IN THE HIGH COURT OF NEW ZEALAND HAMILTON REGISTRY
I TE KŌTI MATUA O AOTEAROA KIRIKIRIROA ROHE
CIV-2020-419-000123
[2021] NZHC 2032
BETWEEN GEORGE GRANT ENGINEERING LIMITED
PlaintiffAND
FABRICATION & PIPE SERVICES LIMITED
Defendant
Hearing: On the papers Counsel:
T J P Bowler for Plaintiff
V Whitfield and M J Meier for Defendant
Judgment:
6 August 2021
COSTS JUDGMENT OF ASSOCIATE JUDGE P J ANDREW
This judgment was delivered by Associate Judge Andrew on 6 August 2021 at 3.30 pm
pursuant to r 11.5 of the High Court Rules Registrar / Deputy Registrar Date………………………
GEORGE GRANT ENGINEERING LTD v FABRICATION & PIPE SERVICES LTD [2021] NZHC 2032 [6
August 2021]
Introduction
[1] In my substantive judgment of 2 June 2021,1 concerning applications for summary judgment from each of the plaintiff, George Grant Engineering (GGE), and defendant, Fabrication & Pipe Services Limited (FPS), I:
(a)dismissed GGE’s application for summary judgment; and
(b)granted summary judgment on the FPS’s application, dismissing the proceedings in their entirety.
FPS now seeks increased costs of $40,656.03 plus disbursements.
[3] GGE opposes any increase and contends the Court should award usual 2B scale costs, in the sum of $10,038.00.
Relevant legal principles
[4] In accordance with Part 14 of the High Court Rules 2016, the party who fails with respect to a proceeding should pay costs to the party who succeeds.2 An award of costs should reflect the complexity and significance of the proceeding3 and costs should be assessed by applying the appropriate daily recovery rate to the time considered reasonable for each step reasonably required in relation to the proceeding.4
[5] The Court of Appeal summarised the approach to standard scale costs, increased costs and indemnity costs in Bradbury v Westpac Banking Corporation:5
(a)standard scale applies by default where cause is not shown to depart from it;
(b)increased costs may be ordered where there is a failure by the paying party to act reasonably; and
(c)indemnity costs may be ordered where that party has behaved either badly or very unreasonably.
1 George Grant Engineering Ltd v Fabrication & Pipe Services Ltd [2021] NZHC 1281.
2 High Court Rules 2016, r 14.2(1)(a).
3 High Court Rules 2016, r 14.2.(1)(b).
4 High Court Rules 2016, r 14.2(a)(c).
5 Bradbury v Westpac Banking Corporation [2009] 3 NZLR 400, (2009) 19 PRNZ 385 (CA) at [27].
[6] A Court may award increased costs if the party opposing costs has contributed unnecessarily to the time or expense of the proceeding by taking or pursuing an unnecessary step or an argument that lacks merit.6
Decision
Scale costs
[7] FPS has advised that its actual costs are $40,656.03 and properly accepts that the Court cannot award an amount of costs that exceed that sum.7
[8] FPS seeks an uplift of 25 per cent on its calculation of scale costs. It provides a schedule of costs calculations that totals $34,655.00.
[9] I accept GGE’s submission that there is a clear element of duplication in these essentially parallel summary judgment applications. Some discount…
Continue reading George Grant Engineering Limited v Fabrication & Pipe Servic...
Sign in free to access the full text
- AGLC
- George Grant Engineering Limited v Fabrication & Pipe Services Limited [2021] NZHC 2032
- Case
- [2021] NZHC 2032
- Decision Date
CaseChat Overview and Summary
The court considered the principles for awarding costs, particularly focusing on the circumstances where a party fails to act reasonably, which could justify an increased costs award. The court found that GGE's application for summary judgment was unreasonable, given that FPS had clearly outlined the factual dispute and the basis for denying liability well before the proceedings began. The court also noted that GGE did not adequately address the terms of trade which were crucial to FPS’s defence. The court determined that FPS was entitled to a 50 per cent uplift on the base scale figure, resulting in a total costs award of $28,373.04, along with disbursements of $38.00.
Associate Judge P J Andrew concluded that while GGE's conduct warranted an increased costs award, it did not meet the threshold for an indemnity costs award. Consequently, GGE was ordered to pay $28,373.04 in costs to FPS, together with the disbursements. This decision underscored the importance of reasonable conduct in litigation and the consequences of pursuing unsuitable claims.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.