Fiordland Discovery Limited v Challenge Marine Limited

Case

[2017] NZHC 1376

21 June 2017

No judgment structure available for this case.

IN THE HIGH COURT OF NEW ZEALAND NELSON REGISTRY

CIV 2016-442-000072 [2017] NZHC 1376

BETWEEN

FIORDLAND DISCOVERY LIMITED

Applicant

AND

CHALLENGE MARINE LIMITED Respondent

Hearing: 13 June 2017

Counsel:

S P Pope for Applicant
P Michalik and G C Engelbrecht for Respondent

Judgment:

21 June 2017

JUDGMENT OF SIMON FRANCE J

[1]      The  respondent  (Challenge)  agreed  to  build  a  boat  for  the  applicant (Fiordland).  It was a fixed price contract with the possibility of variations.  Disputes arose as to variations being sought and the matter went to arbitration.  The parties identified 15 disputed variations out of a much larger number that would go forward to an urgent arbitration.

[2]      The arbitrator issued what was titled an Interim Award (the Award).1    That award analysed the disputes in relation to each variation and identified a figure Challenge was entitled to as regards that item of work.   The Award concluded in these terms:2

163The amounts I award for each of Challenge’s claims are: Variation claim 54 – aluminium alloy: nil

Variation claim 15 – …

1      Challenge  Marine  Ltd  v  Fiordland  Discovery  Ltd  (Interim  Award)  Rodney  Hansen QC,

9 August 2016.

2      At [163]–[165].

164The credits to be allowed to Fiordland in respect of materials and equipment supplied or paid for by Fiordland are as follows: Electronics system …

165I reserve leave to the parties to apply for any further directions required by or arising out of this award, as to the future conduct of

the proceeding and as to costs which are reserved.

[3]      Fiordland  applied  for  further  orders  pursuant  to  paragraph [165]  of  the

Award. These concerned:

(a)       the amount of credit to be given Fiordland in relation to variations 15 and 16 (both being variations dealt with in the arbitration);

(b)three other pleaded credits that were not dealt with in the interim award; and

(c)       the final figure Challenge was required to pay Fiordland.

[4]      Challenge  objected,  particularly  as  regards  the  latter  two  of  these.    It submitted that the three pleaded credits, because they were not attached to any of the

15 variations, were outside the scope of the arbitration.  It also submitted it was not part  of the arbitration  that  the arbitrator  would  direct  payment  of the  outcome, whoever it favoured. The purpose of the arbitration was only to identify the figure.

[5]      A Ruling of Arbitrator (the Ruling) was issued on 19 September 2016 which

discussed but rejected Challenge’s objections.3  The Ruling concluded:4

14.      In my view the balance over that sum is also payable to Fiordland.

As at the time of the interim award, Fiordland had paid Challenge more  than  it  was  liable  to  pay.    Unless  the  contract  provides otherwise – which is not suggested – there is a right to immediate repayment.   A debt arises which is payable on demand unless the parties have agreed otherwise.  On that basis the full amount of the balance of $218,315.88 is due and payable.

15.      This does not, of course, affect Challenge’s rights in relation to any

enforcement action that Fiordland may take.

3      Challenge Marine Ltd v Fiordland Discovery Ltd (Ruling of Arbitrator) Rodney Hansen QC,

19 September 2016.

4      At [14]–[15].

[6]      In reliance on art 35 of Sch 1 of the Arbitration Act 1996, Fiordland have applied  for  recognition  and  enforcement  of  the  Ruling  as  an  arbitral  award. Challenge oppose, and have filed an application for an Order Refusing Recognition and Enforcement of Arbitrator’s Award.  It is submitted:

(a)       the Ruling is not an award;

(b)the Ruling is made on a matter not submitted to the arbitrator for determination;

(c)       the application by Fiordland is an abuse of process and recognition of the award would be contrary to public policy.

[7]      This judgment addresses the competing applications.

