29. Other conditions were that all engineering plans be submitted to the engineer for approval before works commenced, that as built engineering plans be submitted before a compliance certificate under s 224(c) of the Resource Management Act 1991 (the “RMA”) was issued, and that the new road be formed and constructed to the Council’s standards.
[4] A survey plan to enable the first 11 titles in the subdivision to issue was deposited on 10 September 1998. This was followed, on 8 October, by a further plan comprising Lot 1, made up of the balance of the lots in the original subdivision and a new Lot 19, which gave access to Vipond Road. Neither was sought or consented to in the original subdivision consent.
[5] In April 2001 Vipond and the Council agreed, in the course of an exchange of letters, to the relocation of the road to a position to the south of Lot 29, immediately abutting the respondent’s property. No formal application was made under s 127 of the RMA to amend the conditions with regard to the position of the access road or to delete Lot 8. The respondent was unaware of the change and did not consent to it.
[6] Between May and August 2001 various applications were made to build motels on part of the subdivided land. The second application, which the respondent was notified about but did not object to, showed the proposed motel straddling Lot 29.
[7] On 16 December 2001 Vipond transferred possession of the subdivision site, including its interest in the subdivision consent, to Harbourcity. Four days later amended resource consent for the motel was granted, without objection, after a hearing. It was a condition of that consent that the new road be constructed in accordance with the revised roading plan which the Council had earlier (informally) agreed to.
[8] Construction of the new road, in the revised position, took place between late
February and April 2002.
[9] Engineering plans, showing the road “in location”, were approved by the
Council on 19 April 2002.
[10] On 23 October 2002, in reliance upon the resource consents, Harbourcity applied for permission to subdivide the balance of the land into 33 lots. Consent was granted on 27 February 2003 subject to the condition, inter alia, that “the proposed new road” meet engineering standards. In fact, by this stage, it had already been built.
[11] Thereafter the Council certified pursuant to s 224(c) of the RMA that the conditions of the subdivision had been complied with, and the road vested in it some time in 2004.
[12] The current proceedings, naming the Council as first defendant and Harbourcity and Vipond as second and third defendants respectively, were issued in the North Shore District Court in late 2003.
[13] Three causes of action are pleaded:
i) The first, against the Council, is based in negligence;
ii) The second, also in negligence, is against the appellants; and
iii) The third, in nuisance, is pleaded against all three defendants:
the Council and the appellants.
[14] The Council is not a party to the strike out application or this appeal.
The first amended statement of claim
[15] The operative pleading at the time of the District Court hearing was the first amended statement of claim dated 11 May 2005. The relevant claims, for present purposes, are:
[16] First, in negligence that:
27.At all material times Vipond and Harbourcity owed a duty of care to the Plaintiff:
27.1 To implement the subdivision consent in accordance with the RMA and the subdivision consent, and
27.2 To consult with and seek the consent of the plaintiff to the change of the position of the road, since the plaintiff was an adjacent owner to the development, and an adversely affected party.
28. Vipond and Harbourcity breached their duty to the plaintiff in that they carelessly, unlawfully and negligently:
28.1 Failed to implement the subdivision consent in accordance with the RMA and in accordance with the conditions of the subdivision consent, and
Failed to consult with and seek the consent of the plaintiff to the change in the position of the road.
...
29.As a result of the careless and unlawful actions of Vipond and Harbourcity, and the resulting breach of their duty of care to the Plaintiff, the Plaintiff suffered loss ...
30.The loss suffered by the Plaintiff was reasonably foreseeable and was a direct result of Vipond and Harbourcity’s failure to act in accordance with their duties to her.
[17] Secondly, in nuisance, that:
33.As owners and occupiers of the subdivision site, Vipond and Harbourcity owed duties to neighbouring property owners including the plaintiff not to carry out activities on the subdivision land which were, or may have been damaging or detrimental to or interfere with the proper enjoyment of the land of their neighbours’ properties including the plaintiff’s property.
34. The Defendants have acted in breach of their duties to the Plaintiff.
Particulars:
...
34.2 Without consent, with the unlawful permission of the Council, Vipond or Harbourcity constructed the road contrary to the terms of the subdivision consent directly adjacent to the Plaintiff’s property and vested it in the Council.
35.The road, and usage of it, constitutes a nuisance to the Plaintiff’s property.
