| IN THE COURT OF APPEAL OF NEW ZEALAND I TE KŌTI PĪRA O AOTEAROA |
| CA218/2023 [2024] NZCA 212 |
| BETWEEN | ECTCH LIMITED |
| AND | DENNIS & LEO BRADY CONSTRUCTION LIMITED |
| Court: | Katz and Wylie JJ |
Counsel: | T J P Bowler for Applicant |
Judgment: | 4 June 2024 at 11.00 am |
JUDGMENT OF THE COURT
AThe application for an extension of time to file a case on appeal and apply for the allocation of a hearing date is granted. The case on appeal is to be filed within 20 working days of this judgment.
BThe application for an extension of time to pay the scheduling fee is granted. The scheduling fee is to be paid within 10 working days of this judgment.
CWe make no order as to costs.
REASONS OF THE COURT
(Given by Katz J)
Introduction
The applicant, ECTCH Ltd, seeks an extension of time under r 43(2) of the Court of Appeal (Civil) Rules 2005 (the Rules) to file a case on appeal. It also seeks an extension of time for payment of the required scheduling fee.
Background
ECTCH is a property developer. The respondent, Dennis & Leo Brady Construction Ltd (Brady Construction), is a construction contractor. ECTCH and Brady Construction are engaged in litigation over funds that Brady Construction is owed by ECTCH under a construction contract.
Brady Construction issued a statutory demand against ECTCH. ECTCH applied unsuccessfully to set aside that statutory demand on the basis that payment claims had not been validly served (the statutory demand judgment).[1] Having declined that application, Andrew J issued a separate judgment in which he awarded indemnity costs under s 23(2)(a)(ii) of the Construction Contracts Act 2002 to Brady Construction and ordered that ECTCH pay its debt by 28 April 2023. Andrew J further ordered that, if ECTCH failed to pay by that date, Brady Construction would be entitled to apply to put ECTCH into liquidation (the costs judgment).[2]
The application
ECTCH filed an appeal against the costs judgment in this Court on 27 April 2023, within the statutory timeframe. The deadline for filing a case on appeal and applying for a fixture was 27 July 2023. That day, counsel for ECTCH advised the Registry that a four-week extension to file the case on appeal was required. Counsel also sought an extension of time to pay the scheduling fee under r 5A of the Rules.
The Registry extended the time for filing the case on appeal and the application for a fixture by five working days under r 5A(1)(c)(ii) of the Rules (until 3 August 2023). In response to the request for a four-week extension, the Registry advised counsel that an application under r 43 of the Rules was required.
On 2 August 2023, an employee of counsel for ECTCH wrote to the Registry…
Keep reading for free
Create a free CaseChat account to read Ectch Limited v Dennis & Leo Brady Construction Limited and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] NZCA 212
- Decision Date
CaseChat Overview and Summary
The Court considered several factors in deciding the application, including the length of the delay, the reasons for the delay, and the potential prejudice to the respondent. The Court noted that the delay was modest and that the primary reason for the delay was counsel's oversight rather than any fault on the part of Ectch. While Brady Construction argued it had been significantly prejudiced by Ectch's delays, the Court found that further delay should not materially prejudice Brady Construction, given that no stay had been granted. The Court also observed that the merits of the appeal were not clearly hopeless, and the appeal raised significant issues for the parties involved.
In reaching its decision, the Court applied the principles set out in Almond v Read, emphasizing that the ultimate question was what the interests of justice required. The Court concluded that the interests of justice strongly favoured granting an extension, as it would be contrary to those interests for Ectch to lose its right of appeal due to a failure by its counsel. The Court granted the application for an extension of time to file the case on appeal and to pay the scheduling fee, with specific deadlines set for these actions. The Court made no order as to costs, considering that the respondent had not acted reasonably in opposing the extension application.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.