Issue one – the scope of the arbitration

[8]      It is convenient first to address Challenge’s proposition that the purpose of the arbitration was not to produce a figure that would become payable at the time of the Interim Award.  It submits that the arbitrator’s role was to identify that figure – limited to the 15 variations – but to leave it at that.

[9]      Mr Michalik  submits  there  is  unfairness  in  making  the  Award  figure immediately payable  as  excluded from the arbitration were  numerous  variations which will result in money owing to Challenge.   The practice to date under the contract had been to issue credit notes when such a situation arose, and that is consistent with Challenge’s position on the intended scope of the arbitration.

[10]     There is little in the documentation to support this proposition.  Mr Michalik relies primarily on the pleadings where there is no specific request for such an outcome.  Reflecting this, in the Ruling the arbitrator acknowledges that “timing of payment” was not specifically put in issue for the purpose of the interim award.5

However,  he  concluded  it  was  part  of  the  arbitration  and  made  the  direction.

5      Ruling of Arbitrator, above n 3, at [12].

Mr Michalik submits in the absence of an express request, a direction as to payment is outside the scope of the arbitration.

[11]     The starting point is the pleadings.  When the parties agreed upon a reduced urgent hearing, each side drafted documents specific to that reduced hearing. Challenge drafted a “Claimant’s Points of Claim”.   It provided 14 paragraphs of background narrative and then stated:

Pursuant  to  the  submission  to  arbitration  contained  in  clause 13  of  the Agreement,  the  parties  have  agreed  to  refer  15  of Challenge’s  variation claims to arbitration, without prejudice to Challenge’s right to pursue its claim for  the  balance  of  the  variations  and  damages  in  the  future  in  a resumed or new arbitration.

[12]     There is nothing in this paragraph to suggest the type of limitation now being advanced by Challenge.   It contemplates the arbitration may not continue or there may be a new one.  This is consistent with the standard position that the arbitration will resolve the situation as regards the matters submitted.

[13]     At the conclusion of its pleading, Challenge concluded with a prayer for relief being:

(a)       damages in the sums particularised in the pleading, less any monies already paid by Fiordland in respect of the 15 variation claims;

(b)      interest on the net sum payable to Challenge by Fiordland; and

(c)      costs.

[14]     None of this is consistent with Challenge’s present position.   Not only are damages sought, but also “interest on the net sum payable”.   This plainly contemplates the type of order that the arbitrator has directed.  It is not clear what specific pleading might be needed to make it clear the arbitrator was to make an award of money.  Normally a claim for damages is taken as being exactly that.

[15]     Fiordland replied with “Respondent’s Points of Defence and Counterclaim”. In responding to the 14 paragraphs of narrative, Fiordland specifically identified a series of payments it had made that it wished to be taken into account.  There were two groups of payments – agreed items of credit where Fiordland said it had not received all that was due to it, and other items it said had not been credited at all but should have been.  Not all these credits were connected to the 15 variations.

[16]     Fiordland also added six counterclaims.  Challenge objected to these as being outside the scope of the arbitration.   The arbitrator issued a ruling agreeing with Challenge  and  withdrawing  the  six  counterclaims  from  the  arbitration.6    That decision  can  be  read  as  relating  only to  the six  specific counterclaims  that  are pleaded at the end of Fiordland’s document.   It does not apply to the pleading of credits contained in the body of the pleading.

[17]     Challenge filed a “Points in Reply”.   It contended the counterclaims were outside the scope of the arbitration.  It did not, however, challenge the inclusion by Fiordland of the claim for credits.

[18]     In my view the pleadings are sufficient to dispose of Challenge’s contention. They point to a contrary position, namely that an award of an actual amount was expected, together with interest payable on it. The pleading is not consistent with the idea that all the arbitrator was doing was producing a running balance type figure.

