Fenton v Building Code Consultants Limited HC Auckland CIV 2009-404-6348
[2010] NZHC 311
•15 March 2010
IN THE HIGH COURT OF NEW ZEALAND
AUCKLAND REGISTRY
CIV-2009-404-6348
IN THE MATTER OF an appeal of an adjudication of the
Weathertight Homes Tribunal at Auckland
BETWEEN BARRY FENTON, MARGARET FENTON AND MURRAY TANNER Appellants
ANDBUILDING CODE CONSULTANTS LIMITED, NIGEL HAILSTONE & OTHERS
Respondents
Hearing: 18 February 2010
Appearances: J M Holland for Appellants
J Stafford for Respondents
Judgment: 15 March 2010
JUDGMENT OF COOPER J
This judgment was delivered by Justice Cooper on
15 March 2010 at 11.30 a.m, pursuant to
r 11.5 of the High Court Rules
Registrar/Deputy Registrar
Date:
Solicitors:
Chambers Craig Jarvis, PO Box 47830, Auckland
Duncan Cotterill, PO Box 5326, Auckland
Copy to:
James Holland, PO Box 7204, Auckland
FENTON & ORS V BUILDING CODE CONSULTANTS LIMITED & ORS HC AK CIV-2009-404-6348 15
March 2010
[1] This is an appeal against a decision of the Weathertight Homes Tribunal (“the
Tribunal”) exercising its power to remove parties to adjudication proceedings under
s 112(1) of the Weathertight Homes Resolution Services Act 2006 (“the Act”).
[2] Section 93 of the Act gives a right of appeal to any party to a claim that has been “determined” by the Tribunal. The parties in this case proceeded on the basis that the Tribunal’s decision, subject to appeal, amounted to a determination of the claims against the parties removed. In Auckland City Council v Unit Owners in Stonemason Apartment 27 Falcon Street, Parnell & Others[1] Andrews J held that a decision to strike out a party is a determination of the claim in respect of that party. I agree.
[1] Auckland City Council v Unit Owners in Stonemason Apartment 27 Falcon Street, Parnell & Others HC Auckland CIV-2009-404-3118, 11 December 2009.
Background
[3] The appellants are the trustees of a family trust who have commenced a dwellinghouse claim under the Act, in respect of a property in St Mary’s Bay in Auckland. There were originally twelve respondents referred to in the statement of claim. They were said to have been responsible in various ways for defective building work and damage set out in a schedule to the claim. It was claimed that there has been moisture ingress as a result of errors and omissions by those responsible for the design and construction of the dwelling.
[4] In addition, it was alleged that the Auckland City Council acted negligently when it issued the building consent, and that a building certifier breached duties of care by failing adequately to inspect the building work and in issuing a code compliance certificate.
[5] Other respondents to the claim included former owners of the property from whom the appellants purchased it, pursuant to an agreement dated 17 February 2005
(“the agreement”) for the sum of $2,650,000. Clause 17 of the agreement stated:
The Purchaser acknowledges that there are weather tightness and other building issues with the property, and that he has received and read reports by Holloway Builders Limited (dated 16-4-03) and Building Code Consultants Limited (dated 10 February 2005). Accordingly the Vendor will on settlement date allow to the Purchaser a credit in the sum of $5,000.00 in full and final settlement of all claims which the Purchaser may otherwise have had against the Vendor howsoever or whensoever arising directly or indirectly out of the said weather tightness and other building issues.
[6] Under the clause were the handwritten words:
The purchaser, Barry Fenton confirms that this agreement is unconditional.
[7] One David Holloway was the eighth respondent to the claim and his company, Holloway Builders (Auckland) Ltd, the ninth. They had been engaged by the appellants’ predecessors in title in April 2003. They appellants claimed that the report produced by Mr Holloway was negligent in that it failed to identify the defects that were subsequently discovered.
[8] The statement of claim alleged that in February 2005 the appellants’ predecessors in title commissioned a further report, from Building Code Consultants Ltd (“BCCL”), named as the seventh respondent. The report in question was produced on 10 February 2005 (“the report”). Its author was Nigel Hailstone, the eleventh respondent, who was employed by BCCL as a building surveyor. Mr Hailstone was added to the claim by the Tribunal’s Procedural Order No.3 on 27 May 2009. The statement of claim alleged, against both BCCL and Mr Hailstone, that they knew or ought to have known that the report would be relied on by a prospective future owner of the property, and that therefore they owed a duty of care to such persons when inspecting and reporting on the property.
[9] The appellants allege in the statement of claim that BCCL and Mr Hailstone failed to identify “all or any” of the defects of the property. Further, they say that they entered into the agreement “in reliance, or partly in reliance” on the report and thereby suffered loss.