Particulars:
35.1 The road exposes the Plaintiff’s property to significant adverse effects, including but not limited to; noise, vibration, visual effects, loss of privacy (including “living court” privacy), fumes, lighting, pedestrian traffic.
35.2 Adverse affects [sic] resulting from the steep road batter leading down to the fence on the boundary of the plaintiff’s property including the collection of rubbish against the plaintiff’s property and damage caused to the plaintiff’s fence boundary resulting from soil and metal which has piled up at the bottom of the road batter.
35.3 The loss of development potential of the plaintiff’s property.
35.4 The building up of the road and the resulting road batter which is too steep and at variance with Council’s standards and approved drawings has created a drainage problem.
[18] As a result the plaintiff claimed to have suffered loss of not less than
$143,018.25 made up as follows:
24.1 Diminution in value of the property in terms of the proposed redevelopment on the basis that the plaintiff is unable to obtain consent to re-develop as a front site so that the building platform is only 8 metres wide
24.2 Alternatively, diminution in value of the property in terms of the proposed redevelopment on the basis that the
$120,000.00
plaintiff is able to obtain consent to develop the property as a front site
24.3 The cost of new plans for the new dwelling proposed for the plaintiff’s site
24.4 Council fees relating to resource consent application
24.5 Surveying and engineering costs associated with new plans for dwelling
Landscaping costs to ameliorate affects of road and attempt to provide some privacy
$ 70,000.00
$ 7,706.25
$ 500.00
$ 5,000.00
$ 9,812.00
$143,018.25
[19] In addition, the plaintiffs claimed a further $35,000 general damages in respect of each cause of action.
[20] The appellants say they are not liable to the respondent in either negligence or nuisance. In the event however that they are, Vipond seek to be indemnified by Harbourcity. Harbourcity, in turn, have applied to strike out Vipond’s cross-claim.
Judgment under appeal
[21] While he seemed to accept that the action in negligence, as pleaded in the first amended statement of claim, could not succeed, Judge Hole was not prepared to strike it out. He said:
[16] When the statement of claim is looked at in its totality, it seems clear that the main complaint of the plaintiff is that the second and third defendants (or one of them) constructed a road adjacent to her property which has caused her various losses. The main losses claimed related to diminution in the value of the property. Thus, whether or not the subdivisional consent conditions were adhered to, the real complaint against the second and third defendants has little to do with them. Rather, it is the construction of the road which creates the problem. It is a reasonable inference that the road has been constructed on a piece of land where the zoning does not permit such construction. Significantly, cl 28.6 of the statement of claim states that one of the allegations of negligence is that the road was constructed in an unauthorised location. The provisions of s 23(2) have nothing to do with this allegation. However, the judgment in Chisholm may be pertinent.
[17] Counsel for the plaintiff suggested that the statement of claim could be amended by including an allegation of a duty upon the second and/or third defendants to construct the roading to access the subdivision in
accordance with the laws of New Zealand. Whilst this proposal is somewhat bald in its terms, nevertheless it seems to me that it may be possible to draft a tortious allegation pertaining to the construction of the road which in the circumstances of this case relies in part on evidence of a breach of statutory duty.
[18] It is not for the Court to propose suggested amendments to the statement of claim. This is an obligation imposed on the plaintiff. However, the plaintiff, to a relatively limited extent, has included in the statement of claim an allegation of negligence against the second and/or third defendants which seems to be capable of being converted into a pleading giving rise to a cause of action in favour of the plaintiff against the second and/or third defendants. In these circumstances, the application to strike out the statement of claim becomes inappropriate and the problems posed in the existing statement of claim should be remedied by amended pleadings.
[22] And while he also expressed some reservations with regard to the cause of action in nuisance, due to his findings in respect of the negligence claim, the Judge held that:
[21] It is not necessary for me to determine these matters now. The authorities cited in the first part of this judgment establish quite clearly that this is not a case where the statement of claim, or any part of it, should be struck out; rather, the defects as identified can be cured by fresh pleadings.
Strike out principles
[23] The strike out application was made under r 209 of the District Court Rules
1992, the relevant part of which provides:
Where a pleading –
(a) Discloses no reasonable cause of action …
the Court may at any stage of the proceeding, on such terms as it thinks fit, order that the whole or any part of the pleading be struck out.