[19]     If more be needed, it can be found in a side agreement reached between the parties prior to the arbitration.  It concerned one of the items that was the subject of dispute.  Fiordland agreed to advance the money for its purchase but on conditions which Challenge agreed to.  Of particular relevance is this provision:7

(h)       The parties agree to the principle that, depending on the arbitrator’s determination of Variation Claim 15, any amounts ordered by the arbitrator to be paid in relation to the interim arbitration as a whole shall be adjusted to take into account some or all of the funds paid by Fiordland (or such lessor amount if there has been any surplus repaid to Fiordland from Glasgow Harley under (a) above).   For example, if Challenge is successful in relation to all its claim for

6      Challenge Marine Ltd v Fiordland Discovery Ltd (Ruling of Arbitrator as to scope of Interim

Hearing) Rodney Hansen QC, 4 July 2016.

7      Ruling of Arbitrator, above n 3, at [12], emphasis added.

Variation Claim 15, then it will owe Fiordland NZD$56,949.93 (ie

$132,716.90, the total amount of Challenge’s claim for Variation

Claim 15 in the arbitration, less the $123,313.10 that Fiordland paid under this agreement and the $66,353.73 that Fiordland paid to Challenge in November 2015).

[20]     The arbitrator referred to this agreement in his ruling dismissing Challenge’s argument about whether he could direct payment.  As highlighted, the passage refers to  “any amounts  ordered  by the arbitrator  to  be paid  in  relation  to the interim arbitration”.  This is again consistent with the proposition that the arbitrator was to direct payment of a final figure in relation to the arbitration.  Mr Michalik notes that in the example immediately following, the term “owes” is used, but that does not in my view detract from the overall meaning of the passage.

[21]     As noted at the beginning of this discussion, there is objectively nothing that supports   Challenge’s   position.     It   is   a  counter-intuitive  proposition   that   is unsupported  by  documentation  and  which  runs  contrary  to  the  parties  own documents.   I accordingly conclude that a direction that money be immediately payable was not outside the scope of the arbitration.

Issue two – the credits

[22]     Challenge also contends that three of the credits awarded to Fiordland were outside   the   scope   of   the   arbitration   because   they  are   unconnected   to   the

15 variations.  In response to this, the arbitrator observed the credits were pleaded in the statement of defence, were covered in evidence by both parties, and were addressed in closing submissions.8   Nothing more need be said.

Issue three – the Fiordland’s application to register and enforce the award

Is it an arbitral award?

[23]     The  document  is  entitled  a  “Ruling”.     It  otherwise  meets  the  formal requirements of an award.9    It is in writing and is signed by the arbitrator; it states the date and place of the arbitration; it states its reasons, and I understand a signed

copy has been delivered to each party.

8      Ruling of Arbitrator, above n 3, at [7].

9      Article 31 of Schedule 1 of the Arbitration Act 1996.

[24]     Mr Michalik’s objections on behalf of Challenge are that the Ruling is not final, and it is on matters not submitted to the arbitrator.  I have addressed the latter issue already.

[25]     Concerning it not being final, it is well established an award can be interim in the sense of not resolving the whole dispute between the parties.  The definition of “award” in s 2 of the Arbitration Act makes that plain.  As I understand Challenge’s point, it is more a reference to the fact that the figure identified is not a final figure as between the parties.  It is the final figure on those 15 variations, but there are many more credits and debits to be determined.

[26]     Mr Michalik calls in aid two English decisions from the Queen’s Bench.  The first is Charles M Willie and Co (Shipping) Ltd v Ocean Laser Shipping Ltd (“the Smaro”).10     The issue there was when an arbitrator might revisit a decision, or alternatively whether the arbitrator was functus officio.   Rix J held that a decision which  could  be  revisited  was  one  which  concerns  changing  circumstances.11

Examples  were  timetabling  decisions  or  decisions  not  to  permit  amendment. Mr Michalik likens the present case to this since the balance owing between the parties will likewise be constantly shifting.   Accordingly, the arbitrator’s decision cannot be seen as finally dispositive of the issues, and so cannot be recognised.