[10] Despite the allegations in the statement of claim, both parties have subsequently proceeded on the basis that the report was in fact commissioned by Mr Barry Fenton, one of the appellants. That was the basis on which the appellants
originally applied to join Mr Hailstone, and it was an assumption apparent in the reasoning of the Tribunal that made Procedural Order No.3. It was also assumed in both the application, made by BCCL and Mr Hailstone to be removed as parties, and in the opposition by the appellants to that application.
[11] It should be noted that two other respondents have been added to the claim,
as thirteenth and fourteenth respondents, while other respondents have variously become bankrupt, been placed in liquidation, or been struck off the Company’s Register. Others, including the Auckland City Council, have been removed by previous procedural orders of the Tribunal. Procedural Order No.8, which is the subject of the present appeal, struck out both BCCL and Mr Hailstone as parties to the proceeding. According to Mr Holland, that meant only five respondents remained.
Joinder application
[12] Before addressing the application made by BCCL and Mr Hailstone under
s 112, I mention briefly the appellants’ prior application for joinder. While BCCL
was initially named as a respondent, Mr Hailstone was only added as a consequence
of Procedural Order No.3. That order was made on 27 May 2009.
[13] The appellants had applied to join a number of additional parties by a memorandum dated 22 May 2009. Insofar as Mr Hailstone was concerned, the memorandum noted that he was the author of the BCCL report dated 10 February
2005 prepared for the appellants, and claimed that the appellants had made the agreement for sale and purchase unconditional after satisfying themselves of the matters contained in the report. It was asserted:
19The report misrepresented the degree to which the property was a leaky home. Whilst the report isolated some leaks on the northwest wall of the lower accommodation it failed to find water ingress to the upper areas of the building on all elevations.
20When questioned about the cost to remedy the building on or about the date of the report the author indicated to the claimants that the costs would be in the region of $20,000.
21 The report writer was negligent.
22 At all material times Hailstone and or Building Code Consultants
Limited knew or ought to have known that the Hailstone/BCC report to Fenton would be relied upon by them.
23Hailstone/BCC owed a duty of care to the Fentons as purchasers to exercise all reasonable care when inspecting and reporting upon the property.
24In breach of the said duty of care Hailstone failed to identify all or any of the defects with the property in the BCC/Hailstone report.
25The claimants entered into the agreement in reliance on or partly in reliance on the BCC/Hailstone report and thereby suffered loss in that the cost of remedying the damage is not less than $518,226.78.
26 The claimants accordingly seek orders joining Nigel Hailstone and
Building Code Consultants Limited as the 11th respondent.
[14] In deciding the joinder application, the Tribunal held that there was tenable evidence that the parties sought to be joined (including Mr Hailstone) had breached a duty of care, with a causative link to the remedial work required to be carried out on the property.
The application under s 112
[15] BCCL and Mr Hailstone’s application under s 112 of the Act followed on
28 July 2009. It was contained in a memorandum by counsel which noted that the report had raised a number of issues with the state of the dwelling, including instances of moisture ingress, unsatisfactory construction practices, water damage, rust and corrosion. The memorandum noted that the report had concluded with a number of recommendations including:
1The source of the water observed in the lower north west of the building is problematic. The presence of the concrete slab above suggests a masonry wall is behind the Titan board cladding. Should moisture be entering the wall from above this may explain why efflorescent type streaking is apparent on the outside wall and on the internal surfaces. …
10Where water has entered beside the sliding door there may be some damage to the framing. As elsewhere in the building where moisture has been noted, further investigation may be warranted to identify the presence and extent of any damage. Should fungally affected or damaged timber be found it should be moved and replaced with suitably treated timber. …
12The house itself is clad with materials that require ongoing scrutiny and maintenance. The plaster clad fibre cement board in particular
is susceptible to cracking which may allow water to damage framing behind. Any cracking should be dealt with as soon as it is noted. As
discussed by phone, the negative detail on the Titan board cladding may be filled with sealant to increase the weathering characteristics
of the building. As the house is some five years of age it will soon
require the repainting of the monolithic cladding elements. We would recommend that a hi-build acrylic such as Resene X-200 is used for this task. …
14Owing to the presence of monolithic cladding and of the likely presence of untreated timber, no guarantee can be provided in relation to the long term performance of the cladding and framing.
[16] The respondents’ memorandum refuted the pleading in the statement of claim that BCCL had been engaged by the appellants’ predecessors in title, and noted that
it had been engaged directly by Mr Barry Fenton. It recorded Mr Hailstone’s denial that he had made any representation regarding the estimate of the costs of remedying the defects in the BCCL report, as was alleged in para 20 of the appellants’ memorandum. Further, the respondents denied that they had breached any duty owed to the appellants noting that the report had identified areas of concern, and suggested further investigation of areas of potential moisture ingress. They pointed out that they had not been engaged to provide a comprehensive analysis of all potential issues, nor to undertake the invasive testing necessary to do so. The memorandum also disputed that Mr Hailstone could have personal liability as BCCL’s employee, there being nothing to indicate that he had assumed personal responsibility.