…
[24] The principles pertaining to such applications are well settled. In van Soest v Residual Health Management Unit [2000] 1 NZLR 179 (CA) at [7], Blanchard J, delivering the majority judgment of the Court of Appeal, said:
It is common ground that a claim is not to be struck out unless it [is] so clearly untenable that it could not possibly succeed even after amendment in a manner proposed by the plaintiff, and on the assumption that all facts alleged in the statement of claim can be proved to be true (R Lucas & Son (Nelson Mail) Ltd v O’Brien [1978] 2 NZLR 289 at pp 294 – 295; Takaro
Properties Ltd (in receivership) v Rowling [1978] 2 NZLR 314 at pp 316 –
317; Attorney-General v Prince and Gardner [1998] 1 NZLR 262 at p 267).
The statement of claim must be beyond repair. It must be plain that even if it is reformulated the claim cannot succeed.
[25] To similar effect see Attorney-General v Prince and Gardner [1998] 1 NZLR
262 (CA) at 267 where the Court of Appeal accepted counsel’s submission that Courts should be very slow to rule on novel categories of duty of care at the strike out stage.
[26] While generally the Courts will not strike out parts of a pleading where to do so will not dispose of the entire case, this is by no means a hard and fast rule: see, for example, Auag Resources Ltd v Waihi Mines Ltd [1994] 3 NZLR 571.
The Resource Management Act 1991
[27] At issue in this appeal are ss 9, 11, 23 and 127 of the RMA, the material parts of which provided, at the relevant time, that:
PART 3 – DUTIES AND RESTRICTIONS UNDER THIS ACT LAND
9 Restrictions on use of land
(1) No person may use any land in a manner that contravenes a rule in a district plan or proposed district plan unless the activity is—
(a) Expressly allowed by a resource consent granted by the territorial authority responsible for the plan; ...
...
(4) In this section, the word “use” in relation to any land means—
(a) Any use, erection, reconstruction, placement, alteration, extension, removal, or demolition of any structure or part of any structure in, on, under, or over the land; or
...
(c) Any destruction of, damage to, or disturbance of, the habitats of plants or animals in, on, or under the land; or
(d) Any deposit of any substance in, on, or under the land; or
...
(e) Any other use of land—
and “may use” has a corresponding meaning.
...
11 Restrictions on subdivision of land
(1) No person may subdivide land, within the meaning of section 218, unless the subdivision is—
(a) Expressly allowed by a rule in a district plan and in any relevant proposed district plan or a resource consent, and a survey plan relating to the subdivision has in accordance with Part X—
(i) Been deposited by a District Land Registrar or a
Registrar of Deeds; ...
23 Other legal requirements not affected
(1) Compliance with this Act does not remove the need to comply with all other applicable Acts, regulations, bylaws, and rules of law.
(2) The duties and restrictions described in this Part shall only be enforceable against any person through the provisions of this Act; and no person shall be liable to any other person for a breach of any such duty or restriction except in accordance with the provisions of this Act.
(3) Nothing in subsection (2) limits or affects any right of action which any person may have independently of the provisions of this Act.
127 Change or cancellation of consent condition on application by consent holder
(1) The holder of a resource consent may apply to the consent authority for the change or cancellation of any condition of that consent (other than any condition as to the duration of the consent)—
(a) At any time specified for that purpose in the consent; or
(b) Whether or not the consent allows the holder to do so, at any time on the grounds that a change in circumstances has caused the condition to become inappropriate or unnecessary.
...
(3) Sections 88 to 121 shall apply, with all necessary modifications, to any application under subsection (1) as if the application were for a resource consent, except that section 93 (notification of applications) shall not apply if the consent authority is satisfied—
(a) That either—
(i) The adverse effect (other than any effect on any person whose written approval has been obtained in accordance with paragraph (b)) of the activity after any
change or cancellation of the condition will continue to be minor; or
(ii) The degree of adverse effect (other than any effect on any person whose written approval has been obtained in accordance with paragraph (b)) of the activity is likely to be unchanged or decreased relationship of any such change or cancellation; and
(b) That written approval has been obtained from every person (including any person who made a submission on the original application who may be affected by the change or cancellation) who, in the opinion of the authority, may be adversely affected by the granting of the change or cancellation, unless in the authority’s opinion it is unreasonable in all the circumstances to obtain every such approval.
The negligence claim
Submissions
[28] The appellants gave three reasons why the cause of action against them in negligence is untenable and cannot possibly succeed:
• The common law does not recognise any duties of the kind alleged.