[27]     The  second  decision  is  Enterprise  Insurance  Company  PLC  v  U-Drive Solutions (Gibraltar) Limited.12     It similarly holds that procedural rulings by an Arbitrator are not awards capable of qualifying for recognition and enforcement by the High Court because they lack finality.13

[28]     Although not doubting any of the principles in either case, I do not consider either has relevance to the present case.  Enterprise Insurance concerned orders for security for costs, and for payment of the arbitrator’s fee.   The orders included

directions as to the dates by which these events were to occur.  At issue, in part, was

10     Charles M Willie and Co (Shipping) Ltd v Ocean Laser Shipping Ltd [1999] 1 Lloyd’s Law Rep

225 (QB).

11     At 248.

12     Enterprise Insurance Co Plc v U-Drive Solutions (Gibraltar) Ltd [2016] EWHC 1301 (QB).

13     At [38]–[39].

whether the arbitrator was bound by the timetable he had set, or whether he could revisit it. The issues were procedural in nature, and different from the present case.

[29]     The Smaro concerned the ability of the arbitrator to revisit a prior decision as to whether an amendment would be allowed.  Unsurprisingly it might be thought, the Court held the arbitrator could revisit such a decision if circumstances required it. There are no parallels in the Smaro to the present case.  The Ruling represents a final determination  which  will  settle  the  situation  between  the  parties  as  regards  the

15 variations, and the credits claimed by Fiordland.

[30]     The definition of award in the Arbitration Act is:14

a decision of the arbitral tribunal on the substance of the dispute and includes any interim, interlocutory or partial award.

[31]     The inclusion in the definition of reference to the substance of the dispute makes plain the distinction identified in the English cases between orders settling matters and procedural directions.  The present Ruling goes to the substance of the dispute and finally determines those matters.  Notwithstanding the fact it is termed a Ruling (and no point is taken on that), it is an arbitral award capable of recognition and enforcement.

Functus officio?

[32]     Challenge contends that the arbitration was at an end with the issuing of the initial Interim Award.  It is said that the Award determined all the matters at issue, namely the sums payable in relation to each variation.  It is noted the arbitrator heard no further evidence after this Award.

[33]     This submission is a variation on that already discussed concerning the scope of the arbitration.  It is plain from the text of the Interim Award that the arbitrator did not consider all matters had been addressed.  Paragraph [165] of the Award allows for requests for further directions arising out of the award.15   The arbitrator held that

as regards the three credits, they were matters pleaded, and on which evidence was

14     Arbitration Act 1996, s 2, emphasis added.

15     Cited in full at [2] of this judgment.

heard and submissions received.   They were therefore within the scope of the arbitration and had not been addressed in the Award.

[34]     In my view the Interim Award was not, and did not purport to be, the last word on the matters in issue before the arbitrator.  He was accordingly not functus officio.

[35]     Ms Pope  alternatively relied  on  art 33(3)  of  Sch 1  to  the Arbitration Act which provides:

(3)       Unless otherwise agreed by the parties, a party, with notice to the other party, may request, within 30 days of receipt of the award, the arbitral tribunal to make an additional award as to claims presented in the arbitral proceedings but omitted from the award. If the arbitral tribunal considers the request to be justified, it shall make the additional award within 60 days.

[36]     She submits, and I accept, that this provides authority for what occurred, there being matters omitted that were presented in the arbitral proceedings.

[37]     Article 33(5) requires that to be an award, any additional award made under art 33(3) must meet the formal requirements of an award under art 31.  That is met here.  Further, the parties were given full opportunity to make submissions.  The fact no further evidence was needed is supportive of the applicability of art 33(3).   It reinforces that the additional award flows from matters presented in the arbitral proceedings.