[17] The appellants’ memorandum was accompanied by an affidavit sworn by Mr Hailstone on 28 July 2009. He stated that he had been employed by BCCL as a building surveyor, a role in which he undertook pre-purchase property inspections
for prospective purchasers. These would typically be completed in one or two hours, and were limited to non-invasive surveys of buildings attempting to identify issues
of water ingress, maintenance requirements and safety issues. He never attempted to advise about the cost implications of issues that he noted; any inquiry about potential costs was met with the response that clients should ask contractors to price specific work. In this case, he had visited the property after arranging in advance to meet the land agent there. He carried out a visual inspection inside the dwelling and
surveyed its external surfaces including from the roof. He subsequently wrote the report. He could not recall meeting Mr Fenton during the inspection, nor could he recall any subsequent communication, but he accepted he had a conversation with him prior to writing the report in view of the content of paragraph 12 of the report’s recommendations. (“As discussed by phone … .”)
[18] At paragraph 14, Mr Hailstone recorded his surprise at the allegations in the appellants’ memorandum. He continued:
14.… As well as identifying corrosion, efflorescence and moisture in the walls of the lower floor (all indicating the failure of the structure
to adequately deal with water) I also found that “there is also
evidence of moisture ingress beside the sliding door in the south bedroom on the middle level” (p3 BCCL Report).
15.I also identified “What appears to be water damage is apparent on the ceiling of the master bedroom” (p2 BCCL Report). The master bedroom is on the top floor of the Property.
16.As well as the generic statement at the beginning of the BCCL Report, “The cladding has allowed moisture ingress in a number of areas”, five individual areas of concern are then identified on the upper, middle and lower floors of the Property.
[19] He observed at para 20:
20.The BCCL Report clearly sets out a number of areas of concern regarding water ingress. I do not accept that the BCCL Report misrepresented the degree to which the Property exhibited characteristics of a leaky home. Taking into account the fact that my investigation took between 1-2 hours and was visual only I believe that I identified all the main areas of concern visible at the time.
[20] He then refuted as untrue the allegation that had been made by the appellants that, when questioned about the cost of remedying the problems, he had referred to a figure in the region of $20,000. He was certain that he had not given any cost estimate. To do so would have been contrary to BCCL’s policy and outside his expertise. Even an experienced contractor could not have given such an estimate without further investigation to ascertain the scope of the works.
[21] Mr Holland filed a memorandum in opposition to the application for the appellants, but there was no affidavit responding to what Mr Hailstone had said in
his affidavit. In his memorandum, which was dated 21 August 2009, Mr Holland
discussed the law relating to striking out claims, submitting that, before that could occur, the Tribunal must be of the opinion that the pleaded causes of action were so untenable that the claim could not possibly succeed. He emphasised that the Tribunal must consider the application on the basis that the allegations pleaded by the appellants were correct. He noted Mr Hailstone’s denial that he had given advice
to Mr Fenton that costs of repair would be in the region of $20,000, but also noted that Mr Hailstone accepted he had a discussion with Mr Fenton prior to writing the report.
[22] Mr Holland observed that clause 17 of the agreement for sale and purchase of
17 February 2005 specifically recorded receipt of the report, and provided that the vendor would allow the purchasers a credit in the sum of $5,000 to settle claims the purchasers might otherwise have in relation to weathertightness and other building issues. Moreover, that claim had been preceded in negotiations by an earlier draft clause 17, providing:
17. The vendor and the purchaser agree to contribute equally up to a maximum amount of $20,000 ($10,000 each party) to remedy the issues outlined in the building inspection report for the property dated 10th February 2005 by Building Code Consultants Ltd described in Section “E” Recommendations and Conclusions.
All invoices shall be copied to both parties to ensure transparency for both parties.
[23] Mr Holland submitted in his memorandum that both the earlier version of clause 17 and that actually agreed showed the appellants had been concerned to be appraised of likely remediation costs before entering into the contract. Further, Mr Fenton must have understood that remedial costs would be in the region of $20,000 and possibly less, that he had intended to rely on the BCCL report when deciding to purchase the property and made the agreement unconditional only after the report was made available. Since the report predated the agreement, the last submission cannot be correct.
[24] The appellants contended that the report had inadequately covered the weathertightness issues, and coupled with the negligent estimate of repair costs given
by Mr Hailstone, both respondents would be liable if the appellants could sustain their factual allegations. BCCL would be liable in contract, Mr Hailstone in tort.
Mr Hailstone had assumed personal responsibility for the work he did and owed a duty to the appellants in undertaking those services. There was mention too of a claim under the Fair Trading Act 1986 in respect of the misrepresentation of likely costs of repair. Both the report and the misrepresentation had been influential in inducing the appellants to purchase the property. Consequently, it would be wrong for the Tribunal to grant the application.