• If either appellant constructed the road otherwise than in accordance with the terms of the subdivision consent they would be in breach of the restriction created by s 11(1) of the RMA. Pursuant to s 23(2) of the Act those duties and restrictions are only enforceable through the provisions of the RMA.
• The only obligation to consult imposed by the RMA is in Part 6 and relates to consent authorities. The common law does not otherwise acknowledge such a duty.
[29] They say that the other cause of action alluded to by the judge – that the construction of the road was not permitted by the zoning – is tantamount to arguing that the road was not constructed in accordance with the relevant District Plan – in which case ss 11(1) and 23(2) still apply.
[30] In response, the respondent:
• Pointed to ss 23(1) and 23(3) which expressly retain a plaintiff’s right to pursue remedies independently of the RMA, including causes of action based in negligence.
• Conceded that s 23(2) precludes her from claiming in respect of alleged breaches of duties or restrictions under Part 3 of the RMA.
• Acknowledged the appellants’ point in relation to the limitation on the obligation to consult, and in her proposed second amended statement of claim properly abandoned the previously claimed duties in that regard.
• Reformulated her negligence claim against the appellants in a way which, she says, is not based upon a breach of s 11(1).
[31] In her proposed second amended statement of claim the respondent now claims that the appellants owed her a duty of care to construct the road:
27.1 ... in a location authorised by the relevant authority and in accordance with the relevant legislation in force at the time; and
27.2 ... the engineering plans approved by the [Council] ...
[32] She alleges that, in breach of these duties, the appellants:
28. ... carelessly, unlawfully and negligently:
28.1 Failed to construct the public road ... in a location authorised by the relevant local authority, or in accordance with the relevant legislation in force at the time.
28.2 Constructed the road in an unauthorised location next to the
Plaintiff’s property ...
28.3 ... applied for certificates under section 223 RMA in breach of that section.
...
28.3.2 Knowing the actual terms on which the subdivision consent had been granted ... nevertheless authorised the preparation of plans showing configurations different from those specified in the subdivision
consent to be prepared, and submitted these non complying plans to the Council for approval ...
28.4 ... were issued certificates under section 224(c) RMA in breach of that section and the express conditions of the subdivision consent.
28.4.1 ... made arrangements to seek approval under section
224(c) knowing that the requirements of that section and the requirements of the subdivision consent had not been met because no formal approval had been given for the position of the road to be moved.
...
28.5 Implemented the subdivision consent in stages. The RMA requires a consent holder to develop and use its land in accordance with the terms of the consent. The subdivision consent made no provision for the subdivision to be carried out in stages, or for the balance lot to be created.
28.6 Failed to properly apply under the RMA for consent to change the road’s location under section 127 RMA.
28.7 Implemented the subdivision consent in breach of its express terms and conditions.
28.8 Commenced construction of the road before a written building consent was issued.
28.9 Failed to construct the public road in accordance with the engineering plans approved by the first defendant, ...
Discussion
[33] Although the primary focus of counsels’ submissions with regard to the negligence claim was on the application of s 23 of the RMA, it is appropriate to start by looking at the position at common law.
[34] It is well settled in the line of cases culminating in Rolls Royce New Zealand Ltd v Carter Holt Harvey Ltd [2005] 1 NZLR 324 and Attorney-General v Body Corporate 200200 [2007] 1 NZLR 95 (“Sacramento”) that the test to be applied in this country for determining whether a duty of care exists is whether, in all the circumstances, it is just and reasonable to impose it. That in turn, involves two broad fields of enquiry: first the proximity or relationship between the parties and secondly, any wider policy considerations bearing on the issue.
[35] The inquiry into proximity involves more than a simple question of foreseeability; it is concerned more generally with the nature of the relationship between the parties and necessarily involves consideration of the following factors: see Rolls Royce [59]-[65] and Sacramento [37]:
i) Whether duties of care have been imposed in analogous situations;
ii) The vulnerability of the plaintiff and the potential burden on the defendant – Relevant to this is whether other remedies are available to the plaintiff;
iii) The nature of the loss – The Courts are more likely to find proximity where there is a risk of property damage than where the loss is purely economic;
iv) The statutory or contractual background defining the relationship between the parties.
[36] In my view all these factors weigh against the existence of a common law duty of care owed by the appellants to the respondent in this case.
[37] The claimed duties, if they exist at all, arise in the context of the RMA.