Contrary to public policy

[38]     Article 36 of Sch 1 sets out when a Court may decline to enforce an arbitral award.   Article 36(1)(a)(iii) deals with situations where the award is shown to be outside   the   terms   of   the   arbitration.      That   issue   has   been   addressed. Article 36(2)(b)(ii) provides further that the Court may decline the recognition or enforcement of the award if it would be contrary to public policy to do so. Article 36 represents  a  high  threshold  an  applicant  must  overcome  in  order  to  oppose

recognition and enforcement.16    Reflecting this, the public policy ground is to be given a narrow reading.17

[39]     Challenge’s  claim  that  recognition  of  the  19 September  award  would  be contrary to public policy is sourced in the proposition that it would be unfair because the Ruling only deals with part of the dispute between the parties, and it would prove a powerful tool in Fiordland’s hands.  The history between the parties is traversed, leading to a submission that there is a reasonable basis to consider the Ruling, if recognised, would be misused.

[40]     It  is  further  submitted that  allowing recognition  and  enforcement  of this partial award would threaten the continuation of the arbitration.  Support for this as a ground  to  refuse  recognition  is  said  to  be  found  in  Williams  and  Kawharu.18

However, the relevant passage refers to a situation where an overseas Court considered that a subpoena had been issued by a party to an arbitration in order to avoid compliance with an order of the arbitrator.   The subpoena was therefore an abuse of process.  The case, and the passage from the text, is of no relevance to the present proceeding.

[41]     Relevant, however, to the claim advanced by Challenge is a later observation in the text that a public policy consideration will rarely involve going behind the findings of the Tribunal.19   Contrary to that, Challenge here relies in part on what it says  is  generally an  unacceptable  approach  by Fiordland  to  the  contact  dispute between the parties.

[42]     I agree with counsel for Fiordland that the matters raised by Challenge fall a considerable distance short of legitimately engaging the public policy exception. The subject matter of the arbitration is routine, and the award resolves the disputes in an orthodox manner.  The parties chose to submit only part of their dispute to the

arbitrator.  It is unclear why allowing recognition and enforcement of the resulting

16     Hi-Gene Ltd v Swisher Hygiene Franchise Corp [2010] NZCA 359 (CA) at [20].

17     At [21], citing Amaltal Corp Ltd v Maruha (NZ) Corp Ltd [2004] 2 NZLR 614 (CA).

18     David  A  R  Williams  QC  and  Amokura  Kawharu  Williams  and  Kawharu  on  Arbitration

(LexisNexis, Wellington, 2011) at [3.9].

19     At [17.5.7].

award will prevent continuation of the arbitration concerning the balance of the dispute.

[43]     The objection to Fiordland’s application on the basis that recognition of the award would be contrary to public policy is rejected.  For the avoidance of doubt, there  are  no  other  matters  that  might  engage  a  residual  discretion  to  refuse Fiordland’s application.

Conclusion

[44]     The application by Fiordland for recognition and enforcement of the award in the Ruling of 19 September 2016 is granted.  The application by Challenge for an order declining recognition and enforcement of that award is declined.

[45]     Challenge has not established any of the bases on which the Court may decline to recognise an arbitral award:

(a)       the Ruling of 19 September is an arbitral award;

(b)it resolves finally the substance of the dispute concerning the matters submitted to arbitration;

(c)       the parties chose to submit only part of their dispute to arbitration.

The  fact  that  there  are  other  unresolved  issues  does  not  prevent recognition of the award;

(d)the  award  addresses  only  matters  that  were  the  subject  of  the pleadings;

(e)      the Interim Award of 9 August did not finally determine matters.  The arbitrator  invited  applications  on  any  matters  arising  that  were required to finalise the dispute, and the 9 August Award omitted to consider matters that were part of the arbitration (the three credits). The arbitrator was not functus officio when issuing the further Ruling of 19 September 2016;

(f)       there  are  no  public  policy  reasons  which  mean  the  Court  should decline to recognise the arbitral award of 19 September 2016.

[46]     Fiordland  is  entitled  to  costs  on  a  2B  basis,  together  with  reasonable disbursements to be fixed by the Registrar if necessary.

Simon France J

Actions
Download as PDF Download as Word Document


Cases Citing This Decision

0

Cases Cited

1

Statutory Material Cited

0