The Tribunal’s decision
[25] The Tribunal recognised (at [39]) that strike out applications should be considered on the assumption that the facts pleaded in the statement of claim are correct. It also stated that before proceedings can be struck out causes of action must be so clearly untenable that they cannot proceed.
[26] At [37] the Tribunal discussed the range of factors it considered relevant in removal applications. The factors discussed included the likelihood of success against the party seeking removal, the nature and quality of the evidence as to liability for the leaks affecting the building (which it called the “tenability test”) and the relative significance of the allegations of breach of duty against the respondents in the context of the overall claim.
[27] The Tribunal discussed the submissions that had been made in support of the application and Mr Hailstone’s affidavit (at [40]-[44]) and noted (at [45]) that no evidence had been adduced in opposition to the application. In the ensuing discussions the Tribunal was plainly influenced by Mr Hailstone’s affidavit and the absence of evidence contradicting it. For example, at [47] the Tribunal referred to Mr Hailstone’s evidence that he did not express any opinion as to the cost of remedial work; at [50] it held that the investigation preliminary to the preparation of the report did not include invasive testing of the affected dwelling, and discussed other aspects of the report; and at [51] observed that:
The claimants have not established any evidential foundation for the contractual statutory or tortuous allegations set down in their submission.
[28] The Tribunal’s essential reasoning was then contained in [56] and [57]. Those paragraphs read as follows:
56. What is the likelihood of success of the claimants claim against
Building Code Consultants Limited and Mr Hailstone? On the basis
of the evidence outlined above it could only be described as extremely low. What was the nature and quality of the evidence indicating the company’s and Mr Hailstone’s liability, that is, the tenability test? The evidence is simply allegations and submissions, but opposed by sworn statements to the contrary. Accordingly the evidence is some what tenuous.
57.Taking into account all relative factors the Tribunal holds it is fair and appropriate in all the circumstances to remove the seventh respondent Building Code Consultants Limited and the eleventh respondent Nigel Vaughan Hailstone from this proceeding.
[29] The questions posed in [56] clearly reflected the range of factors held to be generally relevant at [37].
The appeal
[30] The appellants adopt the same stance on appeal as they did in opposing the application before the Tribunal. Mr Holland submitted that there was a genuine factual dispute as to whether Mr Hailstone told Mr Fenton that the costs to remedy the defects would be minor when in fact they were in excess of $500,000. That conflict could not be resolved on the papers, as the Tribunal had attempted to do. On the contrary, the Tribunal was bound to deal with the application on the basis that the facts pleaded by the appellants were correct, which it failed to do.
[31] Acknowledging that the appellants had not adduced evidence to rebut Mr Hailstone’s affidavit, Mr Holland argued that that was not necessary in the context of an application to strike out a claim. Evidence should only be necessary where a respondent is relying on a limitation defence or some other issue for which evidence is necessary. That was not the case here, where the appellants could essentially rely on their allegations. Mr Hailstone’s affidavit should not have been regarded as sufficiently compelling to be the basis of the Tribunal’s order under s 112 because it was no more than an untested denial by him of the facts on which the appellants rely.
[32] In response, Ms Stafford pointed out that the allegation that Mr Hailstone had advised the appellants that the cost to remedy the defects identified in the report would be in the region of $20,000 was not pleaded in the statement of claim. It arose
for the first time in the appellants’ memorandum of 22 May 2009 filed in support of the joinder application. Similarly, the further matters raised in Mr Holland’s memorandum opposing the present application were not mentioned in the statement
of claim. Ms Stafford also complained that none of the statement of claim, the application for joinder or the opposition for removal provided any detail as to when, where, how or to whom the alleged representation by Mr Hailstone was made.
[33] Ms Stafford submitted that although the principles to be applied when considering an application for removal under s 112 of the Act were similar to those which applied to strike out applications in the High and District Courts, the language
of the section, stating that a removal order can be made whenever the Tribunal considers it “fair and appropriate in all the circumstances” indicates that the powers are in fact broader. That broader power includes the ability to take into account affidavit evidence when considering factors relevant to the exercise of the Tribunal’s power. That approach is consistent with the stated purpose of the Act set out in s 3, namely to provide “access to speedy, flexible, and cost-effective procedures for assessment and resolution of claims…”. In this case, the Tribunal had legitimately taken into account the affidavit evidence of Mr Hailstone and had correctly concluded that there was not a tenable cause of action against either BCCL or Mr Hailstone.
[34] Ms Stafford emphasised that the report had identified areas of concern, suggested that they be further investigated and provided a general caution against the long-term performance of properties constructed using monolithic cladding and untreated timber. On the other hand, BCCL had not been engaged to provide a comprehensive analysis of all potential issues regarding the property nor was it instructed to undertake the invasive testing necessary in order to carry out such an investigation. In the circumstances, there was no evidence before the Tribunal to suggest that the respondents had failed to meet the requisite standard for the production of a pre-purchase report. Ms Stafford further submitted that there was no basis upon which the appellants could succeed in establishing personal liability of
Mr Hailstone, and that there was no causative link between the alleged representation by him as to the cost of remedial works and the actual cost of the work subsequently undertaken by the appellants, for which they now seek to be compensated. Even if he had made the representation, it could only ever have been
in respect of the items specifically identified in the report.