[38] There is ample authority addressing the nature and extent of duties owed by local or territorial authorities under the RMA, or its predecessor, the Town and Country Planning Act 1953, to people applying for consents or permission: see Port Underwood Forests Limited v Marlborough County Council [1982] 1 NZLR 343 (HC), Morrison v Upper Hutt City Council [1998] 2 NZLR 331 and, very recently, Bella Vista Resort Limited and Anor v Western Bay of Plenty District Council [2007] NZCA. There is also authority concerning the duties which local authorities owe to neighbours whose amenities should reasonably be foreseen to be closely and directly affected by the grant of consent: Craig v East Coast Bays City Council [1986] 1
NZLR 99 (CA).
[39] But Mr Cox did not point to any analogous case where an applicant for resource consent, or any other consents or approvals, as distinct from the authority tasked with statutory responsibility for making the decision, has been held to owe a duty to a neighbour who is adversely affected by it. Nor did he explain how the appellants’ alleged negligence caused the respondent loss. Although he has attempted to re-formulate the duty, essentially it remains a duty to implement the subdivision in accordance with the resource consent and requirements of the RMA. However, responsibility for compliance with the statutory provisions lies not with the applicant for or holder of the consent but with the local authority.
[40] In his judgment in Bella Vista at [25] Robertson J had this to say about the
RMA, and the function and responsibilities of the consent authority within it:
I am satisfied that the proper conceptualisation of the statutory duty in the present case is that a consent authority must act within its power to issue consents in conformity with the purposes of the Act, namely the promotion of the sustainable management of natural and physical resources: s 5(1). In assessing sustainable management, a consent authority is directed to consider the need of communities to provide for their social, economic and cultural wellbeing as well as environmental protection: s 5(2). This direction does not mean that consent authorities are necessarily to be liable for an individual’s economic loss. The Privy Council in McGuire v Hastings District Council [2002] 1 NZLR 477 at [21] held that the true interpretation of s 5 does not allow the definition of sustainable management to be broken up into its component parts. The underlying purpose of the consent process is to provide a system whereby proposed activities can be assessed in terms of their impact on the environment and their sustainability. It does not require an assessment of the economic wellbeing of individual applicants, or subsequent purchasers.
[41] If the consent authority which makes critical decisions under the RMA is not necessarily under a duty to either an applicant or subsequent purchaser, it is fanciful to suggest that an applicant, acting on those decisions, if unlawful, should thereby be held liable for the economic loss suffered by a landowner affected by them.
[42] The only relevant obligation imposed on the appellant under the RMA was to undertake the subdivision in accordance with the District Plan and resource consent, as required by s 11. The other duties proposed by the respondent are simply situational duties owing from the original central one: see Sacramento [43]-[46].
[43] The placement of the road was governed by the terms of the resource consent. The basic reason it is said to be built in an unauthorised location is because the subdivision consent did not permit it and the zoning disallowed it. If a subdivision consent had given the go ahead to the construction of the road adjacent to the respondent’s property, it would not have been contrary to s 11(1). Similarly, the new allegations that the subdivision was carried out in stages, that the appellant did not apply for consent to vary the terms of the original consent and that the road was constructed contrary to the approved engineering plans and before written consent was issued, are all part and parcel of the general complaint, and therefore caught by the operation of s 23(2).
[44] The respondent could have followed the course taken by the adversely affected neighbours in Troughton & Ors v Western Bay of Plenty District Council HC TAU CIV-2003-470-238 18 February 2004 and applied for judicial review of the Council’s decisions before the road was built – but did not. However, she does still have and intends to pursue her claim against the Council.
[45] The respondent has failed to establish that the appellants owed her a common law duty of care. It follows that her claims against them in negligence cannot be sustained.
Nuisance
Submissions
[46] The appellants submit that the cause of action in nuisance, as pleaded, is untenable because:
• The common law does not impose the duties alleged by the respondent;
• The only duty or restriction when subdividing is a statutory one created by s 11(1) of the RMA. Breaches are only enforceable through the provisions of the Act by virtue of s 23(2);
• The construction of the road upon the land is a reasonable user of that land;
• Construction of the road, in itself, has not created any nuisance; Any nuisance suffered is a result of the effect of the use of the road, and neither appellant has occupation or control of it because upon completion the road vested in the Council;
• Furthermore, there is no allegation of recoverable physical damage. The claim is for diminution in the value of the property on the basis that the respondent now lives on a corner section rather than a front one.
