IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY

I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE

CIV-2017-404-2886 [2018] NZHC 966

BETWEEN

EAGLE FLIGHT TRAINING LIMITED

Applicant

AND

AEROSPACE INVEST PTE LIMITED

Respondent

Hearing: 1 May 2018

Appearances:

K M Wakelin and C Juneja for the Applicant L Ponniah for the Respondent

Judgment:

16 May 2018


CORRECTED AND RE-ISSUED JUDGMENT OF ASSOCIATE JUDGE SMITH


[1] On 7 May,  I gave a reserved judgment on an application  by the applicant  (Eagle) to set aside a statutory demand issued by the respondent (Aerospace). Counsel subsequently drew to my attention a computation error in the amount set out at paragraph [108] of that judgment1 for which the statutory demand was upheld. On 16 May 2018 I issued a Minute correcting the computation error under r 11.10 of the High Court Rules, and directing that the 10 working day period referred to in paragraph

[108] 2 of the judgment ran from the date of delivery of the judgment and would expire on 23 May 2018. The judgment is now re-issued, with the corrected figures inserted in (what is now) paragraph [109] 1 and 2.


1      The paragraph has become paragraph [109] in this corrected and re-issued judgment.

EAGLE FLIGHT TRAINING LIMITED v AEROSPACE INVEST PTE LIMITED [2018] NZHC 966 [16 May 2018]

[2]    On 22 November 2017, Aerospace served a statutory demand (the statutory demand), claiming the sum of $130,269.51 from Eagle. The amount demanded was said to be owing by Eagle to Aerospace under an agreement to lease an aircraft, entered into in July 2014 (the Aircraft Lease).

[3]    Eagle has applied under s 290 of the Companies Act 1993 (the Act) to set aside the demand. I now give judgment on that application.

Background

The parties

[4]    Eagle operates a business as a flight training school. Its sole director is Mr Alexander Zapisetskiy. Eagle’s shareholders are Aviation School of New Zealand Limited (ASNZ), a company of which Mr Zapisetskiy is the sole director, and a company called Leadtone Limited (Leadtone). ASNZ holds 63.25 percent of the Eagle shares, and the balance is held by Leadtone.

[5]    The sole director of Leadtone is Mr Igor Ivanov, and Mr Ivanov is the sole shareholder.

[6]    Eagle purchased the flight school business from the former owners in February or March 2010. On 26 February 2010, Mr Ivanov was appointed a director, and Mr Zapisetskiy became a director in May of 2010.

[7]    Mr Zapisetskiy and Mr Ivanov were friends as well as partners in the flight training school business, although for the reasons that will become apparent from this judgment they are no longer friends. Mr Ivanov was removed as a director of Eagle on 18 October 2017.

[8]    Aerospace is a Singapore-based company. Between 23 September 2015 and 3 March 2017, it was a shareholder in Leadtone. Its sole director is Dmitry Martynov,  a businessman who is a friend of Mr Ivanov.

The acquisition and lease of the Aircraft

[9]    Mr Ivanov and…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Eagle Flight Training Limited v Aerospace Invest Pte Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2018] NZHC 966
Decision Date

CaseChat Overview and Summary

In the High Court of New Zealand, Eagle Flight Training Limited (Eagle) sought to set aside a statutory demand issued by Aerospace Invest Pte Limited (Aerospace) claiming $130,269.51 for lease payments under an Aircraft Lease. Eagle contested the debt on several grounds, including a dispute over the calculation of flight hours and the existence of invoices. The court had to determine if there was a genuine and substantial dispute over the debt, whether Eagle had a counterclaim, and if the statutory demand was issued for improper purposes. The court found that while Eagle had a defence against $39,954.60 for the minimum flight hours and counterclaims totaling $25,281.12, there was no evidence of abuse of process by Aerospace. The statutory demand was set aside to the extent of the counterclaims, but upheld for the remaining balance of $65,033.79, with Eagle ordered to pay within 10 working days or face liquidation proceedings.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established