Discussion
[35] Section 112 of the Act provides:
112 Removal of party from proceedings
(1)The tribunal may, on the application of any party or on its own initiative, order that a person be struck out as a party to adjudication proceedings if the tribunal considers it fair and appropriate in all the circumstances to do so.
(2) This section is subject to section 57(2).
[36] Under s 57(1), the Tribunal has the obligation to manage adjudication proceedings in a manner that “tends best to ensure that they are speedy, flexible and cost-effective…”. Section 57(2), referred to in s 112(2), provides that in managing adjudication proceedings the Tribunal must comply with the principles of natural justice.
[37] When an application is made to the High Court for the striking out of a party
or a claim the Court exercises powers given to it under r 15.1 of the High Court Rules as well as, on occasion, the powers that it has under its inherent jurisdiction. Rule 15.1(1) of the High Court Rules provides:
15.1 Dismissing or staying all or part of proceeding
(1) The court may strike out all or part of a pleading if it—
(a)discloses no reasonably arguable cause of action, defence, or case appropriate to the nature of the pleading; or
(b) is likely to cause prejudice or delay; or
(c) is frivolous or vexatious; or
(d) is otherwise an abuse of the process of the court.
Rule 2.50.1 of the District Courts Rules is in a similar form to r 15.1(1) of the High Court Rules, but “embarrassment” has been added to paragraph (b) and paragraph (c) has been omitted.
[38] As can be seen, the power to strike out under r 15.1(1) arises in a range of circumstances. The power may be exercised not only where no reasonable cause of action or defence is disclosed by the pleading, but it can also be used where the pleading is likely to cause prejudice or delay (as where the pleading is unnecessarily
prolix as in Hill v Hunt David[2]) contains scandalous or irrelevant matter (Van der
[2] Hill v Hunt David (1884) 26 Ch D 470.
Kaap v Attorney-General[3]) or contains purely evidentiary, unintelligible or irrelevant material.[4] There is, in addition, the frivolous and vexatious ground (no longer applicable in the District Court), and abuse of the process of the Court. Collectively, these provisions enable the Court to respond to inappropriate proceedings or pleadings in a manner which advances the interests of justice and meets the overall objective of the High Court Rules set out in r 1.2:
[3] Van der Kaap v Attorney-General (1996) 10 PRNZ 162.
[4] See the cases referred to in McGechan on Procedure, para 15.1.03.
The objective of these rules is to secure the just, speedy, and inexpensive determination of any proceedings or interlocutory application.
[39] It may be observed that s 112 the Act does not use any of the language contained in r 15.1 of the Rules. That gives rise to the possibility that its broad reference to the power being exercised if the Tribunal considers it “fair and appropriate in all the circumstances” was intended to enable the Tribunal to range more widely than would be the case if it were a Court applying the High Court Rules or District Court Rules.
[40] Burns & Others v Argon Construction Ltd & Others[5]was an appeal against a decision of the Tribunal to strike out a claim under the Act. At [17], Asher J said that the general principles relating to strike out applications in the High Court and District Courts “can be applied”. He continued:
[5] Burns & Others v Argon Construction Ltd & Others HC Auckland CIV-2008-404-7316, 18 May 2009.
… There may be circumstances where a party chooses to rely solely on the “fair and appropriate” ground in s 112. That has not been the position taken by any of the parties in relation to this application. They have conducted the argument on strike out lines. I have no doubt that if an application should be struck out following an application of strike out principles, it will follow that it is “fair and appropriate” to strike out the relevant party. In Kay v Dickson Lonergan Limited & Ors HC AK CIV-2005-483-2001 31 May 2006, Ellen France J, in an application under the 2002 Weathertight Homes Act, which contained an equivalent provision to s 112 (at s 34), the application to strike out was considered in accordance with accepted strike out principles. I intend to proceed on this basis.
[41] Auckland City Council v Unit Owners in Stonemason Apartment 27 Falcon Street, Parnell & Others[6]was another appeal against an order made by the Tribunal under s 112 of the Act. Andrews J held at [23] that it is appropriate that the test to be applied to striking out a person as a party to adjudication proceedings under the Act should be the same as that applicable to strike outs under the High Court and District Court Rules. As she observed, the effect of striking out a person as a party under the Act will be that a claim against that person cannot be pursued in the Tribunal. The effect of a striking out under the High Court or District Court Rules is the same. Having referred also to a decision of the Tribunal in Cousins v Plaster Systems Limited[7]and to the decision of Ellen France J in Kay v Dickson Lanergan Ltd[8] Andrews J said at [30]:
[6] Auckland City Council v Unit Owners in Stonemason Apartment 27 Falcon Street, Parnell & Others, above n 1.
[7] Cousins v Plaster Systems Limited, Weathertight Homes Tribunal TRI-2008-107 Procedural Order 3, 23 January 2009.
[8] Kay v Dickson Lanergan Ltd HC Auckland CIV-2005-483-201, 31 May 2006.
[30] It can be accepted that the Tribunal’s power to strike out parties to
an adjudication proceeding is akin to that of the High Court and District
Courts, although arguably somewhat broader. Decisions under s 112 have not conclusively established whether it is wider in its scope. In the present case, despite setting out factors to be considered (consistent with applying a “wider scope” of a power to strike out) the Tribunal’s decision in fact addresses only the question whether there is a tenable claim (expressed as a “viable claim” in para 12). Thus, even if the broader interpretation were appropriate, the likelihood of success would remain the determinative factor. Accordingly, it is not necessary to express any conclusive view as to the scope of the test to be applied by the Tribunal.
[42] Notwithstanding those observations, in the case before her Andrews J
decided the appeal on the basis that the Tribunal had incorrectly stated the law when
it held that a party opposing an application for removal on the basis of disputed facts
must produce or point to some cogent evidence in support of their opposition. She held (at [32]) that the appropriate approach was to assume that the facts pleaded in the statement of claim are correct and that the relevant authorities did not support a proposition that the party opposing an application under s 112 must produce or point
to “cogent evidence”, or indeed any evidence, to support their opposition.
[43] I do not consider that the language of s 112 indicates that Parliament intended claims before the Tribunal to be struck out in circumstances where the same claim would not have been struck out in the ordinary Courts. It is to be noted that the provisions of the Act in a case such as the present apply only when a claim is brought under the Act in respect of a dwellinghouse and an application for adjudication may only be made in respect of an “eligible claim”, that is, one that has
been evaluated under s 48 or s 49 as meeting the eligibility criteria.[9] There is
[9] Sections 9 and 10.
nothing to oblige a person to bring a claim under the Act although it may be assumed that the streamlined procedures that it contains may well encourage persons with claims in relation to leaky buildings to do so. A claimant initiates the adjudication of the claim by applying to the Tribunal in writing to have the claim adjudicated and
serving a copy of that application on the other parties to the adjudication.[10]
[10] Section 62(1).
[44] The owner of a dwellinghouse may not apply for adjudication if the subject matter of the claim is already the subject of an arbitration that has commenced or proceedings that have been initiated by the claimant in proceedings in a Court or a Disputes Tribunal, or under s 177 of the Building Act 2004.[11] However, proceedings relating to a claim that have been commenced in the District or High Court may be transferred, by order of a Judge of the relevant Court, to adjudication under the Act. Such an order may be made if the parties to the proceedings agree or the Judge making the order believes that the transfer is in the best interests of justice.[12]
[11] Section 69(5). Section 177 of the Building Act concerns applications to the Chief Executive under that Act.
[12] Section 120.
[45] Consequently, while use of the Act’s provisions by claimants is not mandatory it is possible that a claim commenced in the ordinary Courts might become subject to adjudication under the Act. In the circumstances it seems inherently unlikely that the legislature intended that different strike out rules should apply according to which jurisdiction had been invoked.
[46] That conclusion is not contrary to the purpose of the Act, on which
Ms Stafford relied. Section 3 provides:
3 Purpose of this Act
The purpose of this Act is to provide owners of dwellinghouses that are leaky buildings with access to speedy, flexible, and cost-effective procedures for assessment and resolution of claims relating to those buildings.
[47] While there is no reference to ensuring the just resolution of claims, plainly that must be taken as a given. Given that there would be nothing to prevent the claimants in the present case from advancing their claim against BCCL and Mr Hailstone in the ordinary Courts, an interpretation of s 112 which places claimants and respondents in the same position as they would be in both jurisdictions
is more consonant with the purpose of the Act than one which would contemplate broader strike out powers being exercised by the Tribunal. A more frequent resort to strike out powers could only be contrary to the objective of providing cost effective procedures for the resolution of claims relating to leaky buildings. Moreover, dealing with applications under s 112 on a broader basis must inherently involve the risk that some meritorious claims will be foreclosed at the interlocutory stage.
[48] Ms Stafford referred to the judgment of Harrison J in Auckland City Council
v WHRS & Dennerly.[13] That was a decision on an application for review of a decision made by the Tribunal under the Weathertight Homes Resolution Services Act 2002, the predecessor of the present Act. The Tribunal had dismissed an application made by the Council to add five other parties to a claim to which it had
[13] Auckland City Council v WHRS & Dennerly HC Auckland CIV-2004-404-4407, 28 September
2004 at [28].
been named as the only respondent. Consequently, the case turned on s 33 of the
2002 Act which was the predecessor and equivalent to what is now s 111 of the 2006
Act. At [28] Harrison J said:
[28] A proposition that one or more of the other parties involved in the project may have owed and breached duties to the Dennerlys was insufficient to justify joinder. Council was bound to point the adjudicator to tenable evidence both of breach by the architects and of a causative link to the estimated costs of remedial work. A cursory evaluation of the assessor’s report indicates that less than 50% of the remedial expense might possibly be attributable to architectural negligence. Council’s failure to satisfy any of the statutory criteria through an analytical and reasoned argument before the adjudicator was fatal.
[49] It appears that those words have influenced the Tribunal to hold that in considering removal of a party under s 112 of the Act there must be “tenable evidence” from the claimant of a party’s alleged breach of duty, together with evidence of a causative link to the estimated costs of remedial work required. Certainly, that was what the Tribunal said in Cousins v Plaster Systems Ltd and Others,[14] at [13]. And, in the present case, the Tribunal appears to have taken the same approach when it set out (at [37]) the range of factors to be considered in removal applications, including “the nature and quality of the evidence as to the liability for the leaks in the building, that is the ‘tenability’ tests”. This approach was purportedly based on Auckland City Council v WHRS & Dennerly,[15] as well as observations made by Asher J in Kells v Auckland City Council & Others[16] that a number of the Act’s provisions illustrate that the approach to the joinder of parties under it is different to that in civil proceedings. It is this process of reasoning which led the Tribunal to look closely at Mr Hailstone’s affidavit in support of the s 112 application. Ms Stafford submitted that it was legitimate for the Tribunal to take that approach and to be influenced by the lack of any evidence from the appellants.
[14] Cousins v Plaster Systems Ltd and Others, above n 7.
[15] Auckland City council v WHRS & Dennerly, above n 13.
[16] Kells v Auckland City Council & Others CIV-2008-404-1812, 30 May 2008, at [33].
[50] However, an application for joinder under s 111 of the Act is different from
an application to strike out under s 112 and I do not consider that Harrison J’s decision in Auckland City Council v WHRS & Dennerly held or suggested to the
contrary. In the High Court it is recognised that there may be differences between
the approach required to strike out applications and joinder applications.[17] On a joinder application under the Act, the Tribunal has to decide whether or not the person sought to be joined ought to be bound by, or have the benefit of, an order of
[17] Kirkland v Jaco’s Timber Co. Ltd HC Dunedin CP45/97, 1 May 1998
the Tribunal, that his or her interests are affected by the proceedings or that for any other reason it is desirable that the person should be joined as a respondent. Different considerations apply under s 112 where the question before the Tribunal is whether a person should be struck out as a party.
[51] In my view, s 112 is not intended to give the Tribunal a wider jurisdiction to strike out claims than possessed by the High and District Courts. Where it is sought
to remove respondents on the basis that there is no reasonably arguable cause of action against them, I consider that the Tribunal should apply the same approach as that applied by the High and District Courts. That means that there is no duty on the claimant to adduce evidence directed to that question, because the question must be answered on the basis that the pleaded facts are correct.
[52] In Couch v Attorney-General,[18] Elias CJ delivering the judgment of herself and Anderson J said at [33]:
[18] Couch v Attorney-General [2008] 3 NZLR 725
[33] It is inappropriate to strike out a claim summarily unless the court can be certain that it cannot succeed. The case must be “so certainly or clearly bad” that it should be precluded from going forward.
[footnotes omitted]
[53] Reference can also be made to what was said in the Court of Appeal in
Attorney-General v Prince and Gardner.[19] In a well-known passage at 267
[19] Attorney-General v Prince and Gardner [1998] 1 NZLR 262.
Richardson P, delivering the judgment of himself, Thomas and Keith JJ said:
A striking-out application proceeds on the assumption that the facts pleaded
in the statement of claim are true. That is so even although they are not or may not be admitted. It is well settled that before the Court may strike out proceedings the causes of action must be so clearly untenable that they cannot possibly succeed (R Lucas & Son (Nelson Mail) Ltd v O'Brien [1978]
2 NZLR 289 at pp 294 – 295; Takaro Properties Ltd (in receivership) v
Rowling [1978] 2 NZLR 314 at pp 316 – 317); the jurisdiction is one to be exercised sparingly, and only in a clear case where the Court is satisfied it
.
has the requisite material (Gartside v Sheffield, Young & Ellis [1983] NZLR
37 at p 45; Electricity Corporation Ltd v Geotherm Energy Ltd [1992]
2 NZLR 641); but the fact that applications to strike out raise difficult questions of law, and require extensive argument does not exclude jurisdiction (Gartside v Sheffield, Young & Ellis).