[47] In response, the respondent says:
• The cause of action in nuisance is a common law claim; it does not rely upon the RMA;
• She does not claim that the construction of the road simpliciter is an unreasonable use of the adjoining land. Rather the nuisance claim is based upon the physical damage caused to her property and her inability to develop it as a result of the construction of the road. To emphasise the point she proposes that the particulars of the nuisance in para 35.1 of the first amended statement of claim be amended and expanded to say:
35.1 The road due to its excessively steep batter and height above the Plaintiff’s property, which is a result of the road’s construction contrary to the approved engineering drawings ... exposes the Plaintiff’s property to significant adverse effects, including but not limited to; noise, vibration, visual effects, loss of privacy (including “living court” privacy), fumes, lighting, pedestrian traffic.
35.2 Adverse affects [sic] resulting from the unauthorised and excessively steep road batter leading down to the fence on the boundary of the Plaintiff’s property, which has caused soil metal and rubbish to damage the Plaintiff'’s boundary fence so severely that it requires total reinstatement.
35.3 The building platform on the Plaintiff’s property has been reduced from a width of 15 metres to 8 metres as a
result of the construction of the road which makes the Plaintiff’s property a corner site. The Plaintiff can no longer construct the new dwelling on the property which was planned due to the significant reduction in the available building platform.
35.4 The Plaintiff’s property is prone to flooding caused by water being directed onto the Plaintiff’s property due to the construction of the road contrary to the approved engineering drawings and specifically as a result of the excessive road batter and the failure to construct the drainage on the northern side of the road in accordance with the approved drawings ...
• The fact that her property is worth less as a result of the nuisance is a consequence of it, not the basis for the claim;
• Vipond created the nuisance by seeking Council approval to change the original location of the road without following the statutory procedures or requirements;
• Although Harbourcity took possession of the land on 16 December 2001, ownership did not change until the registration of the transfer from Vipond to Harbourcity on 9 July 2002. The road was built between February and April 2002, when Vipond retained control as the legal owner;
• Harbourcity is liable because it adopted the nuisance commenced by Vipond by adopting an erroneous consent or failing to remedy the discrepancies surrounding the consent after it became aware that such discrepancies existed. Alternatively, as it constructed the road, Harbourcity commenced the nuisance and is therefore strictly liable.
Legal principles
[48] The relevant general principles of the law of private nuisance can be stated, for present purposes, as follows: see Todd (ed) The Law of Torts in New Zealand (4ed) 10.2.01:
• a private nuisance is an unreasonable interference with a person’s right to the use or enjoyment of an interest in land;
• the tort provides a remedy in respect of indirect or consequential interference with land;
• to be actionable the interference must cause either “injury to the property” (i.e. physical damage) or “sensible personal discomfort”: St Helen’s Smelting Co v Tipping [1865] 11 HLC 642 at 650;
• in either case the damage caused must be “material or substantial” and not
“merely trivial”: Hancock v Williams HC NWP AP 18/97 26 November
1997 Robertson J;
• it must also be ongoing;
• generally legal liability for the nuisance rests with the person in “possession and control of the land from which the nuisance proceeds”: Sedleigh-Denfield v O’Callaghan [1940] AC 880 at 903 (HL).
Discussion
[49] The focus of the Court’s enquiry in this case is threefold:
i) the nature and effect of the activity complained about;
ii) whether that constituted an actionable nuisance, and, if it does iii) whether either appellant can be held liable for it.
[50] The respondent’s claims can be divided into two distinct categories:
i) those alleging physical damage to her land or structures on it: paras 35.2 and 35.4 of the proposed second amended statement of claim; and
ii) those bearing on use and enjoyment: paras 35.1 and 35.3.
[51] The claims in respect of physical damage can be dealt with readily. There is no dispute that, if as a result of the way the road was constructed, floodwaters and/or unwanted materials have flowed on to the respondent’s land causing it physical damage, that could constitute a nuisance. Whether or not the road was authorised by a resource consent is irrelevant: Hawkes Bay Protein Ltd v Davidson [2003] 1
NZLR 536 [19]. A resource consent does not necessarily extinguish private rights created by the use of the consent: Todd 10.2.08 (3) at 425, footnote 253.
[52] The remaining claims of intangible interference with the respondent’s
“comfort and convenience” are more problematic.
[53] The test in this regard is:
simply whether a reasonable person, living or working in the particular area, would regard the interference as unacceptable:
Bank of New Zealand v Greenwood [1984] 1 NZLR 525 at 531.
[54] On this test, it is doubtful whether “noises, smells, fumes, vibration” and the like coming from vehicles on the road would constitute interference which a reasonable person, living in the area (which is or was in the process of being developed) would find unreasonable. Indeed, one would expect traffic to be heavier on Vipond Road than on the cul-de-sac which is the subject of the present dispute. All people living in residential or semi-residential areas have to learn to live with and accommodate the noise, fumes and vibrations and loss of privacy which are an inevitable consequence of vehicular traffic.
[55] Furthermore, there is nothing to indicate how this claim can arise as a result of the way in which the road was constructed. The complaint can only be about the use of the land as a road. But as Chambers J remarked in Chisholm v Auckland City Council [2002] NZRMA 362 at 395, albeit in the context of negligence:
... Landowners frequently use their land in ways which can cause financial detriment to their neighbours. They might build a house which blocks a neighbour’s view. They might build a shop in direct competition with their
neighbour’s shop. The law of negligence provides no protection in those circumstances.
[56] Neither does the law of nuisance.
[57] For both these reasons this claim cannot stand.
[58] The last, and most significant of the respondent’s nuisance claims concerns the alleged diminution in the value of her property as a result of the reduction and the size of the allowable building platform because the section is now a corner, rather than a front, site.
[59] That the respondent’s ability to use and enjoy her land has been affected by the construction of the road is evident; whether it is properly covered by the tort of nuisance is not.
[60] Again, essentially the claim is that a road has been constructed on the land.
[61] To be actionable in nuisance the interference with a plaintiff’s enjoyment of land must generally arise from something offensive emanating from the defendant’s land to the plaintiff’s land: Hunter v Canary Wharf Ltd at 685 per Lord Goff. In Bank of New Zealand v Greenwood the glass roof of a veranda was held to create a nuisance by reflecting sunlight into the windows of neighbouring buildings. In Varnier v Vector Energy Ltd [2004] NZRMA 193 the alleged nuisance concerned the emission from an overhead electricity transmission line of electromagnetic fields said to adversely affect the health of occupiers of neighbouring land. In the absence of the necessary link between an activity on the adjoining land and that of the plaintiff, the claim particularised in para 35.3 must also fail.
[62] The final issue then is whether either appellant can be liable for the physical damage to the respondent’s property brought about by the way in which the road has been constructed.
[63] On the Sedleigh-Denfield v O’Callaghan test noted at [48] above, responsibility for any ongoing nuisance, if established, must rest with the Council, as
the current owner of the road, i.e. the body in possession and control of the land from which the alleged nuisance proceeds.
[64] But that is not necessarily the end of the matter. There is authority for also holding the creators of the nuisance liable. The learned authors of Clerk and Lindsell on Torts (19ed) 2006 20-51 state the position boldly:
The person liable for a nuisance is the actual wrongdoer, whether or not he is in occupation of the land ... the person who originally created the nuisance remains liable for all the damage flowing from its continuance, even though by reason of his not being in possession of the premises he is unable to prevent their continuance. “If a wrongdoer conveys his wrong over to another whereby he puts it out of his power to redress it, he ought to answer for it”. Accordingly, he remains liable even if he has sold or leased the building.
[65] On this authority it is possible that Harbourcity, which built the road, could be held liable. I therefore decline to strike out the remaining claims against it.
[66] Vipond’s position is different. Mr Cox submitted that they created the nuisance by seeking Council’s approval to change the original position of the road to its current position without following statutory procedures or requirements. But that is not the nuisance. The actionable nuisance can only relate to the way in which the road was constructed. As already noted, any complaint about the process by which consent was obtained to construct it in the position that it was, can only be addressed, if at all, in the context of the RMA legislation.
[67] The claims under para 35.2 and 35.4 against Vipond are struck out accordingly.
Result
[68] The appeal is allowed to the extent that the claims against both appellants in negligence are struck out, as are all claims against Vipond in nuisance and those particularised in paras 35.1 and 35.3 of the proposed second amended statement of claim against Harbourcity.
[69] This matter is remitted to the District Court for the settlement conference which, I understand, has been deferred pending resolution of the appeal, to be convened.
Costs
[70] The appellants, having been largely successful on appeal, are entitled to an order for costs in their favour. These were agreed to be on scale 2B.
[71] If counsel are unable to agree upon quantum, memoranda addressing the issue are to be filed by 16 April 2007.
M A Frater J
0
0
0