Fiordland Discovery Limited v Challenge Marine Limited

Link copied
Case Copied 15 min read

IN THE HIGH COURT OF NEW ZEALAND NELSON REGISTRY

CIV 2016-442-000072 [2017] NZHC 1376

BETWEEN

FIORDLAND DISCOVERY LIMITED

Applicant

AND

CHALLENGE MARINE LIMITED Respondent

Hearing: 13 June 2017

Counsel:

S P Pope for Applicant
P Michalik and G C Engelbrecht for Respondent

Judgment:

21 June 2017

JUDGMENT OF SIMON FRANCE J

[1]      The  respondent  (Challenge)  agreed  to  build  a  boat  for  the  applicant (Fiordland).  It was a fixed price contract with the possibility of variations.  Disputes arose as to variations being sought and the matter went to arbitration.  The parties identified 15 disputed variations out of a much larger number that would go forward to an urgent arbitration.

[2]      The arbitrator issued what was titled an Interim Award (the Award).1    That award analysed the disputes in relation to each variation and identified a figure Challenge was entitled to as regards that item of work.   The Award concluded in these terms:2

163The amounts I award for each of Challenge’s claims are: Variation claim 54 – aluminium alloy: nil

Variation claim 15 – …

1      Challenge  Marine  Ltd  v  Fiordland  Discovery  Ltd  (Interim  Award)  Rodney  Hansen QC,

9 August 2016.

2      At [163]–[165].

164The credits to be allowed to Fiordland in respect of materials and equipment supplied or paid for by Fiordland are as follows: Electronics system …

165I reserve leave to the parties to apply for any further directions required by or arising out of this award, as to the future conduct of

the proceeding and as to costs which are reserved.

[3]      Fiordland  applied  for  further  orders  pursuant  to  paragraph [165]  of  the

Award. These concerned:

(a)       the amount of credit to be given Fiordland in relation to variations 15 and 16 (both being variations dealt with in the arbitration);

(b)three other pleaded credits that were not dealt with in the interim award; and

(c)       the final figure Challenge was required to pay Fiordland.

[4]      Challenge  objected,  particularly  as  regards  the  latter  two  of  these.    It submitted that the three pleaded credits, because they were not attached to any of the

15 variations, were outside the scope of the arbitration.  It also submitted it was not part  of the arbitration  that  the arbitrator  would  direct  payment  of the  outcome, whoever it favoured. The purpose of the arbitration was only to identify the figure.

[5]      A Ruling of Arbitrator (the Ruling) was issued on 19 September 2016 which

discussed but rejected Challenge’s objections.3  The Ruling concluded:4

14.      In my view the balance over that sum is also payable to Fiordland.

As at the time of the interim award, Fiordland had paid Challenge more  than  it  was  liable  to  pay.    Unless  the  contract  provides otherwise – which is not suggested – there is a right to immediate repayment.   A debt arises which is payable on demand unless the parties have agreed otherwise.  On that basis the full amount of the balance of $218,315.88 is due and payable.

15.      This does not, of course, affect Challenge’s rights in relation to any

enforcement action…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Fiordland Discovery Limited v Challenge Marine Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2017] NZHC 1376
Decision Date

CaseChat Overview and Summary

Fiordland Discovery Limited and Challenge Marine Limited were parties to a contract for the construction of a boat. Disputes arose concerning variations to the contract, and the matter proceeded to arbitration. An Interim Award was issued, which determined the amounts Challenge was entitled to in relation to 15 specific variations. Fiordland applied for further orders concerning credits they were owed in relation to variations 15 and 16, three other pleaded credits, and the final figure Challenge was required to pay Fiordland. Challenge objected, contending that the purpose of the arbitration was only to identify the figure and not to direct payment of the outcome. Fiordland applied for recognition and enforcement of a Ruling of the Arbitrator, which rejected Challenge’s objections and concluded that Fiordland was owed $218,315.88. Challenge opposed Fiordland’s application and filed an application for an Order Refusing Recognition and Enforcement of the Arbitrator’s Award. The court had to decide whether the Ruling was an arbitral award, whether it was made on a matter not submitted to the arbitrator for determination, and whether recognition of the award would be contrary to public policy. The court found that the Ruling was an arbitral award as it was in writing, signed by the arbitrator, and met the formal requirements of an award. The court also found that the matter of payment was within the scope of the arbitration and that the three credits awarded to Fiordland were not outside the scope of the arbitration. Finally, the court found that recognition of the award would not be contrary to public policy as the award resolved the disputes in an orthodox manner and the parties chose to submit only part of their dispute to arbitration. The application by Fiordland for recognition and enforcement of the award was granted, and the application by Challenge for an order declining recognition and enforcement of that award was declined. Fiordland was entitled to costs on a 2B basis, together with reasonable disbursements to be fixed by the Registrar if necessary.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established