[54] I consider that the same rules should apply in dealing with applications to strike out respondents under s 112 of the Act. In the present case, that gives rise to the difficulty from the appellant’s perspective that, as Ms Stafford pointed out, the facts on which the appellants now seek to rely are not those pleaded in the statement
of claim. Indeed the statement of claim contains pleadings which it appears the appellants now acknowledge are incorrect: in particular, the allegation that the report was prepared for their predecessors in title when it is plain from other material placed before the Tribunal and this Court, that the report was in fact prepared for the appellants, or at least for Mr Fenton.
[55] Further, while a general allegation of breach of duty of care is pleaded in the statement of claim (failure to identify all or any of the defects affecting the dwelling) against both BCCL and Mr Hailstone, the cause of action based on what Mr Hailstone is claimed to have said about the cost of repairs appears not in the statement of claim but in Mr Holland’s memoranda of 22 May and 21 August 2009.
It is only from those memoranda that the appellant’s full claim can be ascertained.
[56] Mr Holland attempted to justify this by suggesting that procedures adopted
by the Tribunal are informal in nature and that a strict view is not taken about pleadings. There is a certain irony about that stance, given the appellants’ insistence that the Tribunal should strictly mimic the approach of the High Court to strike out applications, and assume that the content of the statement of claim is correct. However, even where the pleadings are inadequate, the Court generally allows amendment to ensure that parties are not deprived of their right to pursue claims because of inadequacies in the pleadings that are able to be overcome. I consider that a similar approach should be taken here, and I observe that the Tribunal itself did not confine its consideration of the matter to what had been formally pleaded but considered all of the matters that had been put forward in the materials submitted to it by the appellants.
[57] It would not be appropriate to determine the present appeal on the basis that the appellants must be strictly confined to what they have pleaded in the statement of claim as it currently stands. Rather, I consider that the matter should be assessed on the assumption that the statement of claim can be appropriately amended to include matters such as those set out in Mr Holland’s memorandum of 22 May 2009, which I have quoted in [13] above. If the statement of claim were to be amended in that way, it would follow on the approach of the Supreme Court in Couch v Attorney-General[20]and of the Court of Appeal in Attorney-General v Prince and Gardner[21] that it should be assumed for present purposes that the appellants’ allegations are correct.
[20] Couch v Attorney-General, above n 18.
[21] Attorney-General v Prince and Gardner, above n 19.
[58] The consequence of that approach is that it was not appropriate for the Tribunal to decide that the appellants’ position was untenable on the basis of Mr Hailstone’s affidavit. Certainly that affidavit, if accepted as true, would mean that there were considerable hurdles which the appellants would have to overcome in order to establish a claim against either BCCL or Mr Hailstone. But much would turn on the content of the discussion between Mr Fenton and Mr Hailstone the detail of which, at present, Mr Hailstone does not recall. The appellants’ assertion that there was some discussion about cost may not be entirely without substance having regard to the wording of clause 17 of the agreement for sale and purchase, and the draft form of that clause. The differences between Mr Hailstone and Mr Fenton as to what in fact took place cannot properly be determined at a preliminary stage without the proper inquiry, which would occur at a substantive hearing.
[59] The broader question of whether the report was negligently prepared is also inherently one that should only be decided after all the relevant evidence is available.
At first glance there may well be merit in Ms Stafford’s observations about the limited nature of the exercise the respondents were asked to undertake for the purpose of preparing the report, and the implications of that for liability. Again, Mr Hailstone’s evidence, if accepted, may mean that the appellants cannot succeed.
But those issues will need to be explored at a substantive hearing and are inherently
unsuitable for determination under s 112. In my opinion, s 112 should not be treated
as if it were a power to give summary judgment to respondents, which is effectively what happened here.
Result
[60] For the reasons I have given the appeal is allowed and the orders made in the Tribunal’s Procedural Order No.8 insofar as they affect BCCL and Mr Hailstone are reversed under s 95(1)(a) of the Act.
[61] Under s 95(1)(b), this Court, in determining any appeal, may exercise any of the powers that could have been exercised by the Tribunal in relation to the claim. Such powers include the power, under s 73(1)(i), to do something that may reasonably be required to enable effective and complete determination of questions that have arisen and the power, under s 73(1)(l), to issue any other reasonable directions relating to the conduct of the proceedings.
[62] Under those powers there is a further procedural direction that should be made: the appellants must within 15 working days of the delivery of this judgment file an amended statement of claim that properly reflects the allegations it intends to pursue again BCCL and Mr Hailstone.
[63] In effect, the Court has granted an indulgence to the appellants in allowing the appeal while their pleading remains in its present unsatisfactory form. If the amended pleading is not filed it will be for the Tribunal to decide what further order might be appropriate. I consider that were the claim to persist in its present form that might justify a conclusion that the pleading was likely to cause prejudice and that it could be struck out on that ground. That of course is an issue which will be for the Tribunal to decide if the issue arises.
[64] The appellants have succeeded on the appeal, but they have done so on the basis of a pleading which is seriously deficient. In the circumstances, I do not consider that it will be appropriate for there to be an award of costs. Costs should lie where they fall.
0
0
1