| IN THE COURT OF APPEAL OF NEW ZEALAND |
| CA438/2014 [2014] NZCA 536 |
| BETWEEN | DANONE ASIA PACIFIC HOLDINGS PTE LIMITED |
| NUTRICIA LIMITED Second Appellant | |
| DUMEX BABY FOODS CO LIMITED Third Appellant | |
| DANONE DUMEX (MALAYSIA) SDN BHD Fourth Appellant | |
| DUMEX LIMITED Fifth Appellant | |
| DANONE VIETNAM COMPANY LIMITED Sixth Appellant | |
| DANONE NUTRICIA EARLY LIFE NUTRITION (HONG KONG) LIMITED Seventh Appellant | |
| NUTRICIA AUSTRALIA PTY LIMITED Eighth Appellant | |
| AND | FONTERRA CO-OPERATIVE GROUP LIMITED |
| Hearing: | 15 October 2014 |
Court: | White, French and Cooper JJ |
Counsel: | D J Goddard QC and J H Stevens for Appellants |
Judgment: | 7 November 2014 at 12.00 pm |
JUDGMENT OF THE COURT
AThe appeal is dismissed.
BThe appellants are to pay the respondent’s costs for a standard appeal on a band A basis with usual disbursements. We certify for second counsel.
____________________________________________________________________
REASONS OF THE COURT
(Given by White J)
The appellants, collectively called Danone, have claims against the respondent (FCGL) and two of its wholly owned subsidiaries, Fonterra Ltd (Fonterra) and Fonterra Australia Pty Ltd, for damages for the manufacture and supply of nearly 2,000 metric tons of an alleged defective milk powder product (WPC80), an ingredient in Danome’s baby formula.
Danone issued this proceeding against FCGL in the High Court at Auckland on 9 January 2014. Danone seeks damages projected to exceed EUR 630,000,000 on the basis of four causes of action: breach of s 9 of the Fair Trading Act 1986 (FTA); breach of s 13 of the FTA; negligent misstatement; and “product liability”, in relation to the defective WPC80 which Danone claims was produced and supplied outside the scope of a Supply Agreement between the first appellant (Danone AP) and Fonterra (the Supply Agreement). Mr Goddard QC for Danone notes that the “product liability” cause of action is a novel one based on Body Corporate No 207624 v North Shore City Council [Spencer on Byron].[1]
Simultaneously with issuing this proceeding, Danone issued a notice of arbitration to the subsidiaries, under the Supply Agreement. Danone seeks similar damages under the Supply Agreement for breach of the Agreement in the manufacture and supply of the defective WPC80. In addition Danone alleges in its notice that the subsidiaries’ “conduct was tortious and violated applicable statutory law”.
As required by the terms of the Supply Agreement, the arbitration is to take place in Singapore and in accordance with English law. The parties accept that the claims in the High Court proceeding, including the claims under the FTA and for negligent misstatement, can properly be raised and determined in the arbitration. Fonterra concedes that the actions of the relevant FCGL employees are legally attributable to Fonterra. One of the issues in the arbitration will be whether Fonterra’s liability is limited to AUD 30,000,000 under the terms of the Supply Agreement.[2]
[2]Clause 14.5 of the agreement provides for…
Keep reading for free
Create a free CaseChat account to read Danone Asia Pacific Holdings Pte Ltd v Fonterra Co-operative... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2014] NZCA 536
- Decision Date
CaseChat Overview and Summary
The legal issues before the Court involved the discretionary power of the High Court to grant a temporary stay of proceedings pending the resolution of arbitration. Specifically, the Court needed to determine whether the High Court judge correctly exercised his discretion to stay the proceeding in favour of the arbitration and if the terms of the stay should be amended to require further steps by Fonterra in the High Court.
The Court of Appeal concluded that while the High Court judge had the power to grant the stay, the terms of the stay should not be amended to require Fonterra to take further steps in the High Court proceeding. The Court reasoned that the Singapore arbitration would inevitably be resolved before the High Court proceeding, and there was a real risk of injustice to Fonterra in being required to simultaneously defend two overlapping cases. The unnecessary duplication of proceedings would place an undue burden on Fonterra and its subsidiaries, especially when the arbitration might resolve all issues between the parties.
The Court dismissed the appeal and upheld the temporary stay, with the appellants ordered to pay the respondent's costs for the appeal. The decision underscored the principle that a party and its privies should not be twice vexed in the same matter, emphasising the importance of avoiding unnecessary duplication of legal proceedings.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi