Eltek Australia Pty Ltd v Firth

Link copied
Case Copied 34 min read

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY

CIV-2017-404-000241 [2017] NZHC 480

UNDER

The Judicature Amendment Act 1972 and

Part 30 of the High Court Rules 2009

IN THE MATTER OF

A decision made under the Construction
Contracts Act 2002

BETWEEN

ELTEK AUSTRALIA PTY LTD Applicant

AND

DEREK FIRTH First Respondent

HAWKINS CONSTRUCTION NI LIMITED

Second Respondent

Hearing: 15 March 2017

Appearances:

B D Gray QC and K Harkess for Applicant
First Respondent abiding the decision of the Court
G J Christie and D A Rowe for Second Respondent

Judgment:

16 March 2017

RESERVED JUDGMENT OF WYLIE J

This judgment was delivered by Justice Wylie

On 16 March 2017 at 4.30pm Pursuant to r 11.5 of the High Court Rules Registrar/Deputy Registrar

Date:…………………………

Solicitors/counsel:

B Gray QC/McElroys, Auckland

Simpson Grierson, Auckland

ELTEK AUSTRALIA PTY LTD v FIRTH [2017] NZHC 480 [16 March 2017]

Introduction

[1]      The applicant, Eltek Australia Pty Ltd (“Eltek”), seeks judicial review of a decision made by the first respondent, Mr Derek Firth, on 14 February 2017.  Mr Firth gave his decision as an adjudicator pursuant to the Construction Contracts Act

2002 (“the Act”).  He is abiding the decision of the Court.

[2]      Eltek  is  an  Australian  company.    In  September  2013,  it  entered  into  a subcontract with the second respondent – Hawkins Construction NI Limited (“Hawkins”).  There is a dispute between the parties arising out of the subcontract. It  contained an  arbitration  clause and  it  is common  ground that  any arbitration between the parties would be an international arbitration as defined in art 1(3) of the First Schedule to the Arbitration Act 1996.   Accordingly, the dispute between the parties  could  only  be  referred  to  adjudication  under  the  Act  if  both  parties

consented.1      Clause  13.2.1  of  the  subcontract  between  the  parties  provided  as

follows:

Disputes  may  be  dealt  with  by  adjudication  as  provided  for  in  the

Constructions Contract Act 2002.

Mr Firth  held  that  this  clause permitted  either  Eltek  or Hawkins  to  invoke the adjudication procedure set out in the Act, and that both parties had consented to adjudication when they entered into the subcontract.

Background

[3]      Eltek manufactures and supplies an electrical system known as the Eltek Power Train.  The Eltek Power Train provides emergency power when normal input power sources fail.  It is typically used to protect hardware such as computers, data centre equipment, telecommunications equipment and other electrical components from unexpected power disruption.

[4]      In  2013,  Hawkins  and  its  electrical  engineers  approached  Eltek.    They enquired about using the Eltek Power Train in a proposed data centre in Takanini that

Hawkins had contracted to deliver to a third party under a design and build contract.

1      Construction Contracts Act 2002, s 25(3).

[5]      Following a tender process, on 6 September 2013, Eltek entered into the subcontract with Hawkins.  Eltek agreed to design, manufacture, factory test, supply and install the Eltek Power Train system into the data centre.

[6]      The  data  centre  was  completed  and  the  Eltek  Power  Train  system  was installed.  However, in late 2014,…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Eltek Australia Pty Ltd v Firth and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2017] NZHC 480
Decision Date

CaseChat Overview and Summary

Eltek Australia Pty Ltd is an Australian company, and Hawkins Construction NI Limited is a New Zealand company. The two companies entered into a subcontract in September 2013, and there is a dispute between them. Eltek has sought judicial review of a decision made by Derek Firth, who was acting as an adjudicator under the Construction Contracts Act 2002. Firth decided that the subcontract permitted either Eltek or Hawkins to invoke the adjudication procedure set out in the Act, and that both parties had consented to adjudication when they entered into the subcontract. Eltek disputes Firth’s jurisdiction to determine the dispute between the parties. It has brought an application for judicial review, seeking a declaration that Firth does not have jurisdiction under the Act, and an order quashing or setting aside Firth’s decision. Hawkins denies that there was any error by Firth, and says that he exercised his powers in accordance with the relevant provisions in the Act. The court held that Firth did not err in his decision. Firth had set out the relevant contractual and statutory provisions, and had considered the submissions of both parties. The plain and ordinary meaning of the language used in clause 13, and in particular in clause 13.2.1, and the commercial and statutory context, led to the conclusion that the word “may” in clause 13.2 is both permissive, in the sense of allowing either party to invoke the adjudication process provided for by the Act, and consensual, in that it records in advance the parties consent to the use of that process, as required by s 25(3) of the Act. The application for review was declined.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.