IN THE HIGH COURT OF NEW ZEALAND NELSON REGISTRY
CIV 2016-442-000072 [2017] NZHC 1376
BETWEEN FIORDLAND DISCOVERY LIMITED
Applicant
AND
CHALLENGE MARINE LIMITED Respondent
Hearing: 13 June 2017 Counsel:
S P Pope for Applicant
P Michalik and G C Engelbrecht for RespondentJudgment:
21 June 2017
JUDGMENT OF SIMON FRANCE J
[1] The respondent (Challenge) agreed to build a boat for the applicant (Fiordland). It was a fixed price contract with the possibility of variations. Disputes arose as to variations being sought and the matter went to arbitration. The parties identified 15 disputed variations out of a much larger number that would go forward to an urgent arbitration.
[2] The arbitrator issued what was titled an Interim Award (the Award).1 That award analysed the disputes in relation to each variation and identified a figure Challenge was entitled to as regards that item of work. The Award concluded in these terms:2
163The amounts I award for each of Challenge’s claims are: Variation claim 54 – aluminium alloy: nil
Variation claim 15 – …
1 Challenge Marine Ltd v Fiordland Discovery Ltd (Interim Award) Rodney Hansen QC,
9 August 2016.
2 At [163]–[165].
164The credits to be allowed to Fiordland in respect of materials and equipment supplied or paid for by Fiordland are as follows: Electronics system …
165I reserve leave to the parties to apply for any further directions required by or arising out of this award, as to the future conduct of
the proceeding and as to costs which are reserved.
[3] Fiordland applied for further orders pursuant to paragraph [165] of the
Award. These concerned:
(a) the amount of credit to be given Fiordland in relation to variations 15 and 16 (both being variations dealt with in the arbitration);
(b)three other pleaded credits that were not dealt with in the interim award; and
(c) the final figure Challenge was required to pay Fiordland.
[4] Challenge objected, particularly as regards the latter two of these. It submitted that the three pleaded credits, because they were not attached to any of the
15 variations, were outside the scope of the arbitration. It also submitted it was not part of the arbitration that the arbitrator would direct payment of the outcome, whoever it favoured. The purpose of the arbitration was only to identify the figure.
[5] A Ruling of Arbitrator (the Ruling) was issued on 19 September 2016 which
discussed but rejected Challenge’s objections.3 The Ruling concluded:4
14. In my view the balance over that sum is also payable to Fiordland.
As at the time of the interim award, Fiordland had paid Challenge more than it was liable to pay. Unless the contract provides otherwise – which is not suggested – there is a right to immediate repayment. A debt arises which is payable on demand unless the parties have agreed otherwise. On that basis the full amount of the balance of $218,315.88 is due and payable.
15. This does not, of course, affect Challenge’s rights in relation to any
enforcement action…
Keep reading for free
Create a free CaseChat account to read Fiordland Discovery Limited v Challenge Marine Limited and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] NZHC 1